Data Mining for the Management of Software Development Process

Álvarez Macías, José Luis; Mata Vázquez, Jacinto; Riquelme Santos, José Cristóbal

Abstract

In this paper we present a new method for the application of data mining tools on the management phase of software development process. Specifically, we describe two tools, the first one based on supervised learning, and the second one on unsupervised learning. The goal of this method is to induce a set of management rules that make easy the development process to the managers. Depending on how and to what is this method applied, it will permit an a priori analysis, a monitoring of the project or a post-mortem analysis

Full text

DATA MINING FOR THE MANAGEMENT OF SOFTWARE DEVELOPMENT PROCESS J.L. ´ ALVAREZ and J. MATA University of Huelva, Escuela Polit´enica Superior, La R´abida Huelva, 21071, Spain and J.C. RIQUELME University of Sevilla, Escuela T´ecnica Superior de Ing. Inform´atica, Avda. Reina Mercedes Sevilla, 41012, Spain Received (received date) Revised (revised date) Accepted (accepted date) In this paper we present a new method for the application of data mining tools on the management phase of software development process. Specifically, we describe two tools, the first one based on supervised learning, and the second one on unsupervised learning. The goal of this method is to induce a set of management rules that make easy the development process to the managers. Depending on how and to what is this method applied, it will permit an a priori analysis, a monitoring of the project or a post-mortem analysis. Keywords: Project Management; Software Metrics; Software Project Simulation; Data Mining. 1. Introduction In spite of its great diffusion in the last years, the application of data mining techniques to the field of software engineering has not been very much used, nevertheless, it is presented as a task that can offer great advantages and possibilities to this area. One of the possibilities in this respect, although not the only one, consists in the application of data mining techniques to databases on Software Development Projects (SDP). Thus, if we could have a database with the possible values of the initial parameters of a software project and the results at the end of the project, with regard to cost, time and quality for each one of these values, the data mining techniques could induce a set of rules that should permit to relate the initial parameters with the results of the project. It is obvious that this set of rules would offer to the project manager an extraordinary knowledge that would make easy both, the decisions to take in order to undertake new projects and the actions to realise in a development project or the analysis of an already finished project. 1 2International Journal of Software Engineering and Knowledge Engineering This idea has not arisen spontaneously, but as a necessity requested by the software engineering. All of us know the ”crisis” or chronic affliction, as it is described by Diehl [1], that has suffered the software development: a great amount of the undertaken software development projects has not fulfilled the initial expectations of delivery time, cost and quality. This situation is due, mainly, to the estimations or management policies that the manager of the project must carry out at the beginning of the project. Since the development of software projects began on a great scale, one of the main concerns for the managers has been to optimise the attributes that measure the viability of the final process. At the beginning, such task was not easy to carry out, since the manager himself was who, basing on his own experience, estimated the values where the attributes (management policies) that affect the development process had to move. The main problem in this case, lies in the amount of attributes that must be estimated, and besides, it is not enough to establish their values in an independent way, but it is also necessary to know the influence of ones on the others. With the incorporation of the simulation of the development process by dynamic models [2], a quite significant advance in the management of SDP was achieved, since these are simulated, without any risk, before undertaking the real project. Thus, the manager of the project decides the values for the attributes and simulates the process to verify its behaviour. Obviously, this means an improvement, but again, the amount of existing possibilities does not permit an exhaustive verification of the process. Data mining techniques can be used to solve this problem. In this case, the task of data mining techniques is to give the manager of the SDP a knowledge where to be based on. This knowledge helps the manager to estimate which are the most appropriate values, where the attributes that have an influence on the project must move, in order to obtain the desired values at the end of the project with regard to delivery time, cost and quality. It is necessary to emphasise that the application of data mining techniques to the software development process has an added problem that does not exist in other fields: the lack of real databases with information on the parameters that have conditioned the development of other software projects. Nowadays, such deficiency is solved thanks to the existence of powerful simulation systems and to the possibility of constructing dynamic models for the simulation of software projects. For that, the manager establishes the ranges for the doubtful attributes of the project, and by means of the simulator a database with the possible values for these parameters and with the result of the project (time, cost and quality) is generated. In this paper we offer a vision of the application of data mining techniques to SDP with the aim of giving to the manager a new method capable of providing a knowledge that will help him in the management of the project. This method will permit the manager, depending on its application, to have a priori information in the case of starting a new project, to have information for the following of a Data Mining for the Management of Software Development Process 3 project in progress or information for the evaluation and analysis of an already finished project. This project uses as SDP simulation model the one described in [3] and the tools GAR [4] for unsupervised learning and ELLIPSES [5] for supervised learning. Nowadays, similar works are using datamining tools for the induction of management rules for software development project [6]. Fig. 1. Knowledge Discovery in Database. 1.1. Process of Knowledge Discovery: Data Mining The knowledge discovery in database can be defined, in an informal way [7], as the non trivial process for the induction, departing from a set of data, of previously unknown, recent, potentially useful and understandable patterns (knowledge). As figure 1 shows, it is a process made up of several steps where data are selected, pre processed and transformed before we can discover the knowledge. Next, we offer a brief description of the goal to be covered in each step. Selection. It is the step where data that are object of interest are chosen departing from the data initially available. Pre-processed. Selected data are processed with the aim of removing noise (outliers) and of treating the absent values. Transformation. The pre-processed data are treated for the reduction of attributes or instances, fact that will make easy the application of the mining algorithm. Data Mining. This step takes the previously treated data and induces the set of patterns. Evaluation and Interpretation. The induced patterns are analysed by part of the experts with the aim of deducing useful knowledge. 4International Journal of Software Engineering and Knowledge Engineering Despite that all the steps have an important influence on the process, the data mining phase is, in our opinion, the most important within the whole process. In this phase, it is necessary to decide the task and the algorithm to employ on the data. There are two tasks of special interest in the mining step: classification and association. The aim of classification is to induce a set of rules that permits to predict, departing from a data set, the class of a future instance [8]. In a more accurate way, given a data set D(training set), composed by attributes X={x1, x2, ..., xd} and a class Ethat takes the discrete values e1, e2, ..., el, it has as goal to induce a classification model depending on the attributes x1, x2, ..., xd, that permits to assign a determined label e1, e2, ..., el, for the future instances, previously unknown with a certain degree of certainty. Even though the association concept is quite wide and includes different forms of representing and interpreting the knowledge (correlations, sequential patterns, negative associations, etc.), association rules has been the most outstanding ones within data mining. The aim of the mining association rules process consists, basically, in discovering if the presence of a set of pairs attribute-value that it is found in a determined number of records can be used to induce the presence of another set of pairs attribute-value in the same transactions [9]. In a more formal way, if X={x1, x2, ..., xd}is the set of all the attributes of a database D, an association rule is an implication C1* C2, where C1, C2⊆Xand C1∩C2= Ø . C1and C2 are respectively called antecedent and consequent of the rule and it is read ”if C1 then C2”. The probability of a given association rule to be fulfilled is known with the name of confidence. Besides this measure, that shows, up to a certain point, the importance of a rule, there is another one to indicate the covering of the rule, that is to say, the percentage of records in which the rule is fulfilled, and has the name of support. 2. Data Mining Techniques The selection of the algorithm or tool to be used in the data mining step is an essential element in such step. In this paper we use two tools that offer different visions of the knowledge we want to obtain. Thus, we use an association rule algorithm, named GAR [4] and a classification algorithm named ELLIPSES [5], both based on Evolutionary Algorithms [10]. In this paper we offer the details of each one of these algorithms, without studying in depth the implementation details. 2.1. GAR: Association Rules GAR is a algorithm that discovers association rules in databases that have numeric attributes. The core of the algorithm is an evolutionary process that is in charge of finding, in an automatic way, the most suitable intervals for each attribute Data Mining for the Management of Software Development Process 5 that forms part of the rule. This is the main advantage of this technique with regard to others, since it is not necessary to carry out a previous discretization of the continuous domains. if Xa∈[lai, las]and Xb∈[lbi, lbs]and ···and Xz∈[lzi, lzs] then Xk∈[lki, lks]and ···and Xj∈[lji, ljs](1) The model of rule we present has the format described in equation 1, where Xi are the attributes that form the rule and [li, ls] are the minimum and maximum values of the interval discovered by the algorithm. The fitness of a rule is determined by several factors: •Support. This parameter rewards rules with a high value of support. •Confidence. It is the other most used parameter to evaluate the quality of association rules together with support. Therefore, it is also a positive parameter that makes that the search process tend to find rules with high values of confidence. •Before covered cases (recov). It is used to indicate that an attribute of a record has previously been covered by a rule, that is to say, it belong to one of the rules discovered by the algorithm. With this, we get that the algorithm tend to discover different rules in later searches. •Number of attributes (natrib). Association rules with a high number of attributes give an information with more quality to the final user. But we are also aware that, in many cases, it is difficult to find rules with a high number of attributes or that the user is only interested in finding associations among a limited number of attributes. The parameter natrib rewards the number of attributes that has a rule. •Amplitude (ampl). This parameter controls the amplitude of the intervals of the attributes that form the rules. It is a negative parameter that penalises individuals with very wide intervals. Equation 2 shows how the fitness of a rule is obtained. F itness = (support ∗ws) + (confidence ∗wc)−(recov ∗wr)+ +(natrib ∗wn)−(ampl ∗wa)(2) Since, it is very difficult to establish some fixed values valid for the solving of all the problems, each parameter of the function is weighed up to increase or to decrease its effect. Besides of presenting the rule in the format ”if-then”, we offer a graphic representation by means of a parallel coordinate system [11] of each discovered rule. In this system only appear the attributes that form part of the rule. By means of this representation we show, in a graphic way, the intervals of the attributes, in such a way that a qualitative reading of the rule can be done. 6International Journal of Software Engineering and Knowledge Engineering 2.2. ELLIPSES: Classification Rules ELLIPSES is a classification system based on an evolutionary algorithm. The evolutionary process, iterated for each rule to be induced, has as goal function to find the best region in each iteration. The induced regions are elliptical spaces, within the search area, described by equation 3. (x1−c1)2 a2 1 +(x2−c2)2 a2 2 +... +(xd−cd)2 a2 d ≤1 (3) F itness =clasif −nclasif −recov ∗frc +vol (4) The fitness of a region is determined by the number of instances that exist inside it and by its volume (vol). As for the instances, we have to distinguish between the instances (success) of the majority class, established as class of the region (clasif), the instances (errors) of other class (nclasif) and the instances (before covered cases) of the class previously covered by other rules (recov). This last term can be weighted up (frc ∈[0,1]) by the expert, depending on its necessities with regard to the rules overlapping. If frc takes values near to one, the rule overlapping will be much lesser than if this takes values near to zero. In this way, the fitness of a region is determined by equation 4. if x1(c1, a1)and x2(c2, a2)and ··· and xd(cd, ad)then ei(5) h(xi, ai) =            Large if ai>40%Ax MLarge if 25%Ax< ai≤40%Ax Medium if 15%Ax< ai≤25%Ax MShort if 5%Ax< ai≤15%Ax Short if ai≤5%Ax (6) if x1(c1, E1)and x2(c2, E2)and ··· and xd(cd, En)then ei(7) The information is presented by two models of rules: quantitative and semiqualitative, and also by a graphic representation. The quantitative model is directly deduced from equation 3. Thus, a rule in the quantitative model will have the format described in equation 5, where ciand airepresent, respectively, the centre and the amplitude for attribute i ; and e1the class or majority label in the region. In the semi qualitative model, the information of the amplitude for each attribute is replaced by a label obtained depending on it, according to equation 6. In equation 7 we show the format of this model, where Eiare the labels which represent the amplitude. The graphic representation we offer, the same that in GAR, consists in a system of parallel coordinates for each rule. The difference is that the representation for ELLIPSES shows all the parameters of the model, and we can distinguish in it those that do not influence on the decision because they can take any value of their domain. Data Mining for the Management of Software Development Process 7 3. Software Engineering, Dynamic Systems and Data Mining A priori, the design of a method for the union of these three concepts can seem complex. But, the application of dynamic systems to SDP is something quite known and used since the early 90s. Simply, what we need is to incorporate the term ”data mining” to this formula. On the other hand, data mining is a task that is giving huge benefits in a countless amount of knowledge fields, so the fitness seems to be easy. And, so it is. With the pair dynamic systems and SDP we can get to obtain a data set that describes, depending on the initial parameters (input) of the project, how this evolves, according to its expected results of cost, time and quality. This database is the link and departing point for data mining. In the following sections we offer, in a more exhaustive way, the relation between this three concepts and we detail the influence of each one of them on the method proposed in this paper. 3.1. Dynamic Systems for Software Development Projects The software development process can be defined as a set of tools, methods and practices that are used to produce software. As any other organisation, those devoted to software development keep among their main aims the production of software according to the initial planning, besides a constant improvement, with the purpose of achieving the last three goals of any production process: high quality and low cost in the least time. The reduction of the software development cycle without risking the quality of the final product has became a basic goal. Not only for being an advantage from the point of view of the customer but for offering, according to [12], a series of important benefits among which we can emphasize : a larger commercial life of the product and the possibility of beginning to produce as later as possible ending within the limit, what permits to employ the last technological advances available at the moment. Most of the advances produced in the Software Engineering field, directed to the reduction of the development cycle, try to achieve their goals by a substantial improvement of the development technology employed. Such as it is assumed in the model CMM (Capability Maturity Model) of the SEI (Software Engineering Institute) and in the proposal of the norm ISO 9000. The CMM model classifies software development organizations on a scale from one to five resting on the maturity of the process that take place in them. According to [13] we can assure that as a software development organization progress from a level to the one immediately superior, the length of the development cycle diminish, always guaranteeing the quality of the final product. Traditionally, we have tried to face the known problem of the software crisis from the point of view of the development technology used. Thus, significant advances relating to the use of new methodologies and development approaches, CASE tools, 8International Journal of Software Engineering and Knowledge Engineering code reuse, etc, have been produced. At the beginning of the 90s, a significant leap in the management of software development projects is produced with the appearance of the first dynamic model applied to this field [2], which models the process carried out in the management of such projects. In the last years, a significant advance in the field of tools for project management and in the advice for the complex process of decision making has taking place, with the appearance of dynamic models for SDP and powerful simulation environment (Stella, Vensim, iThink, PowerSim, etc.). These tools have been called ”Software Project Simulators” (SPS), and allows the manager of the project to test with different management policies without cost, making easy the most adequate decision taking [14]. The making of dynamic models can constitute a formal methodology according to which we can express the knowledge on the system. Besides, the own model building process forces the researchers to have a high knowledge about which are the key parameters and how they are related among them. The potential of simulation models for the education and training of the project managers is stated in [1], [15],[3]. Thanks to the simulation environment, the managers can be placed in front of real situation they can find in practice and that permit them to acquire experience without risk. Besides, the formal character of the dynamic model allows the managers to share their viewpoints in a not ambiguous way and to harmonise the mental models of the process. Definitively, a software project simulator allows to carry out the following analyses: •An a priori analysis of the project: consisting in simulating the project before starting the development. These simulations can be carried out under different management policies and/or different estimations of initial resources and/or different development technologies. The knowledge of these management rules can be obtained before starting the project performance and it is going to guarantee the obtaining of good results for the variables that the project manager considers of interest (delivery time, cost, quality,...). Besides, the obtaining of management rules permits the manager to analyse which are the most significant management policies in order to achieve the initials goals defined in the SDP and to know if these policies can be applicable or not. •Monitoring of the project: simulation of the project during its development to adapt the realised estimation to its real evolution. For this application it is necessary to have a metric system that permits to pick up the real situation of the project and its comparison with the results of the simulation. •A post-mortem analysis of the project: simulation of an already finished project in order to know how the obtained results could have been improved. In other words, by means of the SPS we can answer questions such as ”What would happens if...?”, before beginning the project, ”What is happening..?”, during its development, and ”What would have happens if...?” once the project is finished. Data Mining for the Management of Software Development Process 9 Fig. 2. Classification of the attributes of a dynamic model for SDP. 3.2. Data Mining in Software Development Projects Once we have arrive at this point we can ask: Could be possible for the project manager to carry out all the possible situations and to analyse their results? The answer is no, unless the manager could spend all his life doing this. Thus, it is necessary an automatic mechanism able to induce some patterns that describe the behaviour of the project in a global way. In order to do that, we will use data mining together with dynamic models. Dynamic models for SDP include a set of attributes that allows us to define the management policies that can be applied to the projects, both those related to the project environment and those related to the development organization and the maturity level of the organization (see figure 2). Inside the group ”Project environment”, we insert the attributes related to the initial estimations of the project and to the complexity of the same. In the group named ”Organization environment”, appear the attributes related to the different management policies that can be applied to SDP and with the maturity degree of the own development organization. Within the subgroup ”Management policies” we collect the different parameters and tables (attributes) that define the management policies related to effort assignment , management policies related to personnel (hiring, dismissal, adaptation, etc .) and management policies related to restrictions on the project delivery time. On the other side, the subgroup ”Maturity degree”, fundamentally includes the attributes bound to the average time in which certain activities of the project are realised and the nominal values used. The subgroup ”Others...” contains the attributes related to the maturity degree of the organization 16 International Journal of Software Engineering and Knowledge Engineering The database CRCCRT has been generated imposing, in the simulation, restrictions on the attributes related to personnel hiring, making it to be fast, and, besides, imposing strong initial restrictions on the delivery time [16]. With the strategy followed in the generation of this database, we pretend to know the value of the attributes related to personnel management that permit to obtain good results for delivery time and to maintain acceptable levels in the project quality, independently of the value obtained for the necessary effort to carry out the project. 4.2.1. Cut 1: Restrictions on Time and Quality For this database, cut 1 induces a set of rules on the input attributes, only fulfilling restrictions on delivery time (TpoDllo) and quality (Quality), according to the cuts established in table 3. Results of GAR The association rules discovered by GAR, where the consequent is formed by the intervals of the variables T poDllo ∈[320,352] and Quality ∈[0,0.45], that is to say, the management rules that would have permitted to obtain good results simultaneously for delivery time and project quality, are the following ones: R1: If RmAnvos ∈[12.4,14.6] and RmCtrata ∈[6.7,9.3] and P mxRet ∈[1.10,1.18]. support = 7%, confidence = 91.3%, covered cases = 21, rc = 0. R2: If RmAnvos ∈[12.5,14.4] and RmCtrata ∈[7.6,9.9] and P mxRet ∈[1.11,1.19] and RmDesp ∈[5,7]. support = 3%, confidence = 100%, covered cases = 10, rc = 7. R3: If RmAnvos ∈[12.1,14.8] and ReCtrata ∈[6.9,9.7] and P mcRet ∈[1.11,1.17] and RmDesp ∈[7.9,9.6]. support = 3%, confidence = 90.91%, covered cases = 10, rc = 8. R4: If RmAnvos ∈[11.8,14.7] and ReCtrata ∈[9.1,9.9] and RmDesp ∈[6,9.3] support = 3%, confidence = 76.92%, covered cases = 10, rc = 8. The quantitative interpretation we can withdraw from the rules discovered by GAR is the following: the support indicates the number of cases (percentage) where the conjunction of values of the rules is produced. The confidence shows the percentage of cases that fulfil such conjunction and besides, fulfil the values of the consequent. Together with this information, we show the number of cases that fulfil the rule in a correct way (covered cases) and the number of cases that also belong to other rules (rc). This interpretation will be applicable to the rest of the examples that are shown next. In this particular case, rule R1 shows that 7% of the cases (21) fulfil the conjunction of values RmAnvos ∈[12.4,14.6], RmCtrata ∈[6.7,9.3] and P mxRet ∈ [1.10,1.18] with the correct consequent, that is to say, with the values of the variables within the range established by the manager. The confidence value of 91.3% shows that in the database there are 23 cases that fulfil the antecedent, but that 2 of them do not fulfil the consequent. Rule R2 shows that 3% of the cases(10) fulfil the antecedent and the consequent. Besides, a 100% of confidence for this rule, means Data Mining for the Management of Software Development Process 17 that all the cases (10) that fulfil the antecedent, also fulfil the consequent. We also want to show that 7 of the cases covered by this rule are also covered by other rules (rc = 7). In figure 5 we offer the graphic representation of these rules. We can check that the average delay in the incorporation of new technicians to the project and their adequacy, are attributes that appear in all the obtained rules. Such attributes take, in all of them, values from medium to high within the interval defined as fast personnel management. With regard to the obtained results, R1 would have been the easiest rule to be applied, since, although it has the same number of attributes than rule R4, we would have only to modify the values of RmAnvos yRmCtrata. Fig. 5. Results of GAR on CRCCRT database for cut 1. Results of ELLIPSES The management rules induced by ELLIPSES that show information about the results labeled as ’Good’ are the following (see figure 6): R1: (RmAvnos-11.9)/3.14+(RmCtrata-7.9)/1.57+(PmxRet-1.18)/0.02=1. Success = 10, Errors = 1, before covered cases = 0. R2: (RmAvnos-13.4)/1.65+(RmCtrata-9.3)/1.53+(PmxRet-1.12)/0.02=1. Success = 10, Errors = 1, Before covered cases= 0. R3: (RmAvnos-13.6)/1.01+(PmxRet-1.16)/0.03+(RmDesp-8.6)/1.17=1. Success = 5, Errors = 0, Before covered cases = 0. 18 International Journal of Software Engineering and Knowledge Engineering Fig. 6. Results of ELLIPSES on CRCCRT database for cut 1. In figure 6 we offer the graphic representation of these rules. The interpretation that can be followed from them would be: •Figure 6.R1): RmAnvos, defined in the interval [5,15], must take medium high values (center 11.9 with a margin of ±3.14), RmCtrata, defined in [5,10], must take medium high values but without reaching the limit (center 7.9 with a margin of ±1.57) and PmxRet, defined in [1,1.2], must take very high values (center 1.18 with a margin of ±0.02), practically at the limit. •Figure 6.R2): RmAnvos takes high values (center 13.4 with a margin of ± 1.65), RmCtrata takes high values (center 9.3 and a margin of ±1.53) and PmxRet takes medium high values (center 1.12 and margin ±0.02). •Figure 6.R3): RmAnvos must take high values without reaching the limit (center 13.6 with a margin of ±1.01), PmxRet must take high values, without reaching the edge (center 1.16 and margin of ±0.03) and RmDesp, defined in the interval [5,10], must take medium and high values, but without reaching the limit (center 8.6 and margin ±1.17). 4.2.2. Cut 2: Restrictions on Time and a High Quality Level Cut 2 for database CRCCRT induces a set of rules on the input attributes fulfilling the restrictions on the same variables, but being less permissive as for the average number of errors for task (Quality) (see table 3). We have to observe that, in this situation and for being a so restrictive policy, there is only 12 cases categorized as good. Results of GAR The association rules discovered by GAR, where the consequent is formed by the intervals of the variables T poDllo ∈[320,352] and Quality ∈[0,0.35], that is to say, the management rules that would have permitted to obtain good results for delivery time, demanding, besides, a high level of quality from the project, are the following ones: Data Mining for the Management of Software Development Process 19 R1: If RmAnvos ∈[13.1,13.8] and RmCtrata ∈[8.3,8.9] and P mxRet ∈[1.11,1.18] and RmDesp ∈[5,6.2]. Support = 1%, confidence = 100%, covered cases = 3, rc = 0. R2: If RmAnvos ∈[12.1,13.6] and RmCtrata ∈[8.5,9.2] and P mxRet ∈[1.17,1.18] and RmDesp ∈[5,6.1]. Support = 1%, confidence = 100%, covered cases = 3, rc = 1. R3: If RmAnvos ∈[12.7,14.1] and RmCtrata ∈[7.1,8.6] and P mxRet ∈[1.13,1.15] and RmDesp ∈[7.9,8.2]. Support = 1%, confidence = 100%, covered cases = 3, rc = 0. R4: If RmAnvos ∈[14.4,14.7] and RmCtrata ∈[9,9.8] and P mxRet ∈[1.02,1.10] and RmDesp ∈[6.1,8]. Support = 1%, confidence = 60%, covered cases = 3, rc = 1. Fig. 7. Results of GAR on CRCCRT database for cut 2. Figure 7 shows the graphic representation of these rules. With regard to the previous cut, we can check that in these rules appear all the attributes implied in the database, and besides, that the ranges are narrower, which implies that, in order to reach the desired goals in this second study, the control on these attributes by the project manager must be larger. We can check that in all the obtained rules, specially in R1, R2 and R4, the tendency is to realize the incorporation and adequacy of the new technicians slowly, while the leaving of the project technicians must tend to be realized quickly (always within the intervals we have defined for these attributes). Although, the 4 attributes that have been used to generate the database appear in all the rules, in this case, rules R3 and R4 indicate that not only the attributes related to the personnel management had to be modified but also the one related to 20 International Journal of Software Engineering and Knowledge Engineering the initial restrictions on delivery time. Thus, it would have been more suitable to apply the rules R1 or R2, since this last attribute was estimated within the interval obtained in the rules. Results of ELLIPSES The rules induced by ELLIPSES whose results show restrictions on development time and a high level of quality are the following: R1: (RmAnvos-13.5)/1.57 + (RmCtrata-8.7)/0.28=1. Success =5, Errors =2, Before covered cases=0. R2: (RmAnvos-12.4)/2.04+(PmxRet-1.16)/0.01+(RmDesp-6.9)/1.19=1. Success =3, Errors =0, Before covered cases =0. R3: (RmAnvos-14.8)/0.74+(RmCtrata-9.9)/1.20+(PmxRet-1.06)/0.05=1. Success =2, Errors =1, Before covered cases =0. Fig. 8. Results of ELLIPSES on CRCCRT database for cut 2. In figure 8 we offer the graphic representation of these rules. Next, we offer the interpretation of these results. •Figure 8.R1): RmAnvos must take high values (center 13.5 with a margin of ±1.57) and RmCtrata must take high values but without reaching the limit (center 8.7 with a margin of ±0.28). •Figure 8. R2): RmAnvos takes high values without reaching the limit (center 12.4 with a margin of ±2.04), PmxRet takes high values without reaching the limit (center 1.16 and margin ±0.01) and RmDesp takes medium low values (center 6.9 and margin ±1.19). •Figure 8.R3): RmAnvos must take very high values (center 14.8 and margin ±0.74), RmCtrata must take high values (center 9.9 and margin ±1.20) and PmxRet must take medium and low values, but without reaching the limit (center 1.06 and margin ±0.05). 4.3. Analysis of the database GENERAL Data Mining for the Management of Software Development Process 21 The database GENERAL has been generated with a less restrictive policy than the previous one, in such a way that we have expanded both the number of attributes to estimate and the cut percentage that establishes when the development of a project is good. Given that the real values of this project for time and effort were of 387 days and 2092 technicians-day respectively, what we are searching in this analysis are the management rules that would have improved the final values of this project, keeping, at the same time, the quality within acceptable levels, as it is shown in table 3. We can check again, the same than in the previous section, that if we limit the goals, that is to say, if we only want to obtain, in a global way, good results for time and effort, independently of the values obtained for the project quality, the number of suitable scenarios considerably increases (goes from 48 to 221). 4.3.1. Cut 1: Restrictions for time, effort and quality The first cut for this database is the only one that establishes restrictions on the three output variables. Therefore, the rules that are induced on the attributes must fulfil the three restrictions simultaneously, according to the cuts shown in table 3. Results of GAR The association rules discovered by GAR, where the consequent is formed by the intervals of the variables EsfNec ∈[1111,2092] and T poDllo ∈[320,387] and Quality ∈[0,0.40], that is, the management rules that would have permitted to obtain, simultaneously, good results for delivery time, effort and project quality, are the following ones: R1: If RmAnvos ∈[33.2,78.3] and P esfDes ∈[0.58,0.84] and T ecInicio ∈[0.57,0.93] and DF ormar ∈[0.05,0.26] and ItmoLcf ∈[0.05,0.22]. Support = 2.2%, confidence = 84.62%, covered cases = 11, rc = 0 R2: If DmT ecn ∈[0.54,0.88] and RmAnvos ∈[41.4,78.4] and RmCtrata ∈[15.1,36.4] and T ecInicio ∈[0.62,0.98] and ItmoLcf ∈[0.05,0.24] Support = 2.6%, confidence = 86.67%, covered cases = 13, rc = 6 R3: If DmT ecn ∈[0.79,0.91] and RmAnvos ∈[41.6,119.2] and RmCtrata ∈[33.1,39.6] and T ecInicio ∈[0.75,0.99]. Support = 2.2%, confidence = 84.62%, covered cases =11, rc = 2 Figure 9 shows the graphic representation of the discovered rules. In this case, R1 is the chosen rule for being realizing a post mortem analysis of the project (rule R2 is similar). This rule, although involves 5 attributes (one more than rule R3), is the one that is closer to the estimations realized for this project. That is to say, we would have improved the obtained results if we had improved the initial estimations on the size of the project (ItmoLcf ), if we had increase the average delay of adequacy of the new technicians (RmAnvos) and if we had increase the number of technicians at the beginning of the project (TecInicio). Rule R3 would imply the modification of the four attributes since, the estimated values for each one of them are not in the range of the values indicated in the rule. Results of ELLIPSES 22 International Journal of Software Engineering and Knowledge Engineering Fig. 9. Results of GAR on GENERAL database for cut 1. The management rules induced by ELLIPSES to obtain results labeled as ’Good’ are the followingc: R1: (a-0.8)/0.16+(e-0.8)/0.15+(h-0.2)/0.05=1. Success =9, Errors =1, Before covered cases=0. R2: (a-0.9)/0.12+(b-94.3)/25.6+(d-33.0)/7.0+(e-0.9)/0.07=1. Success =7, Errors =0, Before covered cases=2. R3: (b-54.3)/44.32+(e-0.5)/0.22+(f-2.7)/0.24=1. Success =6, Errors=1, Before covered cases=0. R4: (d-36.0)/4.00+(e-0.8)/0.20+(h-0.2)/0.21+(i-0.2)/0.20=1. Success=10, Errors =1, Before covered cases =5. In figure 10 we show the graphic representation of the rules obtained by ELLIPSES for time, effort and quality. Next, we offer the interpretation of these rules. •Figure 10.a). DmTecn must take medium-high or high values (center 0.84, margin 0.16), TecInicio must take high values (center 0.85, margin 0.15) and IesfEst must take medium-low values (about 0.2 with a margin of 0.05). Thus, in order to secure a development process that adjust to the initial necessities, the dedication must be high (>70%), the percentage of technicians at the beginning of the project must be high (>70%), but the initial estimation of effort must not overcome medium values (<25%). cKey: a) DmTecn, b) RmAnvos, c) PesfDes, d) RmCtrata, e) TecInicio, f) TecCtrata, g) DFormar, h) IesfEst, i) ItmoLcf. Data Mining for the Management of Software Development Process 23 Fig. 10. Results of ELLIPSES on GENERAL database for cut 1. •Figure 10.b). This rule indicates that an acceptable development process will be carried out with the three conditions (effort, time and quality) if: DmTecn, RmAnvos and RmCtrata take medium-high or high values (centers 0.9, 94.3 and 33 and margins 0.12, 25.6 and 7.0 respectively) and TecInicio takes very high values (center 0.9 and margin 0.1). We can deduce that if the delay in the adaptation (RmAnvos) and in the hiring of new technicians (RmCtrata) is high, more than 70 days and 25 days respectively, then, both the percentage of initial technicians (TecInicio) and the average dedication (DmTecn) must be high, more than 80% in both cases. •Figure 10.c). Practically, RmAnvos has no influence, although it must not take very high values (center 54.3 and margin 44.32). TecInicio must take medium low values (center 0.5 and margin of 0.22), although not very low, and TecCtrata must take medium values (center 2.7 and margin 0.24). That is, if the number of new technicians to be hired (TecCtrata) has a medium value (≈2) then the percentage of initial technicians (TecInicio) can be a medium low value (between 25% and 75%), but the delay in the adaptation of technicians (RmAnvos) must not be very high (<100 days). •Figure 10.d). RmCtrata must take very high values (center 36 and margin 4), TecInicio must take medium-high values (0.8 and 0.2) and both IestEsf and ItmoLcf must take low or medium-low values (center 0.2 and margin 0.2). That is to say, if the initial estimation of effort (IestEsf ) and code lines (ItmoLcf ) are medium-low values (<40% in both cases) and the hiring delay (RmCtrata) is very high (>30 days) then the percentage of initial technicians (TecInicio) must be a medium high value (>60%). 4.3.2. Cut 2: Restrictions on time and effort As the goals of the project are less ambitious, we can check in this case that a 24 International Journal of Software Engineering and Knowledge Engineering larger number of possible scenarios have been found and that the attributes that we have to control in order to fulfil the goals of the project are smaller. Results of GAR The association rules discovered by GAR, where the consequent is formed by the intervals of the variables JBSZMD ∈[1111,2092] y SCHCDT ∈[320,387], that is, the management rules that would have permitted to obtain, simultaneously, good results for delivery time, and effort, are the following ones: R1: If T ecInicio ∈[0.64,0.99] and ItmoLcf ∈[0.05,0.48]. Support = 32%, confidence = 93.02%, covered cases = 160, rc = 0 R2: If T ecInicio ∈[0.59,0.86] and ItmoLcf ∈[0.25,0.44]. Support = 11%, confidence = 100%, covered cases = 54, rc = 48 R3: If RmAnvos ∈[17.8,81.6] and T ecInicio ∈[0.55,0.92] and ItmoLcf ∈[0.05,0.29]. Support = 10%, confidence = 98.04%, covered cases = 50, rc = 44 Fig. 11. Results of GAR on GENERAL database for cut 2. In figure 11 we show the graphic representation of the rules discovered by GAR. Following the criteria proposed by the project manager, the easiest rules to be applied, among the rules obtained, would have been rules R1 and R2. We only would have to modify an attribute in then, since, the underestimation of the size of the project is maintained within the levels initially established and we would only have to modify the value of the percentage of technicians that begin the project. The selection between R1 and R2, will depend exclusively on the project manager, as we have said before, according to his knowledge on the possibility of maintaining the implied attributes within the intervals provided by the rules. Results of ELLIPSES The management rules induced by ELLIPSES to obtained results labeled as ’Good’ are the following onesd : dKey: a) DmTecn, b) RmAnvos, c) PesfDes, d) RmCtrata, e) TecInicio, f) TecCtrata, g) DFormar, h) IesfEst, i) ItmoLcf Data Mining for the Management of Software Development Process 25 R1: (e-0.9)/0.09 = 1. Success =121, Errors =14, Before covered cases =0. R2: (e-0.7)/0.10 + (i-0.4)/0.12 = 1. Success =33, Errors =0, Before covered cases =2. R3: (b-21.9)/11.42 + (e-0.6)/0.11 = 1. Success =19, Errors =2, Before covered cases =2. Fig. 12. Results of ELLIPSES on GENERAL database for cut 2. In figure 12 we show the rules obtained by ELLIPSES for time and effort. Next., we offer their interpretation. •Figure 12.a). We can notice how very high values (center 0.9 and margin 0.09) of attribute TecInicio (>80%) are determinant for the realization of a good software development project (121 cases out of 221), although there is a 11.5% (14 cases) of projects that had not an acceptable development. •Figure 12.b). In this rule, we can notice again, the significance of attribute TecInicio, since its medium high values (center 0.7 and margin 0.10) and medium high values (center 0.4 and margin 0.12) of the attribute ItmoLcf, are enough to reach to a good development. That is to say, if the percentage of technicians estimated at the beginning of the project (TecInicio) has a medium high value (≈60%) then the initial estimation of code lines (ItmoLcf ) must not be very high, between 25% and 50%. •Figure 12.c). In this rule we can notice how medium values (center 0.6 and margin 0.11) of TecInicio and low values (center 21.9 and margin 11.42) of RmAnvos would produce a suitable development, that is, if the percentage of technicians estimated at the beginning of the project (TecInicio) is not very high, an average value between 50% and 70%, then the delay in the adaptation of the technicians that are incorporated (RmAnvos) must be a very low value (<30 days).