Feasibility study for installing a wind farm in Alcoroches (Guadalajara) Document: Report Author: Naim Mu˜noz Blanco Director/Co-director: Daniel Garcia Almi˜nana / Silvia Rodr´ıguez Donaire Degree: Bachelor in aerospace technologies engineering Examination session: Spring 2024
Feasibility study for installing a wind farm in Alcoroches Abstract English The feasibility study for the installation of the Alcoroches wind farm has demonstrated that its construction is completely feasible. The design has been backed up with favourable data at each stage, following a risk-minimising methodology similar to that used by companies in the design of renewable plants. This study not only assesses energy feasibility, but also legislative and environmental constraints. The Sierra de Albarrac´ın is rich in wind resources, but is largely protected by Red Natura 2000, which prevents the installation of renewable parks. However, the proposed location is outside this zone, thus allowing the development of the project. The applicable regulations have been reviewed and have undergone significant changes recently and are likely to continue to evolve, which may require future adjustments to the design of the park. To ensure the accuracy of the project, meteorological data from Checa are compared with the IDAE wind atlas, confirming their concordance. In addition, information from the wind atlas at different heights is used and corrected using MATLAB code. The modification of the Weibull parameters allows the wind speed at different hub heights to be calculated accurately, making it possible to assess the energy production of each wind turbine. A total of nine turbines are selected from the three most prestigious European companies in the wind energy sector. After an exhaustive analysis, the V136-3.45 windmill has been chosen, which allows the wind farm to generate 148,028 MWh/year, ensuring economic viability with a payback time of approximately 11 years. The low environmental impact and the significant reduction of CO2 emissions make the project robust. In addition to the above benefits, there is an increase in revenue collected by the municipality, as well as a population growth of 13%. I
Spanish El estudio de viabilidad para la instalaci´on del parque e´olico de Alcoroches ha demostrado que su construcci´on es completamente factible. El dise˜no se ha respaldado con datos favorables en cada etapa, siguiendo una metodolog´ıa que minimiza el riesgo, similar a la utilizada por empresas en el dise˜no de plantas renovables. Este estudio no solo eval´ua la viabilidad energ´etica, sino tambi´en las limitaciones legislativas y ambientales. La Sierra de Albarrac´ın es rica en recursos e´olicos, pero est´a mayormente protegida por la Red Natura 2000, lo que impide la instalaci´on de parques renovables. Sin embargo, la ubicaci´on propuesta se encuentra fuera de esta red, permitiendo as´ı el desarrollo del proyecto. Se ha revisado la normativa aplicable, la cual ha sufrido cambios significativos recientemente y probablemente seguir´a evolucionando, lo que podr´ıa requerir futuros ajustes en el dise˜no del parque. Para garantizar la precisi´on del proyecto, se comparan datos meteorol´ogicos de Checa con el atlas e´olico del IDAE, confirmando su concordancia. Adem´as, se emplean y corrige la informaci´on del atlas e´olico a diferentes alturas utilizando un c´odigo de MATLAB. La modificaci´on de los par´ametros de Weibull permite calcular con precisi´on la velocidad del viento a diferentes alturas del hub, haciendo posible el c´alculo de la producci´on energ´etica de cada molino. Se seleccionan un total de nueve turbinas de las tres compa˜n´ıas europeas m´as prestigiosas en el ´ambito e´olico. Tras un an´alisis exhaustivo, se elige el molino V136-3.45, que permite al parque generar 148,028 MWh/a˜no, asegurando una viabilidad econ´omica con un tiempo de recuperaci´on de inversi´on de aproximadamente 11 a˜nos. El bajo impacto ambiental y la significativa reducci´on de emisiones de CO2 , hace que el proyecto sea robusto. A los beneficios anteriores hay que remarcar el aumento de los ingresos recaudados por el ayuntamiento, as´ı como el crecimiento demogr´afico que se sit´ua en un 13%. II
Feasibility study for installing a wind farm in Alcoroches Contents 1 Introduction 1 1.1 Object................................................. 1 1.2 Scope ................................................. 1 1.3 Requirements............................................. 2 1.4 Justification.............................................. 3 2 Wind energy situation in the peninsula 5 2.1 Windenergysector.......................................... 5 2.2 Current state of the wind sector . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 2.3 WindparksinGuadalajara ..................................... 7 3 Applied regulation 10 3.1 Europeanregulation ......................................... 10 3.2 Spanishregulation .......................................... 11 3.3 Castilla-La Mancha regulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 4 Selection of the wind farm location 13 4.1 Legislativelimitations ........................................ 13 4.2 Wind energy production limitations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 5 Geographical situation of the wind farm 16 5.1 Mountainshapes ........................................... 16 5.2 Flowoveroraroundterrain..................................... 17 5.3 Surfaceroughnesslength....................................... 19 5.4 Windspeed-upoverhills....................................... 21 6 Collection and study of meteorological data 22 6.1 Weatherstationselection ...................................... 22 6.2 Meteorological data acquisition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 6.3 Climatologicaldataanalysis..................................... 26 6.3.1 Wind frequency distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 III
Contents 6.3.2 Weibulldistribution ..................................... 28 6.4 Comparison of weather data with wind atlas . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 7 Study and selection of wind turbines 34 7.1 Windturbinetechnology....................................... 34 7.1.1 Windturbinetypes...................................... 34 7.1.2 Powercurve.......................................... 35 7.2 Windturbinestudy.......................................... 37 7.3 Windenergyproduction....................................... 40 7.3.1 Net energy generated by the wind turbine . . . . . . . . . . . . . . . . . . . . . . . . . 40 7.3.2 Gross energy generated by the wind turbine . . . . . . . . . . . . . . . . . . . . . . . . 42 7.4 Firsteconomicanalysis ....................................... 43 7.4.1 Windturbineprice...................................... 43 7.4.2 Futureenergyprices..................................... 44 7.4.3 Maintenancecosts ...................................... 46 7.4.4 Paybacktime......................................... 46 7.5 Windturbineselection........................................ 47 8 Wind park design 49 8.1 Wakeeffect .............................................. 49 8.2 Windturbinedistribution ...................................... 50 8.3 Calculation of the electricity production of the wind farm . . . . . . . . . . . . . . . . . . . . 55 9 Technical implementation of the wind farm 59 9.1 Access roads and internal roads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59 9.2 Foundations and platforms for wind turbines . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 9.3 Electricinstallation.......................................... 61 9.3.1 Lowvoltageinstallation................................... 61 9.3.2 Medium voltage installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62 10 Economic analysis 64 10.1Costs.................................................. 64 10.1.1 Installationcost ....................................... 64 10.1.2 Maintenancecost....................................... 66 10.2Revenue................................................ 67 10.2.1 Annual decrease in energy generated . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 10.3Economicparameters......................................... 67 10.4Scenarios ............................................... 69 10.4.1 Baselinescenario....................................... 69 10.4.2 Optimisticscenario...................................... 70 10.4.3 Pessimisticscenario ..................................... 70 IV
Contents 11 Environmental impact 72 11.1Sustainabilityindex ......................................... 72 11.2 CO2emissionsavings ........................................ 72 11.3SocialimpactinAlcoroches ..................................... 73 12 Budget 74 13 Conclusions and future work 76 13.1Conclusions.............................................. 76 13.2Futurework.............................................. 77 V
Feasibility study for installing a wind farm in Alcoroches List of Figures 2.1 Map of national wind power installations. (Source:[6]) . . . . . . . . . . . . . . . . . . . . . . 6 2.2 Evolution of the wind power installation between 2015 and 2023. (Source:[4]) . . . . . . . . . 6 2.3 Evolution of the wind energy generation between 2015 and 2023. (Source:[5]) . . . . . . . . . 6 2.4 Evolution of the wind energy mix percentage between 2007 and 2023. (Source:[4]) . . . . . . 7 2.5 Percentage contribution of each energy to the energy mix by 2023. (Source:[4]) . . . . . . . . 7 2.6 Map of the wind farms in the province of Guadalajara. (Source:[8]) . . . . . . . . . . . . . . . 8 4.1 Preliminary location of the park free of administrative restrictions. (Source:[31]) . . . . . . . 14 4.2 Map of the wind resource in the Iberian peninsula. (Source:[32]) . . . . . . . . . . . . . . . . 14 4.3 Map of the wind resource in the Sierra de Albarrac´ın. (Source:[32]) . . . . . . . . . . . . . . . 15 4.4 Map of the wind resource in Alcoroches. (Source:[32]) . . . . . . . . . . . . . . . . . . . . . . 15 5.1 Satellite image of the Alcoroches mountain area in three dimensions. (Source:[33]) . . . . . . 17 5.2 Satellite image of the three different mountain ranges in Alcoroches. (Source:[34]) . . . . . . . 17 5.3 Variation of Froude number with mountain height and fluid velocity. (Own source). . . . . . 19 5.4 Relationship between roughness length and terrain type. (Source [38]). . . . . . . . . . . . . 20 5.5 Wind profile for different terrain roughnesses. (Source:[36]) . . . . . . . . . . . . . . . . . . . 20 5.6 Speed profile in the valley area and speed-up at the mountain top. (Source:[40]) . . . . . . . 21 5.7 Three-dimensional k−ϵanalysis of wind speed flow (top view) over a 3D hill. (Source:[41]) . 21 6.1 Meteorological data collected by the Checa weather station. (Source:[46]) . . . . . . . . . . . 25 6.2 Sample of the data collected on the Wunderground website and transferred to excel format. (Ownsource) ............................................. 25 6.3 Wind speed frequency diagram at 100 metres. (Own source) . . . . . . . . . . . . . . . . . . 27 6.4 Approximation of the Weibull distribution for 100 m height using MATLAB approximation. (Ownsource) ............................................. 29 6.5 Approximation of the Weibull distribution for 100 m height. (Own source) . . . . . . . . . . 30 6.6 Comparison of Weibull distributions from weather data and CENER Wind Atlas at 50 m. (Ownsource) ............................................. 32 6.7 Comparison of Weibull distributions from weather data and CENER Wind Atlas at 100 m. (Ownsource) ............................................. 33 VI
List of Figures 6.8 Comparison of Weibull distributions from weather data and CENER Wind Atlas at 200 m. (Ownsource) ............................................. 33 7.1 Characteristic aspects of the power curve. (Source: [52]) . . . . . . . . . . . . . . . . . . . . 35 7.2 Turbine selection process. (Own Source) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 7.3 Electricity price evolution 2026-2034. (Own Source) . . . . . . . . . . . . . . . . . . . . . . . 45 8.1 Speed evolution along a generic wind farm. (Source: [58]) . . . . . . . . . . . . . . . . . . . . 49 8.2 Wind rose for the location of the wind farm. (Source:[32]) . . . . . . . . . . . . . . . . . . . . 50 8.3 Optimisation of the distribution of wind turbines in a wind farm. (Source:[59]) . . . . . . . . 50 8.4 Distribution of the wind turbines in the Caldereros I wind farm, located in Pobo de Due˜nas. (OwnSource)............................................. 51 8.5 Distribution of the wind turbines in the Sierra Merena I wind farm, located in Tordesilos. (OwnSource)............................................. 52 8.6 Layout of the wind farm. (Own Source) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54 8.7 Renewable study that has been carried out. (Own Source) . . . . . . . . . . . . . . . . . . . 55 8.8 Wind distribution parameters entered the SAM software. (Own Source) . . . . . . . . . . . . 56 8.9 Wind turbine parameters entered the SAM software. (Own Source) . . . . . . . . . . . . . . 56 8.10 Turbine layout parameters entered the SAM software. (Own Source) . . . . . . . . . . . . . 57 9.1 Location of the turbines of the Alcoroches wind farm. (Own Source) . . . . . . . . . . . . . . 60 10.1 Distribution of costs associated with the wind farm installation. (Own Source) . . . . . . . . 65 10.2 Evolution of the forecast power (green) and scheduled power (red) for the Iberian Peninsula on23/05/2024(Source:[63])..................................... 67 10.3 Evolution of the energy price for the small consumer for the Iberian Peninsula on 23/05/2024. (Source:[64]).............................................. 67 VII
Chapter 1. Introduction of these infrastructures, new technical staff will have to move to live near the wind farm, thus increasing the population level of the village. • Wind farms can provide additional income to the community through land lease agreements, in many cases it is the municipality that receives this income. Such payments can increase local revenues and raise the level of municipal coffers to fund public services and projects that benefit the town. 4
Feasibility study for installing a wind farm in Alcoroches Chapter 2 Wind energy situation in the peninsula 2.1 Wind energy sector Spain could be located in the top five countries in the world when talking about wind power installation, after China, the United States, Germany and India. The country has a great position in Europe in terms of installed wind power capacity, it is the second with most wind energy installation after Germany [3]. Looking at the economic data, the wind energy sector is one of the renewable technologies that contribute the most to the Spanish GPD. In particular, more than 5,896 M€are integrated to the economy, which represents the 0.5 % of the total gross domestic product. The industry is capable of exporting a total value of 2,512 M€in wind turbines, becoming the fifth country in the world that export the most. The industry has experienced great technological advances since its inception. In order to improve the performance of electricity generation, a large amount of capital has been invested in the sector, it amounts to more than 140 M€. Since 2004, a total of 1,256 patents related to wind power technology have been registered. In addition to the previous said, another significantly aspect is the employment that the manufactures are able to generate. A total number of 39,000 people are working in the wind sector, taking into account both direct and indirect employments. If the variation of the employment between 2021 and 2023 is compared, it can be seen that has been an increase of 14% in the employment created. The fabrication plants of wind energy pieces, are located all around the territory. Part of the design phase is placed in Navarra which is a green energy reference in Europe. Nevertheless, not only Navarra has a strong fabrication centre, more than 250 manufacturing plants are located over 16 autonomous communities. 2.2 Current state of the wind sector According to data published by REE in 2023, Spain had a total of 22,147 wind turbines that were capable of producing more than 62,569 GWh [4]. The total installed capacity in the country in 2023 exceeds 30,000 5
Chapter 2. Wind energy situation in the peninsula MW, making it the leading electricity generation source in the energy mix [5]. The wind turbines are distributed throughout the country in more than 1,345 wind farms [3], the image 2.1 shows how these parks are distributed through the territory. Figure 2.1: Map of national wind power installations. (Source:[6]) The PNIEC is a document agreed between the European Commission and MITECO, which defines the objectives for the reduction of greenhouse gas emissions and the penetration of renewable energies. With the reading of this document, a clear path of implementation of renewable energies can be observed and this is reflected in the increase of the total number of wind plants. As the years have gone by, new power has been incorporated into the energy mix. This incorporation has to be done in a coordinated manner between the promoters of the electrical installations, the MITECO and the energy distribution company. The image 2.2 shows how the installed wind power capacity in Spain has evolved, as it can be seen, from 2018 onwards, new wind infrastructures were installed on the peninsula, reaching a total installed capacity of 30,953 MW in 2024. Figure 2.2: Evolution of the wind power installation between 2015 and 2023. (Source:[4]) Figure 2.3: Evolution of the wind energy generation between 2015 and 2023. (Source:[5]) It is important to differentiate between installed power and generated energy. It may be the case that there is more installed power, but the energy generated is lower than in other years. This may be due to the weather conditions of the year, where the wind resource has been lower, the figure 2.3 shows the evolution of wind 6
Chapter 2. Wind energy situation in the peninsula energy generation in the peninsula. Once the evolution of installed capacity and wind power generation has been studied, the weight of this technology in the national energy mix can be analysed. The figure 2.4 illustrates the evolution of Spain’s energy mix, particularly focusing on the percentage of energy generated by wind power from 2007 to 2023. Over this period, there has been a notable upward trend in the contribution of wind energy to the overall energy mix. Starting at 9.6% in 2007, the percentage gradually increased, reaching a peak of 23.1% in 2021 before experiencing slight fluctuations in subsequent years. Figure 2.4: Evolution of the wind energy mix percentage between 2007 and 2023. (Source:[4]) Figure 2.5: Percentage contribution of each energy to the energy mix by 2023. (Source:[4]) In parallel, real data is studied for the nearest full year, in this case the year 2023, see image 2.5. To this end, the contribution of each technology to the energy mix is shown, with wind energy making the greatest contribution to the electricity market. 2.3 Wind parks in Guadalajara Given that the feasibility of installing the wind farm in Alcoroches will be studied, the wind farms in the province of Guadalajara are examinated. Castilla-La Mancha is the third autonomous community with the highest installed wind power, in 2022, more than 800 MW of new capacity was added to the region’s electricity system. With a total of 151 installations, the province that have the most wind turbines is Albacete [7]. At the same time, Guadalajara has 11 wind farms, even though it is the province with the greatest wind potential. In the specific case of the region, in many cases it is not viable to install new wind farms due to the protected natural areas. The wind resource is concentrated in the mountain ranges of the different mountain, most of which belong to the Red Natura 2000. Image 2.6 shows a geographical map of the province of Guadalajara, where it can be observed how the wind farms are distributed. The image shows the exact location of Alcoroches and how two wind farms are near the village. The closest wind farms to possible location of the wind park is less than 30 km away, the wind resource of these wind farms and Alcoroches is practically the same. 7
Chapter 2. Wind energy situation in the peninsula Figure 2.6: Map of the wind farms in the province of Guadalajara. (Source:[8]) A: SIERRA MENERA I Sierra Menera is the closest wind farm to Alcoroches, the two locations are 30 km apart. In the process of implementing the Menera’s wind farm, the wind study was done from the European Wind Atlas. The gross production of the wind farm is 136,071 MWh/year, which means a total of 2,452 equivalent hours per year[9], the characteristics of the wind farm are shown in table 2.1. Table 2.1: Characteristics of the Sierra Merera I wind farm. (Source:[10]) Wind Park Sierra Menera I Province Guadalajara Village Setiles and Tordesilos Power installed 40 MW Wind turbine GAMESA G80 Wind turbine power 2 MW Number of wind turbines 20 B: CALDEREROS The Caldereros wind farm is located at a distance of 36 km from Alcoroches. According to the Ministry of Development of the government of Castilla-La Mancha, the Caldereros wind farm is capable of supplying electricity to more than 12,000 families, producing a total of 95,900 MWh/year [11]. Table 2.2 shows the characteristics of the wind farm. 8
Chapter 2. Wind energy situation in the peninsula Table 2.2: Characteristics of the Caldereros wind farm. (Source:[12]) Wind Park Caldereros I Province Guadalajara Village Hombrados and Pobo de Due˜nas Power installed 37.80 MW Wind turbine VESTAS V90 Wind turbine power 1.8 MW Number of wind turbines 21 9
Feasibility study for installing a wind farm in Alcoroches Chapter 3 Applied regulation For the purpose of installing a wind farm in Alcoroches, it has to comply with the current regulations. With the final of studying the feasibility of installing a wind farm, European, national and regional laws must be followed. The wind energy sector is absolutely regulated, the laws published and approved in the Official State Gazette (BOE) establish the technical and nature protection conditions that wind farms must have. The ordinances that must be followed for the development of a wind farm are very extensive; in this document only the most important laws will be included. The MITECO, on its website, shows the regulations that must be followed to carry out the environmental assessment of wind energy programmes, below is part of this legislation [13]. 3.1 European regulation •UNE-EN IEC 61400-1 [14] This standard forms the basis for the design, manufacture, installation, operation and maintenance of wind turbines, as well as for the associated quality control process. •DIRECTIVE 2001/42/EC [15] This European directive addresses the effects of various plans and programmes on the environment. •DIRECTIVE 2011/92/UE [16] This directive applies to the assessment of the environmental effects of public and private projects likely to have significant effects on the environment. •DIRECTIVE 2003/96/CE [17] With the implementation of this regulation, the Community regime for the taxation of energy products and electricity is restructured. •DIRECTIVE 2019/944 [18] 10
Chapter 3. Applied regulation This directive establishes common rules for the generation, transmission, distribution, storage, and supply of electricity, as well as rules on consumer protection, with a view to creating truly integrated, competitive, consumer-centred, flexible, fair and transparent electricity markets in the Union. 3.2 Spanish regulation In order to know which standards need to be applied in the process of designing and assembling the wind farm, information has been extracted from [19]. •Real Decreto-ley 17/2021 [20] Due to the high tension in the national energy market, explained by the escalation of prices, the government opted to have this ordinance drafted. With the marginalist operation of the Spanish electricity pool, there was a large difference between the cost of energy production and how it was paid for. The paper sets out the urgent measures to mitigate the impact of the escalation of natural gas prices in the electricity markets. It explains how the mechanism to alleviate the excess remuneration of energy production plants works. •Real Decreto-ley 23/2021 [21] This legislation is a correction to RDL 17/2021. The measure contains urgent energy actions for the protection of consumers and the introduction of transparency in the wholesale and retail electricity and natural gas markets. The following laws can be grouped into different categories depending on the content of the text: ACCESS AND CONNECTION •Real Decreto-ley 12/2021 [22] The law explains the reasons for the adoption of urgent measures in the field of energy taxation and energy generation, and on the management of the regulation charge and the water use tariff. •Resoluci´on CNMC de 20 de mayo de 2021 [23] The text details the methodology and conditions for access and connection to the transmission and distribution networks of electricity production facilities. INTEGRATION INTO THE ELECTRICITY GRID •Orden TED/749/2020 [24] The ministerial order details the technical requirements for grid connection necessary for the implementation of the grid connection codes. • Norma t´ecnica de supervisi´on de la conformidad de los m´odulos de generaci´on de electricidad seg´un el Reglamento UE 2016/631[25] 11
Chapter 3. Applied regulation The objective of the conformity assessment is to obtain a final Certificate of MGE, in the document all the steps to follow to obtain this Certificate are detailed. ELECTRICITY MARKET •Resoluci´on de 6 de mayo de 2021, de la Comisi´on Nacional de los Mercados y la Competencia [26] The text drafted by the CNMC establishes the criteria for approving the operating rules for the daily and intraday electricity markets to adapt the supply limits to the European matching limits. 3.3 Castilla-La Mancha regulation •Decreto 34/2017 [27] The document explains how the authorisation procedures for electricity installations are regulated, together with the review and inspection regime. 12
Feasibility study for installing a wind farm in Alcoroches Chapter 4 Selection of the wind farm location 4.1 Legislative limitations As explained in the first pages of the project, the possible location of the wind farm will not be studied iteratively, but is defined from the outset. One of the fundamental aspects to think about when selecting a possible location for a wind farm is the wind resource for the exact location. The wind viability is not the only aspect to be studied, but there are currently other criteria that mark the feasibility of the installation. Part of these new criteria are included in Ley 21/2013, de 9 de diciembre, de evaluaci´on ambiental [28]. Among all the requirements to be taken into account in the execution of a wind farm installation plan, it should be noted that it cannot affect sites protected by Red Natura 2000 [29]. Another important aspect is REE’s capacity to incorporate new power into the electricity grid. It may be the case that the energy distributor cannot transport more energy because there is already congestion in the grid due to other energy-producing plants. In cases where the grid is saturated, the most viable option is not to proceed with the installation of the wind farm. When studying new projects of renewable energy plants, new electricity lines should be incorporated from each wind turbine to the transformation substation, under no circumstances may these pass through areas protected by Red Natura 2000. After having all the information provided by the ministry, it can be seen that the wind farm cannot be placed just anywhere within the municipal boundaries. In the image 4.1, the area marked in green corresponds to the Parque Natural del Alto Tajo, more than 190,000 ha of which were declared on the Red Natura 2000 protection list in January 2001 [30]. The following image shows the mountainous that belongs to the municipality of Alcoroches where there are no administrative restrictions in relation to the protection of the Parque Natutal del Alto Tajo. 13
Chapter 5. Geographical situation of the wind farm Figure 5.4: Relationship between roughness length and terrain type. (Source [38]). With the data provided by the Global Wind Atlas [39], it can be established that the roughness of the terrain at the location of the wind farm is 0.2 m. By studying the roughness of the terrain, it is possible to check how the behaviour of the velocity profile varies. With low terrain roughness, wind energy is practically not dissipated, which means that it has to get very close to the surface before the wind speeds drastically reduce. Visually, as can be seen in image 5.5, in those terrains with high roughness, the velocity profiles vary greatly as it gets closer to the surface. Figure 5.5: Wind profile for different terrain roughnesses. (Source:[36]) The image 5.5, shows the change of wind speed as an approach to the surface is done. With an initial geostrophic wind speed of 10 m/s, different scenarios are studied, taking into consideration different roughnesses. In the case D, with a roughness length of 0.0002 meters, the estimated wind at a height of 200 meters is almost 9 m/s. As it gets closer to the surface, the wind speed is reduced, arriving to a value of 6 m/s at an effective height of 0 m. If case B is evaluated, a different wind profile can be studied. The roughness for an urban terrain is approximately 0.5 metres. Following the same explanation as with the water wind profile, the wind varies as it approaches the surface. At a height of 200 metres the wind speed is almost 6 m/s while approaching the surface, the wind speed is reduced to a value of 1.6 m/s at an effective height of 0 metres. 20
Chapter 5. Geographical situation of the wind farm 5.4 Wind speed-up over hills An important aspect that affects the wind speed profile is the shape of the terrain. In image 5.6, it can be seen how the wind behaviour changes depending on what part of the mountain the study is done. When the wind encounters a hill, it is forced to flow around or over the obstacle. As the wind approaches the hill, it initially slows down due to friction with the ground. This slowing causes the wind to pile up in front of the hill, which causes an increase in pressure. As the wind flows over the crest of the hill, it accelerates due to the reduced pressure on the other side of the hill. According to the basic principles of incompressible fluid mechanics, an increase in fluid velocity is accompanied by a decrease in pressure. Therefore, as the wind accelerates, the pressure decreases, creating a pressure gradient force that accelerates the flow of air. Figure 5.6: Speed profile in the valley area and speed-up at the mountain top. (Source:[40]) Figure 5.7: Three-dimensional k−ϵ analysis of wind speed flow (top view) over a 3D hill. (Source:[41]) The magnitude of the speed-up over hills depends on many factors, such as the size of the mountain, the shape of the hill, wind speed, atmospheric stability and the roughness of the terrain. As done in several scientific articles such us [41], predicting wind speeds over complex terrain accurately is vital in the wind energy sector. Some techniques, such us the use of CFD experiments and the validation of these results with wind tunnel experiments, are common to quantify the speed-up effect over hills. Figure 5.7 shows the result of using Computational Fluids Dynamics models to estimate how the fluid over the hill would behave at 10 metres above the ground. In study [41], the use of k-w CFD analysis has been evaluated, reaching the conclusion that at the top of the hill the wind speed reaches a value of 17 m/s. As the purpose of this thesis is not to study speed-up over hills in depth, the explanation of study [41] is not done in detail. The main aspect is to understand that the wind accelerates as it approaches the top, as can be illustratively seen in picture 5.7. 21
Feasibility study for installing a wind farm in Alcoroches Chapter 6 Collection and study of meteorological data In order to continue with the thesis, it is proceeded to analyse the meteorological data, to this end, the first thing to be done is to compile meteorological information on the area near the wind farm. With a view to carry out a detailed analysis of the climatic conditions in Alcoroches, an exhaustive investigation of the meteorological stations located in the vicinity of the locality is assessed. The main objective is to collect accurate and relevant data that will provide reliable information on wind patterns in the region. 6.1 Weather station selection For this first phase, information has to be collected from weather stations in the areas surrounding Alcoroches, including those managed by governmental institutions as well as private stations. A clear distinction can be made between weather stations, those that pass rigorous quality tests and belong to the state’s network of automatic stations, and those that are managed by private users. The first group includes those stations that belong to the AEMET, where meteorological data are published periodically [42]. For the purpose of studying the feasibility of using the meteorological data, the distance in a straight line between the climatological station and Alcoroches is collected [43]. The results are shown in table 6.1. Table 6.1: Straight line distance from AEMET weather stations to Alcoroches. (Source: [43]) Weather station location Distance to Alcoroches (km) El Pedregal 23 Molina de Arag´on 27 Santa Eulalia del Campo 37 Once it has been verified that the state’s automatic stations are at a great distance from the location of the 22
Chapter 6. Collection and study of meteorological data wind farm, it is proceeded to search for weather stations of private users. To perform this task, a search is made for online weather portals where access to the information provided by user weather stations is available. The most popular weather portals are shown below: •Wunderground •Weathercloud •Meteoclimatic After analysing the positive and negative aspects of the various weather websites, it has been decided that Wunderground will be the main source of weather data. A key aspect for this decision is that this is the weather website with the greatest accessibility to weather registers, being able to acquire years of meteorological information. Having such a large amount of historical resources, it allows realising a good wind analysis of the area. Although Weathercloud and Meteoclimatic also offer useful information, Wunderground is found to better meet the specific needs for the study of Alcoroches. In the same way that has been done with the AEMET weather stations, the Wunderground stations closest to the village of Alcoroches are selected. The distance in a straight line between the climatological station and Alcoroches is shown in table 6.2. Table 6.2: Straight line distance from Wunderground weather stations to Alcoroches. (Source: [44]) Weather station location Distance to Alcoroches (km) Checa 5 Orea 7 Alustante 7 With a view to select the three weather stations to be studied, a comparative table is done. As the purpose of this section is to analyse the wind resource, only those variables related to wind are shown in table 6.3. Table 6.3: Comparative table of climatological information measured by different weather stations (Source: [45] [46] [47] [48] [49] [50]) El Pedregal Molina de Arag´on Santa Eulalia del Campo Checa Orea Alustante Wind speed Yes Yes Yes Yes Yes Yes Wind direction Yes Yes Yes Yes Yes Yes Wind gust speed Yes Yes Yes Yes Yes Yes Wind gust direction Yes Yes Yes No No No After being verified that all the six selected stations provide wind measurement data, the three climatological stations that best fit the purpose of the project have to be selected. Some criteria such as the geographical proximity, the quality of the weather station and the frequency of data measurement are compiled and evaluated. The selection of the different climatological stations is carried out by means of an OWA analysis. With this method, it is possible to select the most suitable stations to obtain relevant and accurate information 23
Chapter 6. Collection and study of meteorological data about the wind resource in the area near Alcoroches. Table 6.4 has been used to score the different stations. It contains three different criteria, which are explained below. •Distance: Distance from the weather station to the wind farm. • Frequency of mesurement: Frequency of measurement of the station, indicates how many minutes a wind measurement data is available. • Data quality: This parameter allows making an approximation of the quality of the wind speed measurement. As there are six stations, it has been decided that those belonging to AEMET show a high quality of data. This statement can be made because they undergo very thorough checks by the governmental authorities. In the case of stations that do not belong to the state network, are only subject to Wunderground controls, so the data may be somewhat distorted. In the analysis shown in table 6.5, it has been decided to score a 5 or a 2.5 depending on the owner of the station. Table 6.4: Comparative table of the studied parameters to carry out the ordered weighted averaging. (Source: [45] [46] [47] [48] [49] [50]) El Pedregal Molina de Arag´on Santa Eulalia del Campo Checa Orea Alustante Distance (km) 23 27 37 5 7 7 Frequency of mesurement (min) 60 60 60 5 5 5 Data quality AEMET AEMET AEMET Private Private Private Table 6.5: OWA comparative table of the different weather stations near the village of Alcoroches. (Own source) Critea Weight El pedregal Molina de Arag´on Santa Eulalia del Campo Checa Orea Alustante g p gxp p gxp p gxp p gxp p gxp p gxp Distance 30 2.75 82.5 2.25 67.5 1 30 5 150 4.75 142.5 4.75 142.5 Frequency of measurement 20 1 20 1 20 1 20 5 100 5 100 5 100 Data quality 50 5 250 5 250 5 250 2.5 125 2.5 125 2.5 125 SUM 100 352.5 337.5 300 375 367.5 367.5 OWA 0.705 0.675 0.6 0.75 0.735 0.735 Once the OWA analysis has been carried out, the selection of the weather station is done. After analysing several factors, the Checa weather station is chosen, first of all, it is the closest weather station to the area of interest. If the frequency of measurements is analysed, they are taken every five minutes, which guarantees a regular data collection. The quality of the data is also remarkable, with a score of 125 out of 250, indicating acceptable reliability. Overall, the OWA score of 0.75 is the highest among all options, closely followed by the Orea and Alustante stations. With all this, it can be assured that the Checa station is the most suitable for the analysis of wind data. 24
Chapter 6. Collection and study of meteorological data 6.2 Meteorological data acquisition Once it has been decided the weather station to analyse, it is essential to extract the data. As discussed in section 6.1, it has been concluded that the optimal is the one located in Checa. This station belongs to the Wunderground network, so it is necessary to access this website in order to download the historical weather data. Unfortunately, due to the unavailability of a direct download option in .csv or other computer format, the data had to be manually copied from the website and pasted into a spreadsheet, the data to be collected can be seen in image 6.1. This methodology involves a more laborious and error-prone process, as it requires manual manipulation of the data. However, in the absence of a direct download option, this is the only way to obtain the data and proceed with its analysis and study. It is important to take care when copying and pasting data to ensure the accuracy and integrity of the information collected. Figure 6.1: Meteorological data collected by the Checa weather station. (Source:[46]) The weather station provides detailed measurements of various weather variables at regular intervals. These include air temperature, dew point, relative humidity, wind speed and direction, as well as wind gust speed. It is also capable of recording atmospheric pressure, precipitation rate and precipitation accumulation, allowing the amount of rainfall to be monitored. The Checa weather station performs detailed measurements of several climatic variables, but the main focus is on wind analysis. For this, all collected data are copied and pasted into an Excel document and then a comprehensive wind speed analysis is performed. This method allows for a deeper understanding of the wind patterns in the study area and the impact they may have on the energy production of the wind farm. Furthermore, as part of the analysis process, the wind speed units are converted from kilometres per hour (km/h) to metres per second (m/s) for better interpretation and comparison, making the units belong to the international system. The final result in excel format can be seen in the image 6.2. Figure 6.2: Sample of the data collected on the Wunderground website and transferred to excel format. (Own source) The study collects meteorological data for a period of one year, starting on January 1st, 2023 and ending on 25
Chapter 6. Collection and study of meteorological data January 1st, 2024. All this information is stored, knowing that the measurement frequency of the weather station is every 5 minutes, it results to have approximately 104,000 wind records during the study period. This systematic data collection provides a detailed and accurate picture of wind speed throughout the year. The large amount of data collected ensures the reliability and robustness of the analysis, providing a solid basis for a better understanding of the wind patterns in the area. 6.3 Climatological data analysis Wind speeds are constantly changing, so it is necessary to describe them statistically. It is useful to construct a wind speed frequency model that is described by a continuous mathematical function rather than a table of discrete quantities. There are several functions that can be used to describe the frequency distribution of wind speed, the most commonly used are the Weibull function and the Rayleigh distribution. In wind analysis, the Weibull function is carried out to understand the frequency and intensity of winds at a specific location, this involves the study of the wind speed distribution over the year. As explained in section 6.2, wind speed data is collected at regular intervals and the Weibull distribution is used to model the probability of occurrence of different wind speeds. From this distribution, it can be determined how many hours per year the wind reaches certain specific speeds, which provides crucial information for the wind farm planning. This analytical approach allows a detailed understanding of the availability and variability of the wind resource in the Alcoroches wind farm. 6.3.1 Wind frequency distribution Speed variation with height To study the variation of speed with height, the equations (6.1) and (6.2) are used to describe the speed profile. The first equation (6.1), uses the quotient of logarithms where the different characteristic heights are taken into account as well as the wind speed measured by the meteorological station. v(h) = vref ·ln h z0 lnhref z0 (6.1) •vref : Reference speed, measured by the meteorological station (m/s) •h: Height to which the velocity is to be extrapolated (m) •href : Height at which speed is measured (m) •z0: Terrain roughness (m) The second equation (6.2) can be considered a particular case of equation (6.1). Applying the properties of logarithms, it can be concluded that equation (6.1) becomes equation (6.2) when h z0=e. Equation (6.2), has the same variables as equation 6.1 except for the use of the Hellman’s parameter, this 26
Chapter 6. Collection and study of meteorological data variable takes into account the height at which the velocity is to be corrected as well as terrain roughness data. v(h) = vref ·h href α (6.2) α=1 ln h z0(6.3) •α: Hellman’s exponent The first equation (6.1) is preferred because of its accuracy, as it uses the ratio of logarithms considering the characteristic heights and the velocity measured by the weather station, whereas the equation (6.2) does not consider such a ratio. Wind frequency distribution As specified in the annexes document in the wind frequency distribution section, the frequency diagram is made. The methodology used in the process is clearly specified in the annex, just as the MATLAB code can be found in the same document. Figure 6.3: Wind speed frequency diagram at 100 metres. (Own source) Figure 6.3 shows the velocity distribution for the real data from the Checa meteorological station, once the wind speed has been corrected for a height of 100 metres. The same study can be found in the annexes document for heights of 50 and 200 metres. 27
Chapter 6. Collection and study of meteorological data 6.3.2 Weibull distribution Before explaining the Weibull distribution function in depth, other important statistical measures for wind analysis are discussed. An important aspect is to know the average annual speed in the area of the wind farm, which can be calculated as follows: <x>=1 n n X i=1 xi(6.4) If it is wanted to know the deviation of the data set from the arithmetic mean, the standard deviation is defined as: σ2=1 n−1 n X i=1 (xi−<x>)2(6.5) The Weibull distribution function is dependent on two parameters called A and k. A value is called the scale factor, this value affects the horizontal position of the distribution curve. The k value is called the shape factor of the distribution, depending on this, the curve is narrower or wider. f(v) = k A·v Ak−1 ·e−(v A)k (6.6) Having explained the above, the expression for the cumulative Weibull frequency is as shown below: F(v)=1−e−(v A)k (6.7) Non-linear fit to the Weibull function In order to fit the data to the Weibull function, the A and k values have to be determined. For this purpose, the non-linear fit is performed using MATLAB, making use of the nlinfit function available in the software. The nlinfit function in MATLAB is used to fit non-linear models to experimental data. It uses the least squares method to estimate the model parameters that best fit the observed data, in this case the relative frequency values. With the script that has been developed, it has been possible to calculate the values that define the Weibull distribution. Table 6.6: Values of the Weibull parameters for the different heights calculated with data from the Checa weather station. Results obtained by non-linear fitting, using MATLAB code. (Own Source) Height (m) A k 50 7.923 1.331 100 9.017 1.351 200 10.071 1.358 28
Chapter 6. Collection and study of meteorological data Figure 6.4: Approximation of the Weibull distribution for 100 m height using MATLAB approximation. (Own source) The procedure for calculating the Weibull function can be found explained in detail in the MATLAB code section in the annexes document. In the same way, it can be consulted the images of the approximation to the Weibull function for the heights of 50, 100 and 200 metres, having made the non-linear approximation. Linear fit to the Weibull function To extract the e A and k values, the cumulative frequency function is used as it is easier to manipulate. The entire mathematical procedure is explained in detail in the annexes document. Once the linear regressions have been performed, the parameters A and k are given in the table 6.7. Table 6.7: Values of the Weibull parameters for the different heights calculated with data from the Checa weather station. Results obtained by linear fitting, using EXCEL. (Own Source) Height (m) A k 50 7.283 1.205 100 8.788 1.314 200 9.884 1.316 29
Chapter 7. Study and selection of wind turbines Wind speed at which the wind turbine stops operating. The windmill is switched off to ensure structural integrity. The angular speed of the rotor must be limited so that the centrifugal forces do not damage the structure of the wind turbine; this maximum rotational speed occurs when the rated wind speed is reached. As the incident wind speed increases, the rotational speed of the wind turbine remains constant, thus avoiding material fatigue and excessive noise emissions. In the figure 7.1, IV zones can be distinguished, which are detailed below. • Region I: The incident wind speed is very low, the rotor is not able to overcome the inertial forces of the system and remains stationary. • Region II: It encompasses the entire area between the velocities Vcut−in and Vrated . This is the region in which the maximum power points operate. • Region III: It encompasses the entire area between the velocities Vrated and Vcut−out . In this region, the power generation is limited to a nominal value. • Region IV: Region with winds above Vcut−out . This corresponds to the area where the wind speed is so high that the wind turbine has to be shut down to avoid possible structural damage. Another important aspect to take into account when studying a wind turbine is the power coefficient. This parameter is a measure of the efficiency of the wind turbine. It is calculated by doing the quotient between the electrical power delivered by the wind turbine and the wind power input. By means of this value, it is possible to study the wind speed at which the turbine has the highest efficiency. The wind turbine manufacturers provide the data of the power curves under certain conditions. These results are obtained under normal conditions, the density has a value of 1.125 kg/m3 , a temperature of 15 ◦C and an atmospheric pressure of 1 atm. The equation 7.1 shows a way of quantifying the energy extractable by a wind turbine. The maximum energy that can be obtained depends on the wind speed and the air density, these are the two variable parameters. P(ho) = 1 2·Cp(λ, v)·ρ0·π·R2·v3(7.1) Where: •ρ0: sea level air density, standard conditions (kg/m3) •R: Rotor diameter (m) •Cp: Power coefficient. Maximum ratio between incident and extraneous power. •v: Fluid velocity at hub height (m/s) As can be seen, the extractable power is modified by the density of the fluid. Given that the wind farm will be located at a height of 1500 m, it is necessary to rectify the power curves provided by the manufacturers. It is 36
Chapter 7. Study and selection of wind turbines for this reason that the correction of the density with height is made, using the ISA atmosphere (Atmosphere International Standard), the variation of the density with height can be modelled using equation 7.2. ρ(h) = ρ01−λ·h T0 g0 Rλ −1 (7.2) Where: •ρ0: Density of air at sea level, has a value of 1.225 kg/m3 •R: Specific constant of gases, has a value of 287 m2s−2K−1 •T0: ISA temperature at sea level has a value of 288 K. •g0: Value of gravity at sea level, with a value of 9.81ms−2 •h: Wind turbine hub height above sea level (m) •λ: Variation of temperature with altitude, has a value of −6.5Kkm−1 Once the density at the height of the wind farm has been calculated, the power curve can be corrected. If the system of equations formed by 7.1 and 7.2 is taken, thus obtaining the power curve corrected for height, this is expressed in equation 7.3. P(h) = P(ho)·ρh ρ0(7.3) In order to facilitate the calculations throughout the work, the hub height of all wind turbines is estimated to be the same. This approximation is only made for the calculation of the density ratio, for the calculation of the energy production no such approximation is made. The density quotient has a value of 0.967, so the power curve can be corrected as follows: P(h) = P(ho)·0.967 (7.4) 7.2 Wind turbine study As specified in the job requirements, only companies that manufacture in Europe will be considered. Since there are currently a large number of companies, only three will be chosen. The following is a list of the three most important. •Vestas (Denmark) •Siemens-Gamesa Renewable Energy (Spain) •Nordex Group (Germany) 37
Chapter 7. Study and selection of wind turbines For the purpose of carrying out a detailed study of the turbines, only those with power curve information are selected. Initially, the official websites of the companies are used, but neither the price of the wind turbines nor the power curve data are available there. Given that it is tried to be rigorous in the treatment of the information, an email is written to the three companies to request more information on the turbines they sell. The same information was provided in all three letters, requesting the unit cost of the wind turbines, as well as the power curve. Despite attempts to collect information, the companies did not provide the necessary data. As an alternative, secondary sources were used, specifically information collected from a website specialised in wind turbine models. On the website [53], only those models for which information on the power curve was available are selected. Subsequently, the important information of these models is collected, from the cut-in speed to the possible hub heights. All relevant information is displayed in the table 7.2. Table 7.2: Compilation of all wind turbines for which power curve information is available. (Source:[53]) Company Model Rated power (kW) Cut-in wind speed (m/s) Rated wind speed (m/s) cut-out wind speed (m/s) Wind class Hub height (m) N60 1.3 2.5 15 25 la 60/65/69/85 N62 1.3 2.5 15 25 la 60/69/80/90 N70 1.5 3.5 13 25 lla 65/85/98/114 N77 1.5 3 11 25 llla 62/85/90/111 N90 Beta 2.3 3 12 25 lla 80/100/104 N177 Gamma 2.4 3 11 20 llla 91/120/141 N80 Alpha 2.5 4 15 25 la 60/80/100/105 Nordex N90 2.5 3 13.5 25 la 70/75/80/100/120 N100 Gamma 2.5 3 12 20 lla 75/100 N177 Delta 3 3 12 25 lla 91/120/141 N131/3000 Delta 3 3 11 20 llla 99/114/134 N100 Delta 3.3 3.5 13.5 25 la 75/85/100 N131/3300 Delta 3.3 3 11 20 llla 134/164 N177/3600 Delta 3.6 3 13 25 lla 91/106/141 N131/3600 Delta 3.6 3 11 20 llla 84/106/112/134 V63 1.5 4 16 25 la 60 V63-1.65 1.65 4 15 25 la 60/78 V63-1.75 1.75 4 16 25 la 60/67/78 V80 1.8 4 15 25 la 60/67/78 V90 2 4 13 25 lla 80/95/105 V112-3.08 3.08 3 12 25 lla 84/94/119 Vestas V112-3.3 3.3 3 13 25 lb 84/94/119/140 V117-3.3 3.3 3 13 25 lla 91/116 V126-3.3 3.3 3 12 22.5 llla 117/137 V112-3.45 3.45 3 13 25 lla and llla 84/94/119/140 V126-3.45 3.45 3 12 22.5 lla 117/137/147/149 V136-3.45 3.45 3 10 22.5 llla 82/112/132/149 G80 2 3.5 12 25 la 60/67/78/100 G83 2 4 13.5 25 lla 67/78 G97 2 3 11 25 llla 78/90/100/120 G114-2 2 2.5 10 25 llla 93/120/140 G114-2.5 2.5 2 10 25 lla 64/80/93/120/140 Gamesa G126-2.5 2.5 2 10 25 llla 84/102/129 G132-3.3 3.3 2 10 25 lla 84/97/114/134 G128-4.5 4.5 1 12 27 llla 81/120/140 G128-5 5 2 14 27 la 81/95/120/140 G132-5 5 1.5 13 27 lla 95/120/140 The table 7.2 shows all wind turbines for which power curve information is available, not all the models shown above are optimal for the Alcoroches wind farm. to select the optimal ones, it is essential to know the 38
Chapter 7. Study and selection of wind turbines wind conditions at the wind farm. In the section 6.4 the wind atlas data has been found to be reliable and is therefore used. As shown in the wind atlas [39], for the location of (40.62411ºN, -1.69593ºE) and a height of 100 metres, the average wind speed is 8.28 m/s . With this data, either a turbine designed for wind class II or III can be chosen. One of the requirements of the project was to do the study with nine different turbines, given that there are three companies, three turbines per company will be chosen. With the final of making the selection and maximising the energy production, the procedure is followed: Figure 7.2: Turbine selection process. (Own Source) In the wind turbine selection process, three technical criteria that take into consideration. Firstly, the classification of the turbine in relation to the wind class is evaluated, choosing only those that belong to class II or III. Once the turbines that meet this criterion have been identified, their rated speeds are compared, giving priority to the turbine with the lowest rated speed. Finally, among the turbines that meet the above requirements, the one with the lowest cut-in speed is selected. The procedure described above has been followed, as it is the one that maximises energy production. Following the criteria described above, it is concluded that the turbines shown in the table 7.3 will be studied. 39
Chapter 7. Study and selection of wind turbines Table 7.3: Potential wind turbines to be installed. (Source:[53]) Company Model Rated power (kW) Cut-in wind speed (m/s) Rated wind speed (m/s) Cut-out wind speed (m/s) Wind class Final hub height (m) N77 1.5 3 11 25 llla 111 Nordex N177 Gamma 2,4 3 11 20 llla 120 N131/3600 Delta 3.6 3 11 20 llla 106 V112-3.08 3.08 3 12 25 lla 119 Vestas V126-3.3 3,3 3 12 22.5 llla 117 V136-3.45 3.45 3 10 22.5 llla 112 G114-2 2 2.5 10 25 llla 120 Gamesa G126-2.5 2.5 2 10 25 llla 102 G132-3.3 3.3 2 10 25 lla 114 7.3 Wind energy production In order to study the energy produced, a distinction is made between net and gross energy. The aspects considered for the study are detailed below. 7.3.1 Net energy generated by the wind turbine To calculate the energy produced by a wind turbine, the power curves as well as the Weibull distribution are used, to be precise, the mathematical procedure is explained in an integral form. The equation 7.5 shows the differential way of calculating the energy that the turbine is able to generate. dE =P(v)·f(v)dv (7.5) The equation 7.6 shows the energy that the turbine is able to generate in one hour. The value of this integral is the energy that the turbine is able to generate if the winds had the behaviour of the Weibull distribution. E=Zvc−o vc−i P(v)·f(v)dv (7.6) To ease the calculus, the integral is decoupled into two velocity sections, these are shown in the equation 7.7. E=Zvr vc−i P(v)·f(v)dv +Zvc−o vr Pr·f(v)dv (7.7) For the feasibility study, the total energy produced over the year has to be calculated. The equation 7.7 has to be multiplied by the total number of hours per year, thus it determines the annual gross energy produced. Eyear−gross = 8760 ·"Zvr vc−i P(v)·f(v)dv +Zvc−o vr Pr·f(v)dv#(7.8) The variables involved in the above equations are: •v: Velocity (m/s) 40
Chapter 7. Study and selection of wind turbines •vc−i: Cut-in velocity (m/s) •vr: Rated velocity (m/s) •vc−o: Cut-out velocity (m/s) •P(v) : Wind turbine power for each speed value (kW) •Pr: Rated power (kw) •f(v) : Speed-dependent Weibull distribution With the finale of obtaining the energy extracted by a wind turbine, a MATLAB code has been developed. This involves the power curves of each wind turbine and the precise Weibull distribution for each hub height. A script has been developed in parallel to the energy production calculation that allows the Weibull correction for the height. The IDAE wind atlas provides the Weibull curve for heights of 50, 100 and 200 metres. Looking at the possible hub heights of the selected wind turbine hubs in the table 7.3, it is shown that this distribution has to be corrected. No wind turbine is designed to be mounted at a height of 100 metres, so the study will be carried out with those heights that exceed 100 m and are closest to this value. The correction of the Weibull parameters has been done similarly as in section 6.3.1. It is important to note that the results in the table 7.4 are an approximation, as it has been assumed that the frequency distribution does not change. One of the variables that has been modified is the velocity vector, which has been adjusted for the characteristic height of each hub. Table 7.4: Correction of Weibull parameters for hub height. (Own Source) Company Model Final hub height (m) Corrected A Weibull parameter Corrected k Weibull parameter N77 111 8.23 1.85 Nordex N177 Gamma 120 8.31 1.86 N131/3600 Delta 106 8.19 1.84 V112-3.08 119 8.30 1.86 Vestas V126-3.3 117 8.28 1.85 V136-3.45 112 8.24 1.85 G114-2 120 8.31 1.86 Gamesa G126-2.5 102 8.15 1.83 G132-3.3 114 8.26 1.85 To calculate the energy production in region II of the wind turbine, where the power is not constant, an approximation using the polyfit function has been performed. The approximation facilitates the estimation of the power output as a function of wind speed. To determine the total energy generated, the power curve is divided into two different sections. The first section is from cut-in speed to rated speed, while the second section is from rated speed to cut-out speed. In order to calculate the energy production, the wind turbine power has been multiplied by the Weibull distribution, considering a wind speed interval of 0.1 m/s. Once the energy has been calculated for the whole speed range, the results are added up. 41
Chapter 7. Study and selection of wind turbines Having a speed range of 0.1 m/s allows a very tight solution to be obtained. With this resolution, it is possible to correctly capture the non-linear part of the power curve. Once all the calculations have been carried out, the annual gross power is shown in the table 7.5. Table 7.5: Gross annual energy production for the 9 selected wind turbines. (Own Source) Company Model Gross annual energy production (MWh) N77 10,205 Nordex N177 Gamma 20,472 N131/3600 Delta 28,618 V112-3.08 22,460 Vestas V126-3.3 25,920 V136-3.45 29,346 G114-2 18,220 Gamesa G126-2.5 22,311 G132-3.3 27,164 7.3.2 Gross energy generated by the wind turbine To calculate the gross energy, the net energy value has to be corrected by means of coefficients. In the following lines, the losses that a wind turbine has are detailed, the information has been extracted from [54]. • Availability losses: They occur when there are unwanted stoppages. They usually occur due to breakdowns. K1= 0.980 • Transformation losses: Generated by the processes of voltage boosting and transport to the electrical connection, losses typically range from around 3%. K2= 0.970 • Substation maintenance losses: They occur when power is not transferred to the grid, usually due to maintenance work. K3= 0.997 Finally, the operating coefficient of the turbine can be calculated doing the product of the three coefficients described above. Kturbine =K1·K2·K3= 0.948 (7.9) Furthermore, as explained in section 7.1.2, the power curve has to be rectified, as the wind farm is located at 1500 metres above sea level. With all this, the annual net energy produced from the wind turbine can be 42
Chapter 7. Study and selection of wind turbines calculated as follows: Eyear−net =Eyear−gross ·Kturbine ·ρh ρ0(7.10) Substituting numerically, the annual net energy can be calculated with the following equation. Eyear−net =Eyear−gross ·0.917 (7.11) Table 7.6: Net annual energy production for the 9 selected wind turbines. (Own Source) Company Model Net annual energy production (MWh/year) N77 9,358 Nordex N177 Gamma 18,772 N131/3600 Delta 26,243 V112-3.08 20,596 Vestas V126-3.3 23,769 V136-3.45 26,910 G114-2 16,708 Gamesa G126-2.5 20,459 G132-3.3 24,910 7.4 First economic analysis To select the most suitable wind turbine for the renewable energy plant, it has been considered that an initial economic analysis should be carried out. This only takes into account 3 parameters: the initial cost of the wind turbine, the future price of energy and the maintenance costs of the machine.In order to make the final selection of the turbine, an OWA analysis will be carried out, taking into account the economic analysis, as well as the energy production shown in table 7.6. 7.4.1 Wind turbine price During the development of the project, it was tried to find a detailed and reliable cost information for the 9 selected wind turbines, unfortunately, this information was not able. As explained in the section 7.2 of the thesis, several companies were contacted and none of them provided the requested data. For this reason, in order to calculate the unit price of each turbine, an approximation of the cost of the wind turbines is used. The calculation is made with an equation extracted from the Plan de Energ´ıas Renovables 2011-2020 (PER) [55]. This formula takes into account both the hub height and the power of the wind turbine, as shown below. 43
Chapter 7. Study and selection of wind turbines WTc= [((hh−66) ·0.005 ·840,000) ·Pwt + ((Pwt −2) ·0.06 ·840,000] ·I(7.12) •WTc: Wind turbine cost (e) •hh: Wind turbine hub height (m) •Pwt: Wind turbine power (MW) •I: Cumulative inflation rate from 2011 to 2023 Originally, the equation 7.12 did not incorporate the inflation term. The function was calculated for the year 2011 and it has been necessary to correct the cost of the machine by multiplying the cumulative inflation between 2011 and 2023. To calculate the accumulated inflation, it is necessary to know the value of the average inflation per year in Spain, this data has been extracted from [56]. Cumulative inflation is realised by the equation 7.13. CPI acum = 2023 Y i=2011 (1 + CPIi) (7.13) The cumulative inflation for the years 2011-2023 has a value of 1.26. The above result is represented as a percentage of one, which means that prices since 2011 have risen by 26%. The calculation has been made using general inflation, without taking into account industry-related. Table 7.7: Cost of wind turbines corrected for inflation value. (Own Source) Company Model Cost 2011 (€) Cost 2024 (€) N77 1,518,300 1,919,483 Nordex N177 Gamma 2,580,480 3,262,325 N131/3600 Delta 3,709,440 4,689,593 V112-3.08 3327240 4206403 Vestas V126-3.3 3,544,380 4,480,919 V136-3.45 3,637,620 4,598,796 G114-2 2,133,600 2,697,365 Gamesa G126-2.5 2,503,200 3,164,626 G132-3.3 3,502,800 4,428,352 7.4.2 Future energy prices During the preparation of this report, it became clear that the current price of energy is very variable. It is therefore necessary to collect sufficient information on the future value of this electricity in order to be able to carry out the first economic analysis. The current regulations do not provide premiums for wind power generation, so that any future income that 44
Chapter 7. Study and selection of wind turbines the wind farm may receive will come exclusively from the sale of electricity. Given that the selling price per megawatt hour (MWh) varies daily, it is imperative to establish a fixed price to guarantee the wind farm’s income. The estimate of this price is set by the Operador del Mercado Ib´erico de Energ´ıa (OMIE), the energy prices have been collected from 2026 to 2034, which is the last year for which OMIE makes predictions.[57]. Table 7.8: Wholesale electricity price evolution 2026-2034. (Source: [57]) Year Electricity price (e/MWh) 2026 51,75 2027 51,13 2028 50,75 2029 50,50 2030 50,50 2031 50,50 2032 49,85 2033 49,77 2034 49,71 With the above data, the graphical representation is made in EXCEL, in order to subsequently calculate the price trend line. Figure 7.3: Electricity price evolution 2026-2034. (Own Source) A linear trend line with the equation y = − 0 . 234 ·x + 51 . 666 has been used, substituting the values up to the year 2044, it completes the table 7.9. 45
Chapter 8. Wind park design Figure 8.5: Distribution of the wind turbines in the Sierra Merena I wind farm, located in Tordesilos. (Own Source) Table 8.2: Left: Identification and geographical location of the Sierra Menera I wind turbines. Right: Normalised distance between wind turbines (Own sorce). Sierra Merena I Sierra Merena I Wind turbine identifier Latitude (º) Longitude (º)Group of turbines Distance (m) Rotor diameter (m) Non-dimensional distance 22 40,6879299 -1,536195 22 and 23 303 80 3.79 23 40,6901831 -1,5398413 23 and 24 418 80 5.23 24 40,6898822 -1,5447991 23 and 25 252 80 3.15 25 40,6919372 -1,5405861 24 and 25 425 80 5.31 26 40,6937436 -1,5420461 25 and 26 244 80 3.05 27 40,6963087 -1,5435175 26 and 27 254 80 3.18 28 40,6978928 -1,5451366 27 and 28 264 80 3.30 29 40,7029687 -1,5547039 29 and 30 275 80 3.44 30 40,7053048 -1,5531808 30 and 31 531 80 6.64 31 40,7098974 -1,5537382 31 and 32 300 80 3.75 32 40,7127537 -1,553817 32 and 33 323 80 4.04 33 40,7150515 -1,5558866 33 and 34 325 80 4.06 34 40,7176305 -1,5577319 35 and 36 308 80 3.85 35 40,7198906 -1,5599942 36 and 37 277 80 3.46 36 40,7223669 -1,5600996 37 and 38 375 80 4.69 37 40,7248784 -1,5602051 38 and 39 467 80 5.84 38 40,7282664 -1,5603665 39 and 40 393 80 4.91 39 40,7324927 -1,5608665 40 and 41 417 80 5.21 40 40,7360632 -1,5612803 41 40,7395672 -1,5630352 The non-dimensional distance is calculated as the quotient of the distance between wind turbines and the rotor diameter. As established in the [59] study, the distance between wind turbines ranges from 2.11 diameters to 6.64 diameters. Once the values for each wind farm are available, the arithmetic mean can be calculated, the values are shown in the table 8.3. 52
Chapter 8. Wind park design Table 8.3: Average, maximum and minimum distance between wind turbines for the Sierra Menera I and Caldereros I wind farms. (Own Source) Non-dimensional distance Minimum distance 2.11 Maximum distance 6.64 Mean Caldereros I 2.93 Mean Sierra Merena 4.27 Mean two wind parks 3.69 When designing the layout of the Alcoroches wind farm, the wind turbines will be placed in such a way that they meet the following criteria. 1. All wind turbines shall be positioned perpendicular to the prevailing wind, facing WSW. 2. The location of the critical wind turbine is decided. A critical wind turbine is understood to be one that is right on the boundary with the urban nucleus, complying with the minimum distance required between the wind turbine and the locality, as set out in current legislation. An attempt is made to install the wind turbine as close to the urban nucleus as possible, always in compliance with the legislation, in order to optimise the number of wind turbines to be installed. 3. Once the location of the first wind turbine is known, the rest of the wind farm is constructed. Using the AutoCAD program, it is ensured that the parallel and perpendicular distances are correct. The parallel distance between wind turbines is set to three diameters and the perpendicular distance to five diameters. To some extent, it is the location of the first turbine that determines the layout of the entire wind farm. 4. Using AutoCAD support, the rest of the cells are built according to the last wind turbine installed, knowing that it is the V136-3.45, with a diameter of 136 metres. As explained above, the cells will have a size of 3x5 diameters, which is equivalent to 408x680 metres. Finally, after following the procedure, the wind farm design is obtained. Using the procedure described above, the turbines are almost not affected by the wake effect and are placed at the maximum height of the hill in order to optimise the wind resource. 53
Chapter 8. Wind park design Figure 8.6: Layout of the wind farm. (Own Source) From the image 8.6, it can be seen that the green circles are the wind turbines, the one marked in red is the critical one. In parallel, the grids represent where the turbines cannot be placed, as they would be influenced by the disturbed wind. Table 8.4: Geographical location and altitude of the wind turbines to be installed in Alcoroches. (Own Source) Alcoroches wind farm Wind turbine identifier Latitude (º) Longitude (º)Altitude above sea level (m) 1 40,6260009 -1,7395798 1500 2 40,6308944 -1,7412308 1493 3 40,6345304 -1,7372146 1504 4 40,6287143 -1,7344893 1499 5 40,6236255 -1,7302397 1518 6 40,6314604 -1,7254658 1544 7 40,6260555 -1,7236366 1593 8 40,6214539 -1,7167175 1556 9 40,6321085 -1,7159292 1602 10 40,6263013 -1,7127937 1609 54
Chapter 8. Wind park design 8.3 Calculation of the electricity production of the wind farm With the final of studying the decrease in energy production in the wind farm, the SAM (System Advisor Model) software is used. The software has been developed by the National Renewable Energy Laboratory and allows a technical-economic analysis of renewable energy projects. The information that has to be entered into the programme to carry out the energy simulation is explained below. 1. Choice of the type of analysis to be carried out It has to be decided which type of renewable project is wanted to analyse, in the precise case a Wind no financial model is chosen as this will be done at a later stage. Figure 8.7: Renewable study that has been carried out. (Own Source) 2. Wind resource The second step is to enter the wind data for the area, to do this, the information provided by the IDAE will be used, which can be seen in the image 8.2. By transferring the wind speed and wind direction data together with the frequency, an EXCEL table can be generated. Once all the information has been compiled, it is then entered into the SAM software. 55
Chapter 8. Wind park design Figure 8.8: Wind distribution parameters entered the SAM software. (Own Source) 3. Wind turbine The third step in calculating the extractable energy of the wind farm as a whole is to specify the wind turbine. In this case, the selected turbine does not appear in the SAM database, so the necessary parameters have to be detailed. Figure 8.9: Wind turbine parameters entered the SAM software. (Own Source) 4. Wind farm The fourth phase is to enter the layout of the wind farm, inserting the exact location of the wind turbines. 56
Chapter 8. Wind park design Figure 8.10: Turbine layout parameters entered the SAM software. (Own Source) Another fundamental aspect is how the wake effect is treated, in this case the wind farm model has been chosen. By making this selection, it is ensured that all disturbances of the turbines are taken into account, regardless of the distance between them. In SAM, as in different software, it makes different simplifications of the wind farm. In this case, it is assumed that all the turbines are at the same height, which is not true. This approximation means that the energy that the plant is capable of producing is greater than that calculated by the software. Given that this is an academic work, it is considered that the energy approximated by the software coincides with the real one. 5. Wind farm losses As explained earlier in the body of the work, turbines are subject to efficiency losses. These are explained below: • Availabiliy losses: Energy-based availability is the amount of energy produced as a percentage of the total amount of energy that the wind plant could have captured if turbines were always ready to generate power. • Electrical losses: Electrical losses from a wind farm are the energy losses inherent in energy transmission in collector lines, transformers, and other site equipment and transmission to the point of revenue metering. 57
Chapter 8. Wind park design • Turbine performance losses: Turbine performance losses represent the amount of energy that is not produced by a wind turbine at a given wind speed. • Operational strategies losses: The deliberate management of a wind plant to reduce the amount of energy compared to what is possible from the available resource. Having carried out all the above steps, the wind farm produces a total of 148,028 MWh/year. 58
Feasibility study for installing a wind farm in Alcoroches Chapter 9 Technical implementation of the wind farm When studying the construction process of the Alcoroches wind farm, it is necessary to compartmentalise the tasks. These tasks can be classified into three main groups: •Access roads and internal roads •Foundations and platforms for wind turbines •Electrical installation 9.1 Access roads and internal roads The purpose of the roads is to provide an access route to the wind turbines, reducing the degree of impact on the environment. For this reason, the use of existing roads is optimised, building new lanes where necessary, always taking into account the criterion of minimum impact on the environment. The project envisages the adaptation of existing roads that do not meet the minimum requirements for the movement of wind turbine assembly and maintenance vehicles. Roads shall comply with the following technical specifications: •Maximum slope: 8◦(14 %) for straight sections and 4◦(7 %) para for curved sections. •Minimum roadway width: 5 m •Minimum radius of curvature: 30 m The internal roads will start at the end of the accesses and will reach the base of the wind turbines that make up the wind farm. The internal roads will serve as conduits for medium voltage cables. The wind turbines have been placed as close to the paths as possible in order to minimise the excavation of earth on the hill and to communicate between the wind turbines along the existing paths. 59
Chapter 9. Technical implementation of the wind farm Initially, the Alcoroches wind farm has been designed to have the layout shown in the image below. Figure 9.1: Location of the turbines of the Alcoroches wind farm. (Own Source) The tasks to be performed can then be implemented in working groups, as shown below: −Cleaning and clearing of vegetation cover on new and existing roads. −Excavation of land where required. −Creation of the embankment using sediments from the previous excavation. −Extension of a bottom and top layer of zahora. −Road compaction by heavy machinery. − Repair of imperfections that have appeared during the execution of the different roads. They are repaired by pressing the ground. 9.2 Foundations and platforms for wind turbines In section 7.2, the basis for the selection of the wind turbine has been specified. Finally, after carrying out the analysis, it was decided to install the V136-3.45 with a hub height of 112 metres. The foundations of the wind turbines must be adapted to the geotechnical conditions of the Alcoroches wind farm. The foundations must follow the technical criteria of the wind turbine manufacturer so that the wind turbine is able to withstand the mechanical demands. The excavation of the foundation must be carried out by mechanical means, using appropriate methods for the fragmentation of the rock. The area where the wind turbines are to be installed is characterised by rocky 60
Chapter 9. Technical implementation of the wind farm terrain, which is why it is essential to have rock fragmentation machinery. The excavation for the foundations of the wind turbines will consist of a circular base with a diameter of 30 metres. The space required for the construction and assembly of the wind turbines is mainly determined by the area occupied by the cranes and the space required to carry out all the manoeuvres during assembly. Taking all of the above into account, an area of land measuring 40x40 metres will be flattened so that the complete assembly of the wind turbine can be carried out. 9.3 Electric installation In this section of the project, only the internal electricity grid is taken into account. Once the energy leaves the wind farm, it is the responsibility of REE to manage it. The power generated in the wind farm has to have its voltage raised in order to minimise electrical losses. This voltage boosting process has two transformation levels, the first one raises the output voltage of the wind turbines to the internal distribution voltage of the wind farm. The second raises the voltage of the wind farm’s internal medium voltage network to the high voltage level of the distribution company’s network, which in the case of Alcoroches is managed by REE. The electrical installation of the park consists of the following elements: •Wind turbines: Energy production element. • Transformation centre: Each wind turbine has a transformation centre associated, the purpose of which is to facilitate connection to the medium voltage line. • Medium voltage wind turbine line: It connects all the transformation centres of the different wind turbines by means of a 20 KV underground power line. It transports all the energy to the transformer substation. 9.3.1 Low voltage installation The low voltage circuit is the one located in the nacelle of each wind turbine. It is the first energy transformation process before it is fed into the wind farm’s internal grid. Table 9.1: Electrical characteristics of the wind turbine V136-3.45. (Source: [60]) Generation Permanent magnets Rated power 3.45 MW Voltage 400 V Frequency 50/60 ±6% Hz Protection IP 54 One aspect to take into consideration is the control of reactive power, it is essential that this is within the limits established by the manufacturers. 61
Chapter 10. Economic analysis allows each value to be calculated. For the specific case of the project, the EXCEL tool has been used. •Net present value Net present value is used to determine whether or not the investment of the wind farm will be profitable down the line. The NPV of an investment is the sum of all future cash flows over the investment’s lifetime, discounted to the present value. [65]. The result is expressed in monetary units. Mathematically it can be expressed as follows: NPV = n X t=1 Ct (1 + kt)t−C0(10.1) Where: –C0:Initial investment –Ct:Cash flow for year t –n: Project duration in years –kt:Applicable discount rate for year t •Return on investment Return on Investment (ROI) is a financial measure that assesses the profitability of the wind farm investment. It is calculated as the ratio between the net benefit obtained and the total cost of the investment, expressed as a percentage [66]. ROI =Net profit Investment·100 (10.2) •Internal Rate of Return IRR is a discount rate that makes the net present value (NPV) of all cash flows equal to zero in a discounted cash flow analysis [67]. The result is expressed as a percentage. Equation 10.1 is used, taking into consideration the same variables, the differentiating fact is that it has to be equated to zero in order to find the value that meets the condition. 0 = NPV = n X t=1 Ct (1 + kt)t−C0(10.3) •Payback time Payback period refers to the amount of time it takes to recover the cost of the inversion of the wind farm. 68
Chapter 10. Economic analysis Payback Time = Total investment Average-annual cash flow (10.4) •Discount operating cost For companies in the power generation industry, this value is calculated using the Weighted Average Cost of Capital (WACC). For this specific case, the information provided by the CNMC is used, which establishes the value of the discount operating cost at 7.09 % [68]. 10.4 Scenarios When carrying out the economic analysis of the project, several possible scenarios will be studied. In these scenarios, the parameters explained in section 10.1.2 will be varied, as well as the price of energy. A baseline, a pessimistic and an optimistic scenario is assessed, the conditions and results of the three scenarios are set out below. In all of them, it is assumed that the lifetime of the installation is 30 years. [62]. 10.4.1 Baseline scenario In the neutral baseline, the electrical and turbine maintenance costs remain unchanged. Similarly, the price of decommissioning and the land rent remain constant. In the case of the energy price, this has the value specified in tables 7.8 and 7.9. The value of the different items is shown in the table 10.2. Table 10.2: Values of the different costs and revenues for the baseline case. (Own Source) COST INCREMENT (%) Wind turbine manteinance 0.16 (€/MWh) 0 Electric manteinance 1500 (€/MW/y) 0 Land rent 6000 (€/MW/y) 0 Decomissioning 7500 (€/MW/y) 0 Energy price See 7.8 and 7.9 0 Based on the data in the table above, the following economic results are obtained. Table 10.3: Results of the economic analysis for the baseline case. (Own Source) Parameter PBT (years) 11.18 NPV (M€) 36.07 IRR (%) 12.01 ROI (%) 66.26 69
Chapter 10. Economic analysis The economic analysis for the installation of a wind farm in Alcoroches shows positive results. If the payback time is analysed, it has a value of 11.18 years, which indicates that the initial investment will be recovered in a short period of time. If the NPV is studied, it has a value of 36.07 million euros, taking into consideration the IRR, it has a value of 12.01%, far exceeding the value of the discount operating cost. This fact makes the installation of the wind farm attractive for investors. Finally, the ROI is 66.26%, demonstrating a considerable return on investment. 10.4.2 Optimistic scenario In this case study, all costs are reduced by 10% while revenues from energy sales increase by 10%. These values are shown in the table 10.4. Table 10.4: Values of the different costs and revenues for the optimistic case. (Own Source) COST INCREMENT (%) Wind turbine manteinance 0.16 (€/MWh) -10 Electric manteinance 1500 (€/MW/y) -10 Land rent 6000 (€/MW/y) -10 Decomissioning 7500 (€/MW/y) -10 Energy price See 7.8 and 7.9 10 Table 10.5: Results of the economic analysis for the optimistic case. (Own Source) Parameter PBT (years) 10.32 NPV (M€) 47.83 IRR (%) 13.75 ROI (%) 87.86 For the optimistic case, the economic values for the implementation of a wind farm in Alcoroches improve significantly compared to the previous case. When analysing the amortisation period, it is observed that this is 10.32 years, which suggests a relatively rapid recovery of the initial investment. The NPV is 47.83 million euros, while the IRR is 13.75%, which is 6.66% higher than the discount operating cost. Finally, with an ROI of 87.86%, it represents a significant return on investment, underlining the profitability of the project. 10.4.3 Pessimistic scenario For the pessimistic case, the simulation has been done by increasing costs by 10 % while revenues from energy sales are decimated by the same proportion. 70
Chapter 10. Economic analysis Table 10.6: Values of the different costs and revenues for the pessimistic case. (Own Source) COST INCREMENT (%) Wind turbine manteinance 0.16 (€/MWh) 10 Electric maintenance 1500 (€/MW/y) 10 Land rent 6000 (€/MW/y) 10 Decommissioning 7500 (€/MW/y) 10 Energy price See 7.8 and 7.9 -10 Table 10.7: Results of the economic analysis for the pessimistic case. (Own Source) Parameter PBT (years) 13.87 NPV (M€) 14.68 IRR (%) 9.03 ROI (%) 26.96 In the pessimistic scenario, the economic analysis of the implementation of the Alcoroches wind farm yields less favourable results than in the previous cases. When examining the amortisation period, this extends to 13.87 years. The NPV has a value of 14.68 million euros, while the IRR is 9.03%, which is marginally higher than the discounted operating cost. The IRR value is 1.94% higher than the one established in section 10.3. If the IRR is studied, even though it is a lower value than the previous cases, there is still a high profitability in the operation. Furthermore, with an ROI of 26.96%, it demonstrates a strong return on the investment. 71
Feasibility study for installing a wind farm in Alcoroches Chapter 11 Environmental impact 11.1 Sustainability index All the information collected in this section will come solely and exclusively from data provided by the authorities of the public administrations. Information provided by Ministerio para la Transici´on Ecol´ogica y el Reto Demogr´afico will be used, as well as other sources of information from public administrations. In order to study the environmental impact of the wind farm, the matrices in documents [69] and [70] will be used. Depending on various parameters of environmental impact, a score is obtained, the result is between 0 and 10. If a value is 0, the installation of the wind farm is totally prohibited, while if a value of 10 is obtained, the wind farm has no impact on the environment. MITECO has an electronic tool that allows the environmental impact to be calculated directly. By accessing [71] and specifying the geographical coordinates of the wind farm, the score is obtained directly. For the specific case of the Alcoroches wind farm with coordinates (40.63600,-1.73957), an environmental sustainability index of 8.58 is obtained. The impacts of the wind farm on the environment are not developed in depth, as they are fully parameterised in the previous sustainability index. This score is obtained because the wind farm affects habitats of community interest and Public Utility Mountains. With this viability index of 8.58, it is concluded that it is possible to proceed with the installation of the wind farm. This positive result implies that the planned interventions are compatible with the protection of priority habitats of community interest and public forests, guaranteeing a sustainable implementation of the project. 11.2 CO2emission savings The Alcoroches wind farm has an annual generation capacity of 148,028 MWh. In the precise case of the peninsula, the emission factor of the energy mix for the year 2022 was 273 gCO2eq/kWh [72]. By performing simple mathematical operations, the installation of the wind farm avoids the discharge of approximately 72
Chapter 11. Environmental impact 40,414 tonnes of CO2per year. This result highlights the crucial role of renewable energies in climate change mitigation, demonstrating their ability to significantly reduce greenhouse gas emissions compared to traditional energy sources. 11.3 Social impact in Alcoroches The installation of the Alcoroches wind farm could be a significant catalyst for population growth. In 2023, Alcoroches had a total of 123 inhabitants [73], this type of infrastructure requires a number of workers for both construction and ongoing maintenance, which may attract new residents to the area. The increase in population can be achieved in several ways, which are detailed below. • Direct Employment: During the construction phase, a large number of workers are needed to carry out the project. During construction, engineers, technicians, and labourers are needed, which means the arrival of many workers for a period of 6 months up to 1 year. • Permanent employment: Once in operation, the maintenance of the wind farm requires specialised technicians. According to the standards established in the PER [55], a wind farm requires one permanent worker for every 8 MW of installed capacity. Given that the Alcoroches wind farm has a capacity of 34.5 MW, approximately 4 specialists would be required. Assuming that the professionals are installed in the municipality and have a family nucleus of 4 people, the population would increase by 16 inhabitants. This increase may not seem significant, but if normalised, the population increase could be as high as 13%. • Indirect employment: In addition to the jobs mentioned above, indirect employment would be generated in associated services such as transport, accommodation, food, and other basic services necessary to support workers and their families. At the same time, the installation of the wind farm can make a very positive contribution to the municipality’s budget. The company installing the wind farm has to pay a fee to the municipality corresponding to the building permit. In addition to this, various taxes are required during the lifetime of the park, those not only have a positive impact on the economy, but also on energy and the environment. The fees and taxes collected by Alcoroches result in a substantial increase in revenue, providing a steady flow of funds that can be used for the improvement of the town’s public services. 73
Feasibility study for installing a wind farm in Alcoroches Chapter 12 Budget Full details of the budget study can be found in the such document, the first part focuses on detailing the cost of carrying out the thesis. The second part explains the real cost of installing the wind farm in the municipality of Alcoroches, this section in the budget document explains in detail all the actions to be taken to carry out the installation. However, a short summary of the actions and the cost of these can be found below. •CIVIL WORK – Land preparation and earthworks: This includes land clearing and grubbing (€102,400), open-cast excavation for land clearing made with heavy machinery (€150,000), dynamic soil compaction (€148,800), and backfilling and paving of own soil (€340,800). The total for this category is €742,000. – Construction of access roads: This section covers open-cast excavation (€528,750), backfilling and paving (€1,201,320), and dynamic soil compaction (€524,520). The total here is €2,254,590. – Foundations: This consists of open-cast excavation in rock (€384,447) and the supply and pouring of concrete (€4,099,563), amounting to a total of €4,484,009. – Trenches: Includes the excavation of trenches in rock (€244,774) and backfilling with sand (€115,256), totalling €360,030. •ELECTRIC INSTALLATION – Wiring: This section includes the supply and laying of a 20 kV underground line with different diameters of cross-section. This goes from a 25 mm2to a 500 mm2conductor. The total cost of installing the cables amounts to €403,476. •WIND TURBINE – V136-3.45: This section of the budget takes into account the transport and installation of the turbine with a hub height of 112 metres, at a total cost of €45,987,960. 74
Chapter 12. Budget •ENVIRONMENTAL IMPACT CORRECTIVE MEASURES – Environmental improvement: Corrective measures for environmental impact, reforestation of affected areas and improvement of the built-up area with a total cost of €95,700. •ENGINEERING STUDY – Wind farm design report: The total cost of drafting the document is €108,000. – Environmental report: The environmental study has a total cost of €1,000. – Economic feasibility report: The economic study of the feasibility of the installation of the wind farm has a total value of €4,000. Taking all of the above into account, the total installation cost of the wind farm amounts to a value of €54,440,765. 75
Feasibility study for installing a wind farm in Alcoroches Chapter 13 Conclusions and future work 13.1 Conclusions After carrying out the feasibility study for the installation of the wind farm in Alcoroches, it can be confirmed that its construction is completely feasible. During the thesis, each step in the design of the wind farm has been supported by data, moving forward only when all of them were favourable. The work has followed a risk-minimising methodology, similar to that employed by renewable plant design companies. The study not only focuses on energy viability, but also analyses other factors such as legislative and environmental constraints. The Sierra de Albarrac´ın, a mountainous area with a notable wind resource, has a large part of its territory under environmental protection as it belongs to the Red Natura 2000. This designation prevents the installation of any renewable park in these areas. However, the proposed location for the wind farm is outside this network, thus allowing the project to move forward. The study includes a review of the regulations applicable to the construction of renewable complexes, which have been considered throughout the document. It is important to note that legislation has undergone significant changes in recent years and is likely to continue to evolve as renewable energy penetration increases. Therefore, it is possible that the wind farm design may need to be adjusted in the future due to legislative reforms. To ensure the accuracy of the thesis, the real data from the Checa meteorological station have been compared with the information provided by the IDAE wind atlas. After confirming the concordance of the information, it can be proceeded with the drafting of the report. The data from the wind atlas for different heights have been used and corrected using MATLAB code, which allows the parameters of the Weibull function to be adjusted. This modification ensures accurate calculation of the wind speed at different hub heights, enabling a reliable study of the energy production. In the selection of the windmills to be installed, the three most prestigious European companies in the wind 76
Chapter 13. Conclusions and future work energy field are considered. From the three companies, a compilation of all the turbines they have in their catalogue is made. After that, three turbines are chosen, only those that meet the specifications detailed in the body of the project. Once the energy production data is obtained, three crucial parameters are analysed: gross energy, rotor diameter and payback time. Through an OWA analysis, it is ensured that the selected turbine is the most suitable for the project requirements. The wind farm is equipped with the V136-3.45 turbine, which obtains the highest score in the OWA study with 0.8175/1. The installation of this windmill allows the park to generate a total of 148,028 MWh/year, positioning Alcoroches as a benchmark in renewable energy in the region. These results confirm considerable economic viability, with a payback time of approximately 11 years in the baseline case. Furthermore, these positive energy and economic data are supported by the low environmental impact, which scored 8.58 in the MITECO environmental assessment test. Finally, it is crucial to highlight the significant reduction of greenhouse gases, avoiding the emission of more than 40,414 tonnes of C 0 2 per year. Added to these benefits, it is important to remark the positive impact on local society, increasing municipal revenue and population by more than 13%. 13.2 Future work The document presented can significantly improve the scope of the study, but this is due to the limited time available for the development of the report. The design of renewable plants offers a challenge for engineering, therefore ways to expand the content of the thesis in future work are detailed below. • Study of the impact of the wake effect on the turbines by performing a CFD analysis, taking into account the specific geographical shape of the wind farm. • Iterative improvement of the position of the turbines by means of the CFD study mentioned in the previous section. •Impact on the improvement of energy production through the use of AFC. •Study of the impact of the AFC on the reduction of greenhouse gas emissions. • Realisation of a hybrid renewable park, consisting of solar photovoltaic and wind energy. Study of the impact it would have on the economic viability, taking into account the evolution of energy prices. 77