Journal of Industrial Engineering and Management JIEM, 2021 – 14(3): 520-537 – Online ISSN: 2013-0953 – Print ISSN: 2013-8423 https://doi.org/10.3926/jiem.3438 A Batch Scheduling Model for a Three-stage Flow Shop with Job and Batch Processors Considering a Sampling Inspection to Minimize Expected Total Actual Flow Time Pratya Poeri Suryadhini , Sukoyo Sukoyo , Suprayogi Suprayogi , Abdul Hakim Halim Institut Teknologi Bandung (Indonesia)
[email protected],
[email protected],
[email protected],
[email protected] Received: December 2020 Accepted: March 2021 Abstract: Purpose: This research develops a batch scheduling model for a three-stage flow shop with job processors in the first and second stages and a batch processor in the third stage. The model integrates production process activities and a product inspection activity to minimize the expected total actual flow time. Design/methodology/approach: The problem of batch scheduling for a three-stage flow shop is formulated as a mathematical model, and a heuristic algorithm is proposed to solve the problem. This model applies backward scheduling to accommodate the objective of minimizing the expected total actual flow time. Findings: This research has proposed a batch scheduling model for a three-stage flow shop with job and batch processors to produce multiple items and an algorithm to solve the model. The objective is to minimize total actual time. The resulting production batches can be sequenced between all types of products to minimize idle time, and the batch processor capacity affects the sample size and indirectly affects the production batch size. Originality/value: This research develops a batch scheduling model for a three-stage flow shop constituting job and batch processors and carrying out integrated production and inspection activities to minimize the expected total actual flow time Keywords: actual flowtime, batch scheduling, a three-stage flow shop, job processor, batch processor, sampling inspection To cite this article: Suryadhini, P.P., Sukoyo, S., Suprayogi, S., & Halim, A.H. (2021). A batch scheduling model for a three-stage flow shop with job and batch processors considering a sampling inspection to minimize expected total actual flow time. Journal of Industrial Engineering and Management, 14(3), 520-537. https://doi.org/10.3926/jiem.3438 -520-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 1. Introduction Production shop floors carry out many activities, such as production processes and product quality tests. The activities must be conformable to avoid delays in completed product delivery to consumers and described as a multi-stage flow shop. In a multi-stage flow shop, it can involve various activities and characteristics of the machines used as in the research conducted by Halim, Suryadhini and Toha (2006). They discussed a batch scheduling model for a two-stage flow shop in an electronics manufacturing company with a common machine in the first stage comprises a surface mounting machine assembling micro-components to the printed circuit board and a parallel dedicated-machine in the second stage assembling the other components. The machines in the first and second stages constitute job processor machines that process parts one by one. Two-stage scheduling models for a flow shop consisting of a common machine in the first stage and a dedicated machine in the second stage have been discussed in Huang and Lin (2013) and Gerstl and Mosheiov (2013) for batch scheduling, and Wang and Liu (2013) for job scheduling. Suryadhini, Sukoyo, Suprayogi and Halim (2018) developed the model in Halim et al. (2006) to accommodate a three-stage flow shop case in which the third stage performs a functional test on a shared machine to ensure that the finished products satisfy the specifications. The machine of the third stage constitutes a batch processor machine that processes a group of parts simultaneously at once. Scheduling research for shops with batch processor machines has been discussed in Hidayat, Cakravastia, Samadhi and Halim (2013) and Suhaimi, Nguyen and Damodaran (2016) for single stage and Chen, Zhou, Li and Xu (2014) and Tan, Mönch and Fowler (2017) for two-stage flow shop. Furthermore, Li, Meng and Liang (2015) dealt with scheduling problems for shops with job processors and batch. This paper addresses a three-stage flow shop scheduling problem that integrates production process and product inspection activities as an extension of the model proposed in Suryadhini, Sukoyo, Suprayogi and Halim (2019). Note that the model in Suryadhini et al. (2019) is a developed model from that in Suryadhini et al. (2018). The difference is that this research includes the type of inspection and the numbers of product type, i.e., the previous research applies 100% inspection and involves two types of products; in contrast, this research applies sample inspection and involves more than two types of products. Several pieces of research discussing the integration between production and inspection activities have been conducted by Indrapriyatna, Suprayogi, Iskandar and Halim (2007) and Pandey, Kulkarni and Vrat (2011). The objective of the model addressed in this research is to minimize the total actual flowtime defines by Halim, Miyazaki and Ohta (1994a); this objective applies a backward scheduling approach to fulfill the on-time delivery. This objective has been widely adopted, such as in Hidayat, Cakravastia, Samadi and Halim (2015) dealing with the scheduling for the heterogeneous batch processor and Maulidya, Suprayogi, Wangsaputra and Halim (2017) dealing with the scheduling for Hybrid Assembly Differentiation Flowshop and many others. 2. Problem Statement The paper addresses a three-stage flow shop batch scheduling producing n types of products with a common due date. The flow shop produces two types of batches, that is, production and inspection batches. In the first stage, all types of products are produced on a common machine with the same processing time. The second stage consists of n parallel dedicated machines; all types are processed on respective dedicated machines and with respective processing times. Production batches are processed in the first and the second stage with the same size and sequence of the batch. The batching process assumes that each production batch consists of only one type of product. In the third stage, all types of products will be inspected in a common machine that constitutes a batch processor. In this stage, the batch to be inspected is called the inspection batch consisting of the sample from the production batch; the sample size is determined using the Dodge-Romig sampling scheme (Schilling & Neubauer, 2009). The inspection batch could consist of one or more types of products because all types have the same test, but the sample size cannot exceed the batch processor capacity. Each production batch that has been processed in the second stage will be sampled and grouped according to the production batch sequence until the total number of -521-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 samples are equal or close to the batch processor capacity. The purpose of the inspection batch is to inspect the sample and to inspect the remaining parts from the rejected production batch due to 100% inspection. The following notations are used in this paper: M0= The common machine in the first stage Mp= The dedicated machine in the second stage processed product type g, for g = 1 to G Mu= The common inspection machine in the third stage G= The number of product types Pa = Percent acceptance of production batch Lg[i]= The production batch from product type g at position i L’[z]= The inspection batch at position z Decision Variables A[i] = The sample size of production batch at position i A’[z] = Size of inspection batch at position z B1 [i] = The starting time of production batch at position i in the first stage B2[z][i] = The starting time of the production batch at position i in the second stage refers to the inspection batch at position z B3[z] = The starting time of inspection batch at position z in the third stage N= Number of production batches Q[i] = Size of production batch at position i Q’[i] = Size of production batch at position i with non-conforming part Z= Number of inspection batches Parameters AOQL = Average Outgoing Quality Limit c = Acceptance number d = The common due date hg= Number of orders for product type g K= The capacity of machine Mu p= The proportion of a non-conforming part s= The common setup time t0= The processing time in the first stage tp= The processing time of product type g in the second stage, for g = 1 to G tu= The inspection time in the third stage Indexes g = Types of product i = The position of a production batch lg= The production batch position of product type g z = The position of an inspection batch -522-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 This research formulates the batch scheduling problem for a three-stage flow shop in a mathematical model and proposes a heuristic procedure to solve the problem. 3. Model Development Let G types of products be indexed by g from 1 to G; each product type consists of hg parts. Each part of each type of product will be grouped into a production batch and will be processed in the first two stages; all production batches will be processed in the common machine at the first stage denoted by M0 with processing time denoted by t0. In the second stage, which consisting of G parallel dedicated machines, the production batches from each type of product will be processed on a respective dedicated machine denoted by Mg with different processing times indicated by tg. Before starting the process in the third stage, each production batch will be sampled and each sample will be grouped into inspection batches. An inspection batch may consist of samples of the same or different types of products, but the total parts must be equal or close to the batch processor capacity. If a rejected production batch is found in the third stage, the production batch must be 100% inspected and the rejected parts will be replaced. 3.1. Production Batch The production batch is formed before the processing in the first stage, and as previously mentioned, a production batch consists of one type of product. The size of the production batch represents several parts in a batch, and it is influenced by the proportion of non-conforming parts (p) because it is assumed that there is no rework process to replace non-conforming parts, and to anticipate this, the number of production units was increased. If the batch size denoted by Q and the size of the production batch to be produced is denoted by Q', then Q' can be formulated as follows: (1) The production batch size is indirectly affected by the sample size of the production batch because the sample size should not exceed the batch processor capacity. If exceeded, the number of production batches will increase, and the size will decrease. 3.2. Inspection Batch The inspection batch is used to inspect the sample and to inspect 100% of the rejected production batch. The inspection batch used to inspect the sample is formed from a group of samples, and to determine the number of samples (A) is done by the following Dodge-Romig rule: (2) In Equation (2), PL is the average outgoing quality limit, whereas the value of y can be found in Schilling and Neubauer (2009). To determine the number of inspection batches, we must know the number of parts to be inspected, and the Dodge-Romig scheme is used to determine the sampling. Deciding the number of parts inspected, for both the sample and the rejected production batches uses the Average Total Inspection (ATI) (Schilling & Neubauer, 2009). The following equations calculate the Average Total Inspection (ATI), the total number of inspection batches (Z), and the number of inspection batches to inspect the samples (Z’): g and I(3) -523-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 g and I (4) g and I (5) In contrast to the production batch, an inspection batch may consist of one or more types of products, but in this research, it is assumed that the samples from the same production batch cannot be inspected on a different inspection batch. Therefore, the inspection batch size may not be full or not equal to the batch processor capacity. The remaining capacity for sample inspection can be used to inspect remaining parts from rejected production batches so that the inspection batches can inspect both samples and parts from rejected production batches simultaneously. However, an inspection batch might only inspect the parts from the rejected production batch if the total number of inspection batch is greater than the total number of inspection batch for the sample (Z >Z'). 3.3. Sequencing Rule for Production and Inspection Batch The sequencing process in this research refers to the research conducted by Halim, Miyazaki and Ohta (1994b), and the research develops multi-item scheduling intending to minimize the total actual flowtime. In the proposed algorithm, after obtaining the number and size of the production batches, the batches are sequenced, the resulting sequence should minimize the total actual flow time. The sequencing process is carried out by an index that reflects the actual flowtime of the batch. The index is calculated using the following equation: g and I (6) The production batches are sequenced by index, starting from the smallest to the largest index. The sequencing process is carried out twice. First, the sequencing is carried out between production batches for the same product type, and the second, sequencing is carried out between types of products. The second sequencing is performed to minimize the idle time in the second stage. 3.4. Actual Flow time The actual flow time is defined by Halim et al. (1994a) as the time interval between the arrival time of a job at the shop and their common due date, and can be formulated as follows: for i = 1, …, N(7) where d is the common due date and B[i] is the starting time of a job. This criterion shows that a job does not have to arrive at the shop floor at the same predetermined time, i.e., at time zero, but may come to the shop floor at the starting time of processing the job. Hence, this criterion reducing the shop time and satisfy the due date simultaneously. This criterion applies the backward scheduling method to fulfill customer satisfaction in on-time delivery. In a batch scheduling problem, the actual flowtime is calculated by multiplying part processing time (t) by the number of parts in a batch (Q[j]), can be written as follows: for i = 1, …, N(8) Equations (7) and (8) are used for a single machine case. -524-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 The actual flow time of each part in a batch is the same as the actual flowtime of a batch because each part in the batch must wait until all the parts in the batch are processed completely. The total actual flow time of all parts through the shop can be written as follows: (9) The total actual flow time of parts processed in a two-stage flow shop with a common machine in the first stage and a parallel dedicated-machine in the second stage has been developed by Halim et al. (2006) as follows: (10) The processing time in the first stage is denoted by t0; in contrast, processing time in the second stage is represented by tg, and the variable Xg[i] is a binary number that indicates the existence of a product type in a batch. The actual flow time in a three-stage flow shop with a common machine in the first stage, parallel dedicatedmachine in the second stage, and common machine for inspection activity have been developed by Suryadhini et al. (2018). In the inspection activity, the inspection position for samples can affect the production batch's starting time at the first stage and the second stages. Therefore we can use the due date and starting time in the first stage (B1[i]) to calculate the total actual flowtime, it can be written as follows: (11) 3.5. Starting Time Determination Suppose the three-stage flow shop processes three types of product, called TP1, TP2, and TP3. If the production batches of each type of product are divided into two batches, and the production batches sequenced in positions counted from the end position on a time scale, the schedule will be as follows. The production batches of TP1 will be at Positions 1 and 4, the production batches of TP2 will be at Positions 2 and 5, and the production batches of TP3 will be at Positions 3 and 6. The samples from each production batch will be grouped as inspection batches; for example, the total number of inspection batches (Z) is 3 batches, and the number of inspection batches for inspecting the samples (Z’) is 2 batches. Thus, one inspection batch was used for 100% inspection of the rejected batch. The samples from the production batch at Positions 1, 2, 3, and 4 will be inspected in the inspection batch at Position 1, and the samples from the production batch at Positions 4 and 5 will be inspected in the inspection batch at Position 2. Figure 1 shows the Gantt chart of the illustrated problem. Regarding Figure 1. the starting time of inspection batch for sampling inspection affected by the number of inspection batch for 100% inspection, to determine the starting time of the inspection batch for sample inspection at Position 1 and Position 2 can be formulated as follows: (12) (13) According to Equations (12) and (13), the general formulation of the starting time in the third stage can be formulated as follows: -525-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 (14) The starting time of the production batch in the second stage (B2[z][i]) is affected by the inspection position of the sample. The sample from the production batch at Position 1 is certainly inspected in the inspection batch at Position 1, and the starting time for the production batch at Position 1 in the second stage can be formulated as follows: (15) Figure 1. The Gantt Chart for Three-Stage-Flowshop with Job and Batch Processor According to Figure 1. The starting time of production batch L2[5] and L3[6] in the second stage, can be formulated as follows: (16) (17) Equations (16) and (17) show that the starting time of the production batch is in the second stage. The starting time of a production batch at a particular position in the second stage is affected by the starting time of the inspection batch, which inspects the production batch and the processing times in the second stage for the production batch and also the production batch at the previous position for the same type of product. The starting time of the production batch at Position i in the first stage (B1[i]) can be affected by the starting time of the production batch at Position i in the second stage or the starting time of the previous batch in the first stage; therefore the start time of the first stage can be formulated as follows: (18) -526-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 3.6. Mathematical Formulation The problem of batch scheduling for a three-stage flow shop, where a common machine in the first stage and parallel dedicated machines in the second stage constitute job processors, and where a common machine comprising a batch processor in the third stage, to minimize expected total actual flowtime can be formulated as the following model: Minimize (19) Subject to (20) i ≥ 2(21) (22) (23) i ≥ 2, z = 1 (24) i ≥ 2, z ≥ 2 (25) -527-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 (26) i(27) i(28) i(29) i and z(30) z(31) g(32) i and g(33) (34) (35) i and z(36) i(37) Constraint (20) shows the production batch at Position 1 backwardly must be completed at the common due date. Constraint (21) shows the formulation of the starting time of the production batch at Position i in the first stage, for i 2. Constraint (22) shows that the starting time of the batch sequenced at the last Position backwardly in the first stage must be equal to or greater than time 0. Constraint (23) shows that the completion time of the last production batch processed in the second stage must be equal to the starting time of the last inspection batch processed. Constraint (24) shows the formulation of the starting time of the production batch at Position i in the second stage, which exists in the inspection batch in the first position. Constraint (25) shows the starting time of the production batch in the second stage, which exists in the inspection batch at position z. Constraint (26) shows the last batch inspection that inspects the samples, and the expected batch inspection that runs the 100% inspection must be completed at the common due date. Constraint (27) shows the formulation of the sample size of the production batch at position i. Constraint (28) the upper bound of sample size and constrain (29) the lower bound of sample size. Constraint (30) shows the number of samples in the inspection batch at position z. Constraint (31) -528-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 V TFa N 1 N 2 N 3 1600 163,552 25 25 25 1300 163,552 25 25 25 900 144,977 22 25 15 800 130,545 11 20 24 700 99,707 7 9 12 690 97,663 7 9 11 670 93,616 7 8 9 650 91,224 6 8 9 630 83,872 6 7 8 620 83,872 6 7 8 610* 81,599 6 7 7 608* 81,599 6 7 7 607 96,273 6 6 7 606 96,273 6 6 7 605 96,273 6 6 7 Table 4. The result of the expected total actual flowtime i Q' [ i ]g A [ i ]Total sample in a batch z 1 11 1 6 16 12 9 2 5 3 8 3 5 4 11 1 6 16 25 8 2 5 6 8 3 5 7 11 1 6 16 38 8 2 5 9 8 3 5 10 11 1 6 15 411 8 2 5 12 7 3 4 13 11 1 6 15 514 8 2 5 15 7 3 4 16 11 1 6 20 6 17 8 2 5 18 7 3 4 19 8 1 5 20 7 2 4 4 7 Table 5. The resulting sequence of the example -535-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 5. Concluding Remark This paper presented the problem of batch scheduling for three-stage flow shop processing g types of products with common and parallel dedicated machines constitutes a job processor in the first and the second stages, and a common machine in the third stage constitutes a batch processor. The result of the example shows that the proposed algorithm could work well. In this research, the determination of batch size is indirectly influenced by the capacity of the batch processor because the sample size must not exceed the capacity of the batch processor. The sequence of production batches depends on each production batch's index, and sequencing of the production batches is carried out either on the same product type or between different product types. This condition is gainful for reducing idle time. Declaration of Conflicting Interests The authors declared no potential conflicts of interest with respect to the research, authorship, and/or publication of this article. Funding This research is funded by Research and Community Service Institutions of Institut Teknologi Bandung (P3MI- ITB 2020), Indonesia. References Chen, H., Zhou, S., Li, X., & Xu, R. (2014). A hybrid differential evolution algorithm for a two-stage flow shop on batch processing machines with arbitrary release times and blocking.. International Journal of Production Research, 25(19), 5714-5734. https://doi.org/10.1080/00207543.2014.910625 Gerstl, E., & Mosheiov, G. (2013). A Two-Stage Flow Shop Batch-Scheduling Problem with The Option of Using Not-All-Machines. International Journal of Production Economics, 146(1), 161-166. https://doi.org/10.1016/j.ijpe.2013.06.018 Halim, A.H., Miyazaki, S., & Ohta, H. (1994a). Batch- Scheduling Problems to Minimize Actual Flow times of Parts Through The Shop Under JIT Environment. European Journal of Operation Research, 72(3),529-544. https://doi.org/10.1016/0377-2217(94)90421-9 Halim, A.H., Miyazaki, S., & Ohta, H. (1994b). Lot Scheduling Problems of Multiple Items in The Shop with Both Receiving and Delivery Just In Time. Production Planning & Control: The Management of Operations, 5(2), 175-184. https://doi.org/10.1080/09537289408919484 Halim, A.H., Suryadhini, P.P., & Toha, I.S. (2006). Batch Scheduling to Minimize Total Actual Flowtime In a Two-Stage Flowshop With Dedicated Machine in The Second Stage. Proceedings of the 7th Asia Pacific Industrial Engineering and Management System Conference, Bangkok (Thailand), 17-20 Dec., 2006. Hidayat, N.P., Cakravastia, A., Samadhi, T.M.A., & Halim, A.H. (2013). A single item batch scheduling model on a batch processor to minimize total actual flow time of parts through the shop. Proceedings of the 14th Asia Pacific Industrial Engineering and Management System Conference, Cebu Island (Philippines), 3-6 Dec., 2013. Hidayat, N.P., Cakravastia, A., Samadhi, T.M.A., & Halim, A.H. (2015). A batch Scheduling Model for m Heterogeneous Batch Processor. International Journal of Production Research, 54(4), 1-16. https://doi.org/10.1080/00207543.2015.1056322 Huang, T.C., & Lin, B.M. (2013). Batch Scheduling in Differentiation Flow Shops for Makespan Minimisation. International Journal of Production Research, 51(17), 5073-5082. https://doi.org/10.1080/00207543.2013.784418 Indrapriyatna, A.S., Suprayogi, Iskandar, B.P., & Halim, A.H. (2007). Model Penjadwalan Batch pada Flowshop untuk Meminimasi Total Biaya Simpan dan Total Biaya Simpan. Jurnal Teknik dan manajemen Industri, 27(3), 142-160. -536-
Journal of Industrial Engineering and Management – https://doi.org/10.3926/jiem.3438 Li, D., Meng, X., & Liang, Q. (2015). A heuristic-search genetic algorithm for multi-stage hybrid flowshop scheduling with single processing machines and batch processing machines. Journal of Intelligent Manufacturing, 26, 873-890. https://doi.org/10.1007/s10845-014-0874-y Maulidya, R., Suprayogi, Wangsaputra, R., & Halim, A.H. (2017). Batch Scheduling in The First Stage for Hybrid Assembly Differentiation Flowshop to Minimize Total Actual Flowtime. Proceedings of the 18th Asia Pacific Industrial Engineering and Management System Conference, Jogjakarta (Indonesia), 3-6 Dec., 2017. Pandey, D., Kulkarni, M.S., & Vrat, P. (2011). A Methodology for Joint Optimization for maintenance Planning, Process Quality and Production Scheduling. Computers & Industrial Engineering, 61(4),1098-1106. https://doi.org/10.1016/j.cie.2011.06.023 Schilling, E.G., & Neubauer, D.V. (2009). Acceptance Sampling in Quality Control. Boca Raton: Chapman & Hall/CRC. https://doi.org/10.1201/9781584889533 Suhaimi, N., Nguyen, C., & Damodaran, P. (2016). Lagrangian approach to minimize makespan of non-identical parallel batch processing machines. Computers & Industrial Engineering, 101, 295-302. https://doi.org/10.1016/j.cie.2016.09.018 Suryadhini, P.P., Sukoyo, Suprayogi, S., & Halim, A.H. (2018). A Batch Scheduling Model for a Three-stage Flowshop with Job and Batch Processor to Minimize Total Actual Flowtime. Proceedings of the 19th Asia Pacific Industrial Engineering and Management System Conference, Hongkong (China), 5-8 Dec., 2018. Suryadhini, P.P., Sukoyo, Suprayogi, S., & Halim, A.H. (2019). A Batch Scheduling Model for a Three-stage- flowshop with Job and Batch Processors Considering Rework Process for Non-Conforming Items to Minimize Total Actual Flowtime. Proceedings of the 20th Asia Pacific Industrial Engineering and Management System Conference, Kanazawa (Japan), 2-5 Dec, 2019. Tan, Y., Mönch, L., & Fowler, J.W. (2017). A hybrid scheduling approach for a two-stage flexible flow shop. Journal of Scheduling, 21, 209-226. https://doi.org/10.1007/s10951-017-0530-4 Wang, S., & Liu, M. (2013). A heuristic method for a two-stage-hybrid flow shop with dedicated machines. Computer and Operations Research, 40(1), 438-450. https://doi.org/10.1016/j.cor.2012.07.015 Journal of Industrial Engineering and Management, 2021 (www.jiem.org) Article’s contents are provided on an Attribution-Non Commercial 4.0 Creative commons International License. Readers are allowed to copy, distribute and communicate article’s contents, provided the author’s and Journal of Industrial Engineering and Management’s names are included. It must not be used for commercial purposes. To see the complete license contents, please visit https://creativecommons.org/licenses/by-nc/4.0/. -537-