sustainability Article Waste Identification in the Operation of Structural Engineering Companies (SEC) According to Lean Management Felipe Muñoz-La Rivera 1,2,3,* , Juan Carlos Vielma 1, Rodrigo F. Herrera 1and Elisa Gallardo 4 Citation: Muñoz-La Rivera, F.; Vielma, J.C.; Herrera, R.F.; Gallardo, E. Waste Identification in the Operation of Structural Engineering Companies (SEC) According to Lean Management. Sustainability 2021,13, 4249. https://doi.org/10.3390/ su13084249 Academic Editor: Guido Perboli Received: 19 March 2021 Accepted: 8 April 2021 Published: 11 April 2021 Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. Copyright: © 2021 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https:// creativecommons.org/licenses/by/ 4.0/). 1School of Civil Engineering, Pontificia Universidad Católica de Valparaíso, Av. Brasil 2147, Valparaíso 2340000, Chile;
[email protected] (J.C.V.);
[email protected] (R.F.H.) 2School of Civil Engineering, Universitat Politècnica de Catalunya, Carrer de Jordi Girona, 1, 08034 Barcelona, Spain 3International Centre for Numerical Methods in Engineering (CIMNE), C/ Gran Capitán S/N UPC Campus Nord, Edifici C1, 08034 Barcelona, Spain 4 Department of Civil Engineering, Universidad de la Frontera, Francisco Salazar 1145, Temuco 4780000, Chile;
[email protected] *Correspondence:
[email protected] Abstract: Although the architecture, engineering and construction (AEC) industry is highly relevant to national development, it suffers from significant productivity challenges. Beneath the design and documentation of structures, a dynamic, complex process is taking place, with constant modifications and feedback involving numerous professionals from different fields and their respective approaches and work developed using various computer programs. This diversity of factors converges within an iterative trial-and-error process and does not stop until a refined model is achieved. To understand traditional structural engineering companies (SECs) in Chile involved in building private procurement projects, 25 non-value-adding SEC activities were identified and classified according to typical lean management waste categories. These were initially validated by a panel of experts and then confirmed through a survey of 37 companies. The identified activities reduce the productivity of SEC organizations, contributing to low AEC industry indicators. Keywords: structural engineering companies (SECs); engineering workflows; structural design problems; lean management 1. Introduction The architecture, engineering and construction (AEC) industry is known for having low productivity levels, which is worrying in an industry of relevance to a country’s development, in terms of its contributions to the gross domestic product and the social welfare that it generates [ 1 ]. This is due to several well-known problems: cost overruns and delays, minimal interaction between different actors, poor knowledge management, a focus on routine activities, high fragmentation, poor asset management, design changes during the construction stage and poor planning and scheduling, among others [ 2 ]. All these problems are associated with the complexity of AEC industry projects, the high number of processes, professionals and approaches involved in the different stages of the project, the insufficient incorporation of technologies, automation and collaborative work [3]. Fragmentation in the construction industry, considered to be one of the major problems in the sector, is caused by, on the one hand, the separation of the design and construction phases and, on the other hand, the composition and structure of the construction industry. In this regard, it is common to find professionals dedicated to design who fail to anticipate how the company should carry out the construction of the project they have designed, which, in the long run, produces delays, disputes and claims that negatively impact the scheduling of the work [3]. In this context, trends have emerged in the last decade that could contribute to the improvement of these indicators [ 4 ]. The term Industry 4.0 refers directly to the current Sustainability 2021,13, 4249. https://doi.org/10.3390/su13084249 https://www.mdpi.com/journal/sustainability
Sustainability 2021,13, 4249 2 of 19 shift towards digitization and automation of the manufacturing environment worldwide. However, this concept has not yet reached unanimous acceptance within the construction industry and it is necessary for the industry to adopt the political, social, economic, technological, environmental and legal implications that Industry 4.0 requires [5]. The desire to introduce digital change into the construction industry has benefited from the irruption of building information modeling (BIM) [ 6 ]. Despite this, professionals in the construction industry are frequently involved in situations involving the loss of information necessary for the development of the work. The challenge then centers on enabling the development of systems that facilitate the exchange of information within organizations. It is currently estimated that errors made in the design process cause approximately 30% of the errors that occur during the construction stage and approximately 55% of the errors that are made during the maintenance phase of a project [ 3 ]. In this sense, the BIM system can be considered the confluence of digital information necessary to support the design and construction processes, favoring collaborative work and the exchange of information [7]. Lean project management is a methodology designed to achieve three fundamental goals which could address the problems mentioned above: deliver a product, maximize value and minimize waste [ 8 ]. In the design phase, the greatest wastes involve the clarification of needs, rework, internal control of activities, interdisciplinary reviews, waiting times and interruption [ 9 ]. To maximize value and minimize waste in the design phase, there are some lean design management practices that can be applied, such as involving specialists, designers and builders during early stages; encouraging the active, systematic participation of clients during decision making; and holding meetings to resolve problems, identify waste and define a responsible person to reduce it, among others [10]. Considering the role of structural engineering companies (SECs) in building projects with private procurement [ 11 ] and the importance of their efficient work in the initial stages of construction projects [ 12 ], this paper seeks to identify and quantify situations and problems that hinder optimal processes in the functioning of traditional SECs in Chile, especially those issues responsible for reducing the productivity of these organizations and that contribute to the low indicators of the AEC industry. Based on a literature review and validated by a panel of experts, the SEC workflow was identified, detailing roles and processes. According to these interactions and based on a literature review, the non-value-adding SEC activities were studied through the identification of waste according to lean management. Information was collected through a survey of 37 Chilean SECs, studying the frequency with which these activities occur in the work process and the importance that companies give to these activities as hindering the work process. With these results of importance and frequency for each SEC activities that do not add value in the workflows, three indicators were calculated (relative importance index (RII), frequency index (FI), and frequency adjusted importance index (FAII)), with which it was possible to make a ranking of these activities, based on the importance/frequency analysis. In addition, using a Kruskal–Wallis test, it was possible to determine that these trends were maintained regardless of the size of the SEC projects. The research seeks to answer the following questions: •What problems arise in current SEC workflows? •What is the importance that professionals in the field place on these problems? •What is the recurrence of these problems in SECs? • Is there a difference in the presence of problems according to the size of projects executed by companies? 2. Research Methods The research methodology is organized into three stages: (1) identification of SEC operation, (2) identification of SEC activities that do not add value and (3) validation of SEC activities that do not add value. Figure 1specifies the activities, research tools and deliverables for each stage of the research. The research is focused on building projects with private procurement.
Sustainability 2021,13, 4249 3 of 19 Sustainability 2021, 13, x FOR PEER REVIEW 3 of 21 2. Research Methods The research methodology is organized into three stages: (1) identification of SEC operation, (2) identification of SEC activities that do not add value and (3) validation of SEC activities that do not add value. Figure 1 specifies the activities, research tools and deliverables for each stage of the research. The research is focused on building projects with private procurement. STAGE Literature review RESEARCH TOOLS ACTIVITIES DELIVERABLES Definition of SEC operations Flowchart of the processes developed in SEC (1) Identification of SEC operation Expert panel Validation of SEC processes Literature review Identification of SEC activities that do not add value (2) SEC activities that do not add value Research team analysis Classification according to typical waste of Lean Management List of SEC activities that do not add value, according to typical waste of Lean Management Expert panel Validation of SEC activities that do not add value (3) Validation of SEC activities that do not add value 37 SEC responses Execution of surveys List of SEC activities that do not add value, according to typical Lean Management waste, validated and ranked Kruskal-Wallis test Importance/ Frequency Analysis Analysis of difference in results according to the size of the projects. Rank based on Importance/Frequency analysis (according to indicators RII, FI and FAII) Frequency/importance assessment of SEC activities that do not add value In the first stage, the SEC operation in building projects with private procurement was defined, considering roles and workflows based on the traditional methods currently performed. These SEC processes were validated by a panel of five experts. In the second stage, based on the flowchart of the processes developed in the SECs, 25 activities were identified that do not add value; these were then classified according to the typical waste categories in lean management and then validated by a panel of five experts. In the third stage, the list of SEC activities that do not add value—according to the typical waste categories of lean management—was incorporated into a questionnaire using a scale of 1 to 5, so that 37 SECs could evaluate the importance and frequency of each of the 25 identified wastes. Based on this assessment, the authors analyzed and validated the identified waste and its relevance to SEC workflows. Literature reviews were conducted in stages 1 and 2, considering recommendations from literature review methodologies [13,14]. Figure 2 shows, in simplified form, the steps performed for this purpose. The specific aspects of each search are detailed in Sections 2.1 and 2.2, below. Figure 3(a) shows the distribution of the selected articles in the range of years included in the study. Figure 3(b) shows the “Search criteria” distribution according to selected articles. Figure 4 shows the journal distribution of the selected articles. Figure 1. Research methodology. In the first stage, the SEC operation in building projects with private procurement was defined, considering roles and workflows based on the traditional methods currently performed. These SEC processes were validated by a panel of five experts. In the second stage, based on the flowchart of the processes developed in the SECs, 25 activities were identified that do not add value; these were then classified according to the typical waste categories in lean management and then validated by a panel of five experts. In the third stage, the list of SEC activities that do not add value—according to the typical waste categories of lean management—was incorporated into a questionnaire using a scale of 1 to 5, so that 37 SECs could evaluate the importance and frequency of each of the 25 identified wastes. Based on this assessment, the authors analyzed and validated the identified waste and its relevance to SEC workflows. Literature reviews were conducted in stages 1 and 2, considering recommendations from literature review methodologies [ 13 , 14 ]. Figure 2shows, in simplified form, the steps performed for this purpose. The specific aspects of each search are detailed in Sections 2.1 and 2.2 , below. Figure 3a shows the distribution of the selected articles in the range of years included in the study. Figure 3b shows the “Search criteria” distribution according to selected articles. Figure 4shows the journal distribution of the selected articles. Sustainability 2021, 13, x FOR PEER REVIEW 4 of 21 ELIGIBILITY PRELIMINAR OBJETIVES AND BOUNDARIES EXCLUSION INCLUDED Relevant articles after screening of title, keywords and abstract Scopus Web of Science Total articles (n=74) Articles excluded (n=29) Articles included in review (n=45) Keywordsbased research Start Exclusion Criteria: Construction processes, technical aspects of design and/ or construction, infrastructure construction projects, public procurement building projects. Search Criteria: Processes in engineering, engineering design, structural engineering companies Search Criteria: problems in engineering design, interactions in engineering projects, processes in engineering, engineering design and structural engineering firms SEC operation: processes and interactions of the design stage and the SEC, with focus on building projects with private procurement. Activities that do not add value in the SEC: problems and interactions in SEC operation, with focus on building projects with private procurement. Figure 2. Summary of the literature selection process. (a) (b) Figure 3. Number of papers per year (a). “Search criteria” distribution according to selected articles (b). Figure 4. Journal distribution. 2.1. Stage 1: Identification of SEC Operation A literature review was carried out, based on the methodology proposed by Tranfield et al. [15]. It consists of three parts: a) planning the review, b) conducting the review and c) reporting and dissemination. Figure 2. Summary of the literature selection process.
Sustainability 2021,13, 4249 4 of 19 Sustainability 2021, 13, x FOR PEER REVIEW 4 of 21 ELIGIBILITY PRELIMINAR OBJETIVES AND BOUNDARIES EXCLUSION INCLUDED Relevant articles after screening of title, keywords and abstract Scopus Web of Science Total articles (n=74) Articles excluded (n=29) Articles included in review (n=45) Keywordsbased research Start Exclusion Criteria: Construction processes, technical aspects of design and/ or construction, infrastructure construction projects, public procurement building projects. Search Criteria: Processes in engineering, engineering design, structural engineering companies Search Criteria: problems in engineering design, interactions in engineering projects, processes in engineering, engineering design and structural engineering firms SEC operation: processes and interactions of the design stage and the SEC, with focus on building projects with private procurement. Activities that do not add value in the SEC: problems and interactions in SEC operation, with focus on building projects with private procurement. Figure 2. Summary of the literature selection process. (a) (b) Figure 3. Number of papers per year (a). “Search criteria” distribution according to selected articles (b). Figure 4. Journal distribution. 2.1. Stage 1: Identification of SEC Operation A literature review was carried out, based on the methodology proposed by Tranfield et al. [15]. It consists of three parts: a) planning the review, b) conducting the review and c) reporting and dissemination. Figure 3. Number of papers per year (a). “Search criteria” distribution according to selected articles (b). Sustainability 2021, 13, x FOR PEER REVIEW 4 of 21 ELIGIBILITY PRELIMINAR OBJETIVES AND BOUNDARIES EXCLUSION INCLUDED Relevant articles after screening of title, keywords and abstract Scopus Web of Science Total articles (n=74) Articles excluded (n=29) Articles included in review (n=45) Keywordsbased research Start Exclusion Criteria: Construction processes, technical aspects of design and/ or construction, infrastructure construction projects, public procurement building projects. Search Criteria: Processes in engineering, engineering design, structural engineering companies Search Criteria: problems in engineering design, interactions in engineering projects, processes in engineering, engineering design and structural engineering firms SEC operation: processes and interactions of the design stage and the SEC, with focus on building projects with private procurement. Activities that do not add value in the SEC: problems and interactions in SEC operation, with focus on building projects with private procurement. Figure 2. Summary of the literature selection process. (a) (b) Figure 3. Number of papers per year (a). “Search criteria” distribution according to selected articles (b). Figure 4. Journal distribution. 2.1. Stage 1: Identification of SEC Operation A literature review was carried out, based on the methodology proposed by Tranfield et al. [15]. It consists of three parts: a) planning the review, b) conducting the review and c) reporting and dissemination. Figure 4. Journal distribution. 2.1. Stage 1: Identification of SEC Operation A literature review was carried out, based on the methodology proposed by Tranfield et al. [ 15 ]. It consists of three parts: (a) planning the review, (b) conducting the review and (c) reporting and dissemination. • In (a), to identify the workflow of the SECs, the following search topics were considered: processes in engineering, engineering design and structural engineering companies. Journals specializing in structural engineering, engineering and construction project management and conference proceedings were considered, based on the Web of Science and Scopus collections. Documents focusing on construction processes and technical aspects of design and/or construction were excluded. For the search, documents from the year 2000 to the present were considered. • In (b), the search was carried out, selecting 47 references on processes and interactions of the design stage and the SECs, with a focus on building projects with private procurement. • In (c), based on the selected references, the SEC workflow was described, detailing its characteristics, professionals and main processes. The SEC operation was defined using a flow chart that shows the processes developed during a structural engineering project linked to seven positions in charge of each of the indicated activities. This flow chart and the description of its operation was validated by a panel of experts detailed in Table 1. Five experts were selected who met the following requirements: (a) more than ten years of practice and (b) experience as a consultant or researcher in the
Sustainability 2021,13, 4249 5 of 19 area of structural engineering and engineering design stages. In a focus group, the experts discussed the proposed processes and flows, finalizing the flowchart of the processes developed in SECs. Table 1. Characterization of the expert panel that validated the SEC processes. Profession (Grade) Occupation Field of Work Years of Experience Civil Engineering, PhD Researcher and consultant Structural engineering; structural management >25 Civil Engineering, PhD Researcher and consultant Project management; Lean management >10 Civil Engineering, MSc Consultant and senior structural engineer Structural engineering; structural management; project management >25 Civil Engineering, MSc Consultant and senior structural engineer Structural engineering; structural management >20 Civil Engineering, PhD candidate Researcher and consultant Structural engineering; project management; BIM; Lean management >10 2.2. Stage 2: SEC Activities That Do Not Add Value A second literature review was carried out according to the guidelines described above [15]. It again comprised three parts: • In (a), to identify activities that do not add value in the SEC workflow, the following search topics were considered: problems in engineering design, interactions in engineering projects, processes in engineering, engineering design and structural engineering firms. Journals specializing in structural engineering, engineering and construction project management and conference proceedings, based on the Web of Science and Scopus collections, were considered. Documents focusing on construction processes and technical aspects of design and/or construction were excluded. Documents from the year 2000 to the present were considered for the search. • In (b), the search was performed, selecting 47 references that identify problems within SEC workflows, with an emphasis on construction projects with private contracting. Activities that do not add value were identified based on waste categories according to lean management. Eight types of waste were identified based on the lean management philosophy, which are shown in Table 2. • In (c), from the selected references, a list of activities was identified and classified according to the lean waste categories. Based on the literature review and the flowchart obtained in Stage 1, activities that do not add value to the processes developed in the SECs were identified. These activities were then classified according to the typical waste categories of Lean Management and then validated by the panel of experts described in Table 1, following the same work dynamics described in Stage 1, thus obtaining a list of 25 SEC activities that do not add value.
Sustainability 2021,13, 4249 6 of 19 Table 2. Typical waste categories of lean management [12,16]. ID Type of Waste Description W1 Waste of overproduction Producing more than required leading to overstaffing, storage and transportation costs. Causes a significant amount of resource to be tied up, which otherwise could be used for value-adding operations. W2 Waste of time on hand (waiting) All the time which is not spent for value-adding activities. W3 Waste in transportation Carrying works which does not add value to final product for customer. W4 Waste of processing itself (overprocessing) Unnecessary transactions involved in the process. W5 Waste of movement Any unnecessary movement performed by sources W6 Waste of stock on hand (inventory excess) Excessive amount of supply stored with respect to customer needs and value. W7 Waste of making defective products Deviation of products from customer requires or specification. W8 Unused Employee Creativity This is a situation of not using the potential efficiently, which makes an organization to benefit less than possible. 2.3. Stage 3: Validation of SEC Activities That Do Not Add Value To validate the list of 25 SEC activities that do not add value, according to typical lean management waste categories, the researchers invited all the SECs involved with the collaborative space of technology, innovation, management and sustainability (TIMS) in civil engineering in Chile to join the research. Thirty-seven interested Chilean SECs were assessed; each company’s representative had the following characteristics: (1) more than ten years of experience, (2) basic knowledge about BIM and lean and (3) agreed to provide information about the waste of their SEC. A survey was given to the 37 Chilean SECs, either online through the SurveyMonkey platform or through personal interviews. The measurement instrument, shown in Table 3 , uses a Likert scale of five points, according to two indicators: frequency of occurrence (never = 1, rarely = 2, occasionally = 3, frequently = 4 and very frequently = 5) and importance of the problem as hindering the process (not important = 1, of little importance = 2 , moderately important = 3, important = 4 and very important = 5). Based on the answers of the 37 SECs, the distribution of the response rates with respect to frequency and importance was obtained, based on the Likert scale, for each of the 25 SEC activities that do not add value. In addition, the following analyses were carried out: (1) an analysis to rank the 25 SEC activities that do not add value, based on importance/frequency and (2) a Kruskal–Wallis test to identify if there are differences according to the size of the projects developed by the different SECs. With the aim of obtaining a ranking of the 25 activities, based on a weighting between importance and frequency, three indicators were calculated [17]: • The relative importance index (RII) was used to measure the importance of the different SEC activities. The five-point Likert scale ranging from 1 (not important) to 5 (very important) was implemented. The RII was calculated based on Equation (1): RII =∑w A N (1) where Wis the weight given to each factor by the respondents (1 to 5), Ais the highest weight (in this case 5) and Nis the total number of respondents (in this case 37). The
Sustainability 2021,13, 4249 7 of 19 value of the RII varies from 0 to 1: the greater the value, the higher the importance of each SEC activity. • The frequency index (FI) was used to measure the frequency of the different SEC activities. The five-point Likert scale ranging from 1 (never) to 5 (very frequently) was implemented. The FI was calculated based on Equation (2): FI (%)=∑Wn N100 5(2) where Wis the weight given to each factor by the respondents (1 to 5), nis the frequency of the responses and Nis the total number of respondents (in this case 37). The value of the FI varies from 0% to 100%: the greater the percentage, the higher the frequency of each SEC activity. • The frequency adjusted importance index (FAII) was used to rank frequency and importance at the same time. Based on both the FI and RII, the frequency adjusted importance index was calculated according to Equation (3): FAII (%)=RII FI (3) The value of the FAII varies from 0% to 100%; the greater the value, the higher the importance/frequency ratio of each SEC activity. The SEC activities were ranked based on the values of the FAII. Table 3. Measurement instrument. Type N◦Description Section 1 A General identification of the respondent B Indicate the size of projects you commonly undertake (less than 500 m2, between 500 m2 and 1000 m2, between 1000 m2and 5000 m2, between 5000 m2and 10,000 m2, between 10,000 m2and 20,000 m2, or more than 20,000 m2). Section 2 (25 SEC activities) Question n Description of SEC activities that do not add value Frequency Importance 1 Never 1 Not important 2 Rarely 2 Of little importance 3 Occasionally 3 Moderately important 4 Frequently 4 Important 5 Very frequently 5 Very important Results were quantitatively assessed for differences according to project size via the Kruskal–Wallis test, which is used to determine if the medians of two or more groups differ. As a non-parametric test, it is efficient for studying independent samples obtained from professionals working on different project sizes. For cases where statistical distributions are not precisely known, the test identifies whether or not there are differences in samples. With this technique, each problem raised was verified and the following hypotheses were formulated: • H 0 = there is no difference in the assessment of the problems (in frequency or importance) with respect to the different sizes of projects carried out by the respondents. • H 1 = there is a difference in the assessment of the problems (in frequency or importance) with respect to the different sizes of projects carried out by the respondents. A significance level of 0.05 was defined and the p-value was obtained for each of the problems raised to determine whether the H 0 or H 1 hypotheses was accepted. If the p-value is greater than the level of significance, the null hypothesis cannot be rejected; otherwise, the null hypothesis is rejected, resulting in H1.
Sustainability 2021,13, 4249 8 of 19 3. Literature Review 3.1. Fragmentation in the AECO Industry Traditionally, companies that are dedicated to the development of structural projects have very well-defined activities that make up their workflow, from the beginning of conceptualization until the detailed engineering of a specific project [ 18 ]. To a large extent, the workflow ultimately obeys the technological tools adopted by each company; these include analysis and structural design programs, plan-drawing programs and programs for the preparation of budgets and internal company practices [ 11 ]. These tools, even when they can be adapted to each company’s way of working, do not offer the possibility of carrying out the integrated work of teams operating from the same platform, which would allow the coordination of the different stages of a structural project. Instead, the existing tools result in a significant fragmentation of the work that affects the quality of the product, the execution time and the cost of the structural project [ 19 ]. This last condition is evident in the lack of fundamental methods that would allow adequate BIM interoperability between architectural design and structural analysis [20]. Three characteristics that determine the fragmentation within the industry can be pointed out, namely the isolation of the different disciplines that participate in a project, the lack of coordination between designers and builders and the execution of work in a formal manner. The isolation is undoubtedly due, in part, to the fact that many of the relationships established in the construction industry are of a temporary nature; this also affects the loss of the transfer of knowledge that is generated in individual projects and the actors who participate in them in a formal way [1]. On the one hand, fragmentation can be understood as related to the number of specialist companies or professionals involved in construction projects. This implies a growth in the demand for specialties as the project grows in size and complexity. Additionally, fragmentation can be classified depending on whether it is internal or external [ 3 ]. Likewise, one study [ 2 ] identified 26 main sources that create interaction problems within the construction industry; among these, employer interference and poor planning and coordination stand out. On the other hand, the interfaces of construction projects have also been identified as the main obstacle to innovation [ 1 ]. Of the various interfaces, the interface representing the relationship with customers is recognized as one of the most active, while the interface with suppliers appears to be the most distant. The consequences of this non-integrated work have been thoroughly studied recently [ 20 – 24 ] and they include the following: lack of precision, delays in the delivery of information, the need for re-correction of tasks, the slowing down of certain demanding processes and errors in the transfer of information, among others. These consequences, from a project management point of view, can be considered losses for the company. Moreover, this is not an exhaustive list, as the construction industry is often identified as not having done its part to mitigate the effects of pollution emissions [25]. 3.2. BIM and Lean Construction Industry 4.0 represents a notable increase in the digitization and automation of manufacturing processes, the implementation of which involves notable challenges related to the construction industry’s high complexity due to its interdisciplinary work, the uncertainty associated with its processes, a fragmented supply chain, short-term thinking and its cultural roots [ 5 ]. Apart from this, the construction industry is perceived as conservative, with little focus on innovation [ 1 ] and as having a high impact on the environment [ 26 ]. Despite these obstacles, the implementation of Industry 4.0 has various benefits: it improves productivity, increases quality and efficiency and promotes collaboration, security and sustainability, all of which are necessary to improve the image of the construction industry. Improving efficiency within the construction industry requires new approaches to channel all initiatives related to Industry 4.0. For this reason, Fang et al. [ 27 ] propose the implementation of a conceptual framework under a sector innovation system that
Sustainability 2021,13, 4249 9 of 19 allows construction work to be simplified, saving time and costs. This proposed conceptual framework is based on a new theory of innovation in construction. The irruption of new technologies focused on the field of structural engineering, as well as other civil engineering disciplines, has caused a radical change in the way these fields operate [ 28 – 30 ]. In this context, it is necessary to mention the impact that has occurred around the appearance of building information modeling (BIM). The transition from the traditional way of producing a structural project to the more integrated approach through the application of BIM has not been without problems and losses associated with work delays. BIM allows for the efficient, parametrical modelling and management of information in an integrated way throughout the life cycle of a project; however, the effective implementation of BIM within a construction company requires significant technical capabilities, which usually results in resistance to adoption [ 31 ]. Reality has shown that the implementation of BIM within the construction industry is led by independent designers or specific design offices. Since interdisciplinary interaction and collaboration in complex projects seems inevitable, it also seems inevitable that changes will occur in the efficient detection of project modifications that originate during the design and quality control stages [ 32 ]. To solve this problem, it has been proposed that large companies and project units of large corporations can use the internal networks of other companies to learn about what has happened in projects of a similar nature in order to gain knowledge [1]. In the case of construction companies that have implemented BIM, it is necessary to keep a reliable record of the changes carried out in the different versions of a BIM model, for which Gu et al. [ 32 ] have proposed a modification of the semantic classification of the changes, allowing effective detection in the models. These improvements, carried out within construction companies, will undoubtedly lead to an improvement in the value of BIM models [26]. In the case of companies dedicated to projects involving large structures or singular structures, BIM has allowed advances in the efficiency of the design and detailing processes, since it offers tools for which other platforms, such as the CAD platform, have few development capabilities. In terms of the aforementioned need to produce an adequate transfer of information between the design team and the construction team, this undoubtedly offers an excellent opportunity for improvement, as evidenced in the work of Gu et al. [ 33 ]. In this sense, it has been reported that the use of BIM in structural projects manages to reduce by 37% to 48% the number of instructions to modify projects and to eliminate between 43% and 68% of requests for information, although the cost of a project can be increased by up to 31% compared to the cost achieved with traditional processes [34]. In the review of the implementation of BIM within project companies, the use of tools that combine BIM with CAD applications has been found to have negative consequences, especially in the process of information exchange by different disciplines [34]. Another aspect that adversely affects the implementation of BIM in construction companies, apart from the associated costs, has to do with the need to count on the reliable interoperability of the computational tools used within the entire process [ 26 ]. Interoperability undoubtedly allows for the automation of the import-export processes that usually occur within interdisciplinary work. In this regard, the intention is to obtain a complete transfer of the model, meaning a complete export of the geometry, the static loads, the boundary conditions and the properties of the model materials. The IFC format (industry foundation classes) usually has associated errors and a loss of information [26]. On the other hand, it is well known that the design stage is one of the stages considered within lean construction, which seeks the continuous improvement of these processes. Despite good intentions, implementation of this approach in the area of structural design has not been an easy task, especially due to the resistance to change that exists in the companies in charge of carrying out such projects. In the identification of case studies in which lean construction was applied for the improvement of structural projects, one
Sustainability 2021,13, 4249 16 of 19 to the initial coordination of the projects (N6, FAII: 6th) and timely information of changes (N3, FAII: 4th). Table 6. SEC activities analysis. SEC Activities Type Interaction Rank Based on Importance/Frequency Kruskal-Wallis Test RII (%) FI (%) FAII (%) Ranking FAII Frequency Importance P-Valor Decision p-Value Decision N25 I-I 82.70 87.57 72.42 1 0.636 H0 0.683 H0 N15 I-I 85.95 80.54 69.22 2 0.987 H0 0.8 H0 N1 I-E 78.38 74.59 58.47 3 0.347 H0 0.357 H0 N3 I-E 86.49 67.03 57.97 4 0.42 H0 0.079 H0 N17 I-I 76.22 75.14 57.27 5 0.953 H0 0.569 H0 N6 I-E 83.24 68.11 56.70 6 0.577 H0 0.984 H0 N19 I-I 79.46 71.35 56.70 7 0.387 H0 0.502 H0 N22 I-I 78.38 71.35 55.92 8 0.825 H0 0.881 H0 N14 I-I 70.81 78.38 55.50 9 0.385 H0 0.608 H0 N23 I-I 76.22 71.89 54.79 10 0.548 H0 0.82 H0 N2 I-E 77.30 69.19 53.48 11 0.245 H0 0.177 H0 N18 I-I 76.76 67.03 51.45 12 0.705 H0 0.906 H0 N13 I-E/I-I 74.59 66.49 49.60 13 0.085 H0 0.884 H0 N12 I-E/I-I 81.08 61.08 49.53 14 0.98 H0 0.547 H0 N4 I-E 80.00 57.84 46.27 15 0.649 H0 0.523 H0 N9 I-E 75.14 60.54 45.49 16 0.948 H0 0.182 H0 N7 I-E 70.27 64.32 45.20 17 0.147 H0 0.205 H0 N10 I-E 74.05 60.00 44.43 18 0.072 H0 0.379 H0 N20 I-I 78.38 55.68 43.64 19 0.95 H0 0.224 H0 N16 I-I 82.70 52.43 43.36 20 0.683 H0 0.773 H0 N21 I-I 78.38 55.14 43.21 21 0.919 H0 0.505 H0 N24 I-I 70.81 55.68 39.42 22 0.658 H0 0.86 H0 N5 I-E 73.51 52.43 38.54 23 0.654 H0 0.523 H0 N11 I-E/I-I 78.38 48.65 38.13 24 1H0 0.92 H0 N8 I-E 73.51 51.35 37.75 25 0.199 H0 0.424 H0 In addition, the results of the Kruskal–Wallis test, based on the six size categories in Table 5, are shown below. Table 6shows the hypothesis and results for each issue. There is no difference in perception, for either importance or frequency, with respect to the different sizes of projects carried out by the SEC respondents in all cases. 5. Limitations According to the development of the study and the analyses carried out, the research had the following limitations: • The study considered only structural engineering companies in Chile. The 37 companies evaluated are not a global statistical sample; however, the study establishes trends for this country and provides a guideline for further studies that may examine companies from different countries, by making qualitative and quantitative assessments of the results obtained. • The activities and workflow described in the SEC operations, together with the problems identified therein, correspond to privately contracted building projects. It is important to note that the results shown may be influenced by the type of projects developed by the companies, which are focused on residential or commercial buildings using a structural typology based on reinforced concrete walls and slabs, designed under the high levels of seismic hazard in Chile. •The study did not measure the combined effect of the 25 non-value-adding activities identified. Therefore, future research should identify the origin and evaluate the combined impacts of these activities and quantify the individual and combined effects on the processes’ performance (both quantitative and qualitative).
Sustainability 2021,13, 4249 17 of 19 • The workflows and non-value adding activities identified are not necessarily all the possible ones that can be presented, as practices associated with specific IT processes, such as the use of BIM or work in the cloud, were not considered. Further studies should evaluate the impact of these methodologies and technologies and the improvement they bring to the processes. 6. Conclusions In structural engineering companies (SECs), interactions between professionals both within and outside the organization, and the workflows they follow tend to create situations that decrease productivity, interaction problems among different professionals, inefficient exchanges of information, inadequate communication channels, reworks and recurrent changes. Several authors have described activities and workflows, mainly in the complete design and construction process (not focusing on or detailing the structural design stage) [ 11 , 18 ]. They have shown, based on case studies or macro analyses of the construction sector, several of the problems described in this work concerning fragmentation [ 1 , 3 ], interaction problems [ 2 ] and its consequences for the processes [ 4 , 20 – 25 ], associated with reductions in quality, time efficiency and general management problems. This study collected part of those experiences and focused on and detailed the workflows and issues in the structural design process. Moreover, these diverse situations were categorized into 25 specific activities and evaluated by several professionals in the field in relation to their importance and frequency. Concerning importance, all problems raised were considered shortcomings affecting the correct development of daily tasks, thus damaging optimal SEC workflows. In terms of frequency, 21 of the 25 problems were rated as highly recurring in the daily work of professionals. In addition, it was found that SEC activities are independent of project size. In other words, in all cases studied, there was no difference in respondent perception, either in importance or in frequency, with respect to the different project sizes. Thus, in light of the results obtained and in view of the professionals involved, it was concluded that SECs present several deficiencies that interrupt the flow of processes and interactions. In general terms, similar problems were found irrespective of the size of the company and the size of the project. Therefore, SECs require methodological and technological restructuring to improve productivity and methodologies such as BIM could help to solve these problems effectively. The results of this study allow general managers of SECs and their project managers to identify the main types of waste incurred in their projects. The identification of waste allows organizations to diagnose the problem and to propose improvement plans for the systematic mitigation or elimination of waste from the production process. Additionally, this study provides a questionnaire that allows SECs to self-diagnose and to compare themselves with similar companies. As outlined above, this study had some limitations: the sample size does not allow for making inferences that characterize all structural engineering companies; the study only identifies the waste and not the sources of waste; it focuses on privately contracted building projects; and it does not propose actions, tools or technologies for the improvement of the processes of structural engineering companies. Therefore, for future studies, it is recommended to increase the sample size, to identify the sources of losses and their interactions in the SECs and to propose methods for the improvement of the productivity of the SECs, based on Lean Management and BIM methodologies. Author Contributions: This paper represents the results of teamwork. Conceptualization, F.M.-L.R., J.C.V. and R.F.H.; methodology, F.M.-L.R.; validation, F.M.-L.R.; formal analysis, F.M.-L.R.; investigation, F.M.-L.R.; resources, F.M.-L.R.; data cu-ration, F.M.-L.R., J.C.V. and R.F.H.; writing—original draft preparation, F.M.-L.R.; writing—review and editing, F.M.-L.R., J.C.V., R.F.H. and E.G.; supervision, J.C.V. and R.F.H. All authors have read and agreed to the published version of the manuscript.
Sustainability 2021,13, 4249 18 of 19 Funding: This research was funded by CONICYT grant number CONICYT—PCHA/International Doctorate/2019-72200306 for funding the graduate research of Muñoz-La Rivera. Institutional Review Board Statement: Not applicable. Informed Consent Statement: Not applicable. Data Availability Statement: Not applicable. Acknowledgments: The authors wish to thank all organizations participating in this study as well as the experts for the insight provided. Conflicts of Interest: The authors declare no conflict of interest. References 1. Håkansson, H.; Ingemansson, M. Industrial renewal within the construction network. Constr. Manag. Econ. 2013 ,31, 40–61. [CrossRef] 2. Yeganeh, A.A.; Azizi, M.; Falsafi, R. Root Causes of Design-Construction Interface Problems in Iranian Design-Build Projects. J. Constr. Eng. Manag. 2019,145, 1–14. [CrossRef] 3. Nasrun, M.; Nawi, M.; Baluch, N.; Bahauddin, A.Y. Impact of Fragmentation Issue in Construction Industry: An Overview 3 Discussions: Fragmentation Issue. In Proceedings of the MATEC Web of Conferences, Langkawi, Malaysia, 31 May–2 June 2013; Volume 15. 4. Muñoz-La Rivera, F.; Mora-Serrano, J.; Valero, I.; Oñate, E. Methodological-Technological Framework for Construction 4.0. Arch. Comput. Methods Eng. 2020,28, 689–711. [CrossRef] 5. Oesterreich, T.D.; Teuteberg, F. Computers in Industry Understanding the implications of digitisation and automation in the context of Industry 4.0: A triangulation approach and elements of a research agenda for the construction industry. Comput. Ind. 2016,83, 121–139. [CrossRef] 6. Berard, O.; Karlshoej, J. Information delivery manuals to integrate building product information into design. Electron. J. Inf. Technol. Constr. 2012,17, 64–74. 7. Muñoz-La Rivera, F.; Vielma, J.; Herrera, R.F.; Carvallo, J. Methodology for Building Information Modeling (BIM) Implementation in Structural Engineering Companies (SEC). Adv. Civ. Eng. 2019,2019, 8452461. [CrossRef] 8. Ballard, G.; Howell, G.A. Lean project management. Build. Res. Inf. 2003,31, 119–133. [CrossRef] 9. Freire, J.; Alarcón, L.F. Achieving Lean Design Process: Improvement Methodology. J. Constr. Eng. Manag. 2002 ,128, 248–256. [CrossRef] 10. Herrera, R.F.; Mourgues, C.; Fernando, L.; Pellicer, E. An Assessment of Lean Design Management Practices in Construction Projects. Sustainability 2019,12, 19. [CrossRef] 11. Li, M.; Yang, J. Analysis of interrelationships between critical waste factors in office building retrofit projects using interpretive structural modelling. Int. J. Constr. Manag. 2014,14, 15–27. [CrossRef] 12. Mazlum, S.K.; Pekeriçli, M.K. Lean design management—An evaluation of waste items for architectural design process. Metu J. Fac. Archit. 2016,33, 1–20. [CrossRef] 13. Paoletti, I. Mass customization with additive manufacturing: New perspectives for multi performative building components in architecture. Procedia Eng. 2017,180, 1150–1159. [CrossRef] 14. Moher, D.; Liberati, A.; Tetzlaff, J.; Altman, D.G.; Grp, P. Preferred Reporting Items for Systematic Reviews and Meta-Analyses: The PRISMA Statement. Phys. Ther. 2009,89, 873–880. [CrossRef] [PubMed] 15. Tranfield, D.; Denyer, D.; Smart, P. Towards a Methodology for Developing Evidence-Informed Management Knowledge by Means of Systematic Review. Br. J. Manag. 2003,14, 207–222. [CrossRef] 16. Ohno, T. Toyota Production System Beyond Large-Scale Production; CRC Press: New York, NY, USA, 1988. 17. Gunduz, M.; Yahya, A.M.A. Analysis of project success factors in construction industry. Technol. Econ. Dev. Econ. 2018 ,24, 67–80. [CrossRef] 18. Oti, A.H.; Kurul, E.; Cheung, F.; Tah, J.H.M. A framework for the utilization of Building Management System data in building information models for building design and operation. Autom. Constr. 2016,72, 195–210. [CrossRef] 19. Wang, Y.; Thangasamy, V.K.; Hou, Z.; Tiong, R.L.K.; Zhang, L. Collaborative relationship discovery in BIM project delivery: A social network analysis approach. Autom. Constr. 2020,114, 103147. [CrossRef] 20. Wu, J.; Sadraddin, H.L.; Ren, R.; Zhang, J.; Shao, X. Invariant Signatures of Architecture, Engineering, and Construction Objects to Support BIM Interoperability between Architectural Design and Structural Analysis. J. Constr. Eng. Manag. 2021 ,147, 04020148. [CrossRef] 21. Aranda, J.Á.; Martin-Dorta, N.; Naya, F.; Conesa-Pastor, J.; Contero, M. Sustainability and interoperability: An economic study on bim implementation by a small civil engineering firm. Sustainability 2020,12, 9581. [CrossRef] 22. Moreno, C.; Olbina, S.; Issa, R.R. BIM Use by Architecture, Engineering, and Construction (AEC) Industry in Educational Facility Projects. Adv. Civ. Eng. 2019,2019. [CrossRef]
Sustainability 2021,13, 4249 19 of 19 23. Babatunde, S.O.; Udeaja, C.; Adekunle, A.O. Barriers to BIM implementation and ways forward to improve its adoption in the Nigerian AEC firms. Int. J. Build. Pathol. Adapt. 2020. [CrossRef] 24. Hamidavi, T.; Abrishami, S.; Hosseini, M.R. Towards intelligent structural design of buildings: A BIM-based solution. J. Build. Eng. 2020,32, 101685. [CrossRef] 25. Saleh, R.M.; Al-Swidi, A. The adoption of green building practices in construction projects in Qatar: A preliminary study. Manag. Environ. Qual. An. Int. J. 2019,30, 1238–1255. [CrossRef] 26. Santos, R.; Aguiar Costa, A.; Silvestre, J.D.; Pyl, L. Development of a BIM-based Environmental and Economic Life Cycle Assessment tool. J. Clean. Prod. 2020,265. [CrossRef] 27. Fang, C.Y.; Rasiah, R.; Klobas, J.E. Motivation in Construction Innovation: Commercial Opportunities, Problem-Solving and Passion for Improvement. In Proceedings of the MATEC Web of Conferences 66, Kuala Lumpur, Malaysia, 7–8 March 2016; Volume 66. 28. Sun, C.; Xu, H.; Jiang, S. Understanding the risk factors of BIM technology implementation in the construction industry: An interpretive structural modeling (ISM) approach. Eng. Constr. Archit. Manag. 2020,27, 3289–3308. [CrossRef] 29. Tayeh, B.A.; Hamad, R.J.A.; Alaloul, W.S.; Almanassra, M. Factors Affecting Defects Occurrence in Structural Design Stage of Residential Buildings in Gaza Strip. Open Civ. Eng. J. 2019,13, 129–139. [CrossRef] 30. Kouhestani, S.; Nik-Bakht, M. IFC-based process mining for design authoring. Autom. Constr. 2020,112, 103069. [CrossRef] 31. Cao, D.; Li, H.; Wang, G.; Luo, X.; Tan, D. Relationship Network Structure and Organizational Competitiveness: Evidence from BIM Implementation Practices in the Construction Industry. J. Manag. Eng. 2018,34, 1–12. [CrossRef] 32. Lin, J.R.; Zhou, Y.C. Semantic classification and hash code accelerated detection of design changes in BIM models. Autom. Constr. 2020,115, 103212. [CrossRef] 33. Gu, P.; Tao, F.; Wang, G. Application of BIM technology in fine design in steel structure bridges. IOP Conf. Ser. Earth Environ. Sci. 2020,474, 072016. [CrossRef] 34. Yang, B.; Liu, B.; Zhu, D.; Zhang, B.; Wang, Z.; Lei, K. Semiautomatic Structural BIM-Model Generation Methodology Using CAD Construction Drawings. J. Comput. Civ. Eng. 2020,34, 1–17. [CrossRef] 35. Dufresne, M.; Mok, H.Y.; Shakeri, R.; Elbarkouky, M.; Sharma, V. Application of lean methods for productivity improvement in steel fabrication shops: A case study. In Proceedings of the International Structural Engineering and Construction, Chicago, IL, USA, 20–25 May 2019; pp. 2–6. [CrossRef] 36. Bascoul, A.M.; Tuholski, S.J.; Tommelein, I.D. Lean construction to manage project structural complexity: The LPDS-MDM framework. In Proceedings of the Construction Research Congress, New Orleans, LA, USA, 2–4 April 2018; pp. 271–281. [CrossRef] 37. Junior, J.S.; Baldauf, J.P.; Formoso, C.T.; Tzortzopoulos, P. Using bim and lean for modelling requirements in the design of healthcare projects. In Proceedings of the 26th Annual Conference of the International Group for Lean Construction, Chennai, India, 18–20 July 2018; Volume 1, pp. 571–581. [CrossRef] 38. Hayes, J. Investigating design office dynamics that support safe design. Saf. Sci. 2015,78, 25–34. [CrossRef] 39. He, R.; Li, M.; Gan, V.J.L.; Ma, J. BIM-enabled computerized design and digital fabrication of industrialized buildings: A case study. J. Clean. Prod. 2021,278, 123505. [CrossRef] 40. Sebastian, R.; Olivadese, R.; Piaia, E.; Di Giulio, R.; Bonsma, P.; Braun, J.-D.; Riexinger, G. Connecting the Knowhow of Design, Production and Construction Professionals through Mixed Reality to Overcome Building’s Performance Gaps. Proceedings 2018 , 2, 1153. [CrossRef] 41. Kim, D.; Lim, C.; Liu, Y.; Kim, S. Automatic Estimation System of Building Frames with Integrated Structural Design Information (AutoES). Iran. J. Sci. Technol. Trans. Civ. Eng. 2020,44, 1145–1157. [CrossRef] 42. Tauriainen, M.; Marttinen, P.; Dave, B.; Koskela, L. The Effects of BIM and Lean Construction on Design Management Practices. Procedia Eng. 2016,164, 567–574. [CrossRef] 43. Hayne, G.; Kumar, B.; Hare, B. A qualitative study on the impact of digital technologies on building engineering design offices. In Proceedings of the International Workshop on Computing in Civil Engineering, Austin, TX, USA, 21–23 June 2015; pp. 296–304. [CrossRef] 44. Muñoz La Rivera, F.; Herrera, R.F.; Vielma, J. Importance of collaborative teaching in university environments as a response to the fragmentation of the Architecture, Engineering, and Construction industry. In Proceedings of the XXXI Congress SOCHEDI, Viña del Mar, Chile, 10–12 October 2018. 45. Liu, Z.; Li, Y.; Zhang, H. IFC-based integration tool for supporting information exchange from architectural model to structural model. J. Cent. South Univ. Technol. 2010,17, 1344–1350. [CrossRef] 46. Lee, D.G.; Park, J.Y.; Song, S.H. BIM-Based Construction Information Management Framework for Site Information Management. Adv. Civ. Eng. 2018,2018. [CrossRef] 47. Sanguinetti, P.; Abdelmohsen, S.; Lee, J.; Lee, J.; Sheward, H.; Eastman, C. General system architecture for BIM: An integrated approach for design and analysis. Adv. Eng. Inform. 2012,26, 317–333. [CrossRef] 48. Herrera, R.F.; Muñoz-La Rivera, F.; Vielma, J.C. Interaction Networks within Student Teams Learning Building Information Modeling (BIM). J. Civ. Eng. Educ. 2021,147, 05020008. [CrossRef] 49. Salzano, A.; Asprone, D.; Cosenza, E.; Manfredi, G. Building Information Modeling: New frontiers for structural Engineering Building Information Modeling: New frontiers in structural engineering. In Proceedings of the Italian Concrete Days Gionate AICAP 2016 Congresso CTE, Rome, Italy, 27–28 October 2016.