Iterative Beam Search for Simple Assembly Line Balancing with a Fixed Number of Work Stations Christian Blum ALBCOM Research Group Universitat Polit`ecnica de Catalunya, Barcelona, Spain [email protected]c.edu Abstract The simple assembly line balancing problem (SALBP) concerns the assignment of tasks with pre-defined processing times to work stations that are arranged in a line. Hereby, precedence constraints between the tasks must be respected. The optimization goal of the SALBP-2 version of the problem concerns the minimization of the so-called cycle time, that is, the time in which the tasks of each work station must be completed. In this work we propose to tackle this problem with an iterative search method based on beam search. The proposed algorithm is able to obtain optimal, respectively bestknown, solutions in 283 out of 302 test cases. Moreover, for 9 further test cases the algorithm is able to produce new best-known solutions. These numbers indicate that the proposed iterative beam search algorithm is currently a state-of-the-art method for the SALBP-2. 1 Introduction The class of problems known as assembly line balancing problems (ALBPs) concerns the optimization of processes related to the manufacturing of products via assembly lines. Their importance in the industrial world is shown by the fact that much research efforts have been dedicated to many different types of ALBPs during the past 50-60 years [17, 7]. The specific problem considered in this paper is the so-called simple assembly line balancing problem (SALBP) [20], a well-studied scientific test case. An assembly line is composed of a set of work stations arranged in a line, and by a transport system which moves the product to be manufactured along the line. The product is manufactured by executing a given set of tasks. Each of these tasks has a pre-defined processing time. In order to obtain a solution to a given SALBP instance, all tasks must be assigned to work stations subject to precedence constraints between the tasks. In the context of the SALBP, all work stations are considered to be of equal size. Moreover, the assembly line is assumed to move in constant speed. This implies a maximum of Ctime units—the so-called cycle time—for processing the tasks assigned to each work station. The SALBP has been tackled with several objective functions among which the following ones are the most studied ones in the literature: •Given a fixed cycle time C, the optimization goal consists in minimizing the number of necessary work stations. This version of the problem is refered to as SALBP-1. 1
•Given a fixed number mof work stations, the goal is to minimize the cycle time C. The literature knows this second problem version as SALBP-2. The feasibility problem SALBP-F arises when both a cycle time Cand a number of work stations mis given and the goal is to find a feasible solution respecting Cand m. In this work we will deal with the SALBP-2 version of the problem. For what concerns the comparison between SALBP-1 and SALBP-2, much of the scientific work has been dedicated to the SALBP-1. However, also for the SALBP-2 exists a considerable body of research papers. An excellent survey was provided by Becker and Scholl in [20]. Approaches for the SALBP-2 can basically be classified as either iterative solution approaches or direct solution approaches. Iterative approaches tackle the problem by iteratively solving a series of SALBP-F problems that are obtained by fixing the cycle time. This process is started with a cycle time that is set to some calculated upper bound. This cycle time is then decremented during the iterative process, which stops as soon as no solution for the corresponding SALBP-F problem can be found. In contrast to these indirect approaches, direct approaches intend to solve a given SALBP-2 instance directly. Heuristic as well as complete approaches have been devised for the SALBP-2. Among the existing complete methods we find iterative approaches such as the ones proposed in [8, 19] but also direct approaches such as the ones described in [18, 11]. Moreover, the performance of different integer programming formulation of the SALBP-2 has been evaluated in [15]. The currently best-performing exact method is SALOME-2 [11]. Surprisingly this exact method even outperforms the existing heuristic and metaheuristic approaches for the SALBP-2. The most successful metaheuristic approach to date is a tabu search method proposed in [21]. Another tabu search proposal can be found in [5]. Other metaheuristic approaches include evolutionary algorithms [2, 24, 13] and simulated annealing [9]. Finally, a two-phase heuristic based on linear programming can be found in [22], whereas a heuristic based on Petri nets was proposed in [10]. Contribution of this work. Subsequently we propose to tackle the SALBP-2 by means of an iterative approach based on beam search, an incomplete variant of branch & bound. The resulting iterative beam search algorithm is inspired by one of the current state-of-the-art methods for the SALBP-1, namely Beam-ACO [3]. Beam-ACO is a hybrid approach that is obtained by combining the metaheuristic ant colony optimization with beam search. In this work we propose to use the beam search component of Beam-ACO in an iterative way for obtaining good SALBP-2 solutions. Our computational results show indeed that the proposed algorithm is currently a state-of-the-art method for the SALBP-2. It is able to obtain optimal, respectively best-known, solutions in 283 out of 302 test cases. Moreover, in further 9 cases the algorithm is able to produce new best-known solutions. Organization of the paper. In Section 2 we present a technical description of the tackled problem. Furthermore, in Section 3 the proposed algorithm is described. Finally, in Section 4 we present a detailed experimental evaluation and in Section 5 we conclude our work and offer an outlook to future work. 2
2 The SALBP-2 The SALBP-2 can technically be described as follows. An instance (T, G, m) consists of three components. T={1,...,n}is a set of ntasks. Each task i∈Thas a pre-defined processing time ti>0. Moreover, given is a precedence graph G= (T, A), which is a directed, acyclic graph with Tas node set. Finally, mis the pre-defined number of work stations which are ordered from 1 to m. An arc li,j ∈Aindicates that i∈Tmust be processed before j∈T. Given a task j∈T,Pj⊂Tdenotes the set of tasks that must be processed before j. A feasible solution is obtained by assigning each task to exactly one work station such that the precedence constraints between the tasks are satisfied. The objective function consists in minimizing the so-called cycle time. The SALBP-2 can be expressed in the following way as an integer programming (IP) problem. min z(1) subject to: m X s=1 xis = 1 ∀i∈T(2) m X s=1 sxis ≤ m X s=1 sxjs ∀j∈T, i ∈Pj(3) X i∈T tixis ≤z s = 1,...,m (4) xis ∈ {0,1} ∀i∈T, s = 1,...,m (5) z > 0 (6) This IP model makes use of the following variables and constants: xis is a binary variable which is set to 1 if and only if task i∈Tis assigned to work station 1 ≤s≤m. The objective function (1) minimizes the cycle time z > 0.1The constraints (2) ensure that each task i∈Tis assigned to a single work station 1 ≤s≤m. Constraints (3) reflect the precedence relationships between the tasks. More specifically, if task j∈Tis assigned to a work station 1 ≤s≤m, all tasks i∈Pjmust be assigned to work stations 1 ≤s′≤mwith s′≤s. The constraints (4) ensure that the sum of the processing times of the tasks assigned to a work station 1 ≤s≤mdo not exceed the cycle time z. Note that this model is not necessarily the most efficient IP model for solving the SALBP-2. An evaluation of several different models can be found in [15]. 2.1 Solution Representation The following solution representation is used for the description of the algorithm as given in Section 3. A solution Sis an ordered list S=hS1,...,Smiof msets of tasks, where Sidenotes the set of tasks that are assigned to the i-th work station. Abusing notation we henceforth call Sia work station. Note that for a solution Sto be valid the following conditions must be fulfilled: 1Note that we refer to the variable cycle time of the IP model as z, while fixed cycle times are denoted by C. 3
1. Sm i=1 Si=T={1,...,n}and Tm i=1 Si=∅, that is, each task is assigned to exactly one work station. 2. For each task j∈Siit is must hold that Pj⊆Si k=1 Sk. This ensures that the precedence constraints between the tasks are not violated. 2.2 Reverse Problem Instances The reverse problem instance (T, Gr, m) with respect to an original instance (T, G, m) is obtained by inverting the direction of all arcs of G. It is well-known from the literature [20] that tackling the reverse problem instance may lead an exact algorithm faster to an optimal solution, respectively, may provide a better heuristic solution when tackled with the same heuristic as the original problem instance. Moreover, a solution Srto the reverse problem instance (T, Gr, m) can easily be converted into a solution Sto the original problem instance (T, G, m) as follows: Si:= Sr m−i+1 for i= 1,...,m (7) 3 Iterative Beam Search As mentioned in the introduction, the basic component of our algorithm for the SALBP-2 consists of beam search (BS), which is an incomplete derivative of branch & bound [14]. Initially BS has especially been used in the context of scheduling problems (see, for example, [16, 6, 23]). To date only very few applications to other types of problems exist (see, for example, [12, 1, 4]). In the following we briefly describe how one of the standard versions of BS works. The crucial aspect of BS is the parallel extension of partial solutions in several ways. At all times, the algorithm keeps a set Bof at most kbw partial solutions, where Bis the so-called beam, and kbw is known as the beam width. At each step, at most kext feasible extensions of each partial solution in Bare selected on the basis of greedy information. In general, this selection is done deterministically. At the end of each step, the algorithm creates a new beam Bby choosing up to kbw partial solutions from the set of selected feasible extensions. For that purpose, BS algorithms determine—in the case of minimization—a lower bound value for each extension. Only the maximally kbw best extensions—with respect to these lower bound values—are included in B. Finally, if any complete solution was generated, the algorithm returns the best of those. Note that the underlying constructive heuristic that defines feasible extensions of partial solutions and the lower bound function for evaluating partial solutions are crucial for the working of BS. In the following we first present a description of the implementation of the BS component, before we describe the algorithmic scheme in which this BS component is used. 3.1 The Beam Search Component The BS component described in this section—see Algorithm 1 for the pseudo-code—is the main component of the proposed algorithm for the SALBP-2. The algorithm requires a problem instance (T, G, m), a fixed cycle time C, a beam width kbw, and a maximal number of extensions kext as input. Given a fixed cycle time Cand m(the number of work stations) BS tries to find at least one feasible solution. As mentioned before, the crucial aspect of BS is the extension of partial solutions in several possible ways. At each step the algorithm extends 4
Algorithm 1 Beam search 1: input: an instance (T, G, m), a fixed cycle time C, a beam width kbw, and kext 2: l:= 0 3: Initialization of an empty solution S 4: B:= {S} 5: Bcompl := ∅ 6: while B6=∅do 7: Bext := ∅ 8: l:= l+ 1 9: for all S ∈ Bdo 10: for i= 1,...,kext do 11: S′:= S {copy partial solution Sinto S′} 12: S′ l:= ExtendPartialSolution(S′, l, C){see Algorithm 2} 13: if solution S′is complete (that is, all tasks are assigned) then 14: Bcompl := Bcompl ∪ {S′} 15: else 16: if l < m and S′ lis different to the l-th work station of all other S ∈ Bext then 17: Bext := Bext ∪ {S′} 18: end if 19: end if 20: end for 21: end for 22: B←SelectSolutions(Bext,kbw) 23: end while 24: output: If Bcompl 6=∅the output is true, otherwise false each partial solution from Bin a maximum number of ways. More specifically, given a partial solution with l−1< m work stations already filled, an extension is generated by assigning a set of so-far unassigned tasks to the next work station Slsuch that the given cycle time Cis not surpassed and the precedence constraints between the tasks are respected (see lines 11–12 of Algorithm 1). The algorithm produces extensions in a (partially) probabilistic way rather than in the usual deterministic manner.2Each generated extension (partial solution) is either stored in set Bcompl in case it is a complete solution, or in set Bext otherwise (see lines 13–19 of Algorithm 1). However, a partial solution is only stored in set Bext if it uses at most m−1 work stations, and if its l-th work station is different to the l-th work station of all partial solutions that are already in B. Finally, BS creates a new beam Bby selecting up to kbw solutions from set Bext of further extensible partial solutions (see line 22 of Algorithm 1). This is done in function SelectSolutions(Bext,kbw) on the basis of a lower bound function LB(·). In the following we describe in detail the extension of partial solutions and the working of function SelectSolutions(Bext,kbw). Extending Partial Solutions. The generation of an extension of a partial solution S′with l−1 work stations already filled works as follows. Unassigned tasks are iteratively assigned 2This is done for avoiding a choice-without-replacement process for which all possible work station fillings must be generated beforehand. 5
Algorithm 2 Function ExtendPartialSolution(S′, l, C) of Algorithm 1 1: input: A partial solution S′, the index lof the work station to be filled, and the cycle time C 2: S′ l:= ∅ 3: T′:= {i∈T|i /∈Sl j=1 S′ j, Pi⊆Sl j=1 S′ j, ti+crem ≤C} 4: crem := C 5: while T′6=∅do 6: j:=ChooseTask(T′, crem ) 7: crem := crem −tj 8: T′:= {i∈T|i /∈Sl j=1 S′ j, Pi⊆Sl j=1 S′ j, ti+crem ≤C} 9: S′ l:= S′ l∪ {j} 10: end while 11: output: Filled work station S′ l to work station S′ luntil the sum of their processing times is such that no other task can be added to S′ lwithout exceeding the given cycle time C. This procedure is pseudo-coded in Algorithm 2. At each step, T′denotes the set of so-far unassigned tasks that may be added to S′ lwithout violating any constraints. The definition of this set of available tasks is given in line 3, respectively 8, of Algorithm 2. It remains to describe the implementation of function ChooseTask(T′, crem )of Algorithm 2. For that purpose let us first define the following subset of T′: Tsat := {i∈T′|ti+crem =C}(8) This definition is such that Tsat contains all tasks that saturate, in terms of processing time, the l-th work station Sl. The choice of a task from T′is made on the basis of greedy information, that is, on the basis of values ηi>0 that are assigned to all tasks i∈T′by a greedy function. The first action for choosing a task from T′consists in flipping a coin for deciding if the choice is made deterministically, or probabilistically. In case of a deterministic choice, there are two possibilities. First, if Tsat 6=∅, the best task from Tsat is chosen, that is, the task with maximal greedy value among all tasks in Tsat. Otherwise, we choose the task with maximal greedy value from T′. In case of a probabilistic decision, a task from T′is chosen on the basis of the following probability distribution: p(i) := ηi P j∈T′ ηj ,∀i∈T′(9) For completing the description of function ChooseTask(T′, crem ), we must describe the definition of the greedy values ηi,∀i∈T. In a first step a term γiis defined as follows: γi:= κ1·ti C+κ2· |Sucall i| max1≤j≤nSucall j!,∀i∈T(10) Hereby, Sucall idenotes the set of all tasks that can be reached from iin precedence graph G via a directed path. This definition combines two greedy heuristics that are often used in the context of assembly line balancing problems. The first one concerns the task processing 6
times and the second one concerns the size of Sucall i. The influence of both heuristics can be adjusted via the setting of weights κ1and κ2. In order to be more flexible we decided to allow for both weights a value from [−1,1]. This means that we consider for each heuristic potentially also its negation. Given the γi-values, the greedy values ηiare then derived as follows: ηi:= γi−γmin + 1 γmax ∀i∈T , (11) where γmin, respectively γmax, denote the minimum, respectively maximum, values of all γi. Interestingly, for obtaining well-working greedy values, parameters κ1and κ2have to be chosen in a problem-instance-dependent way. Tuning experiments are present in Section 4.2. The Lower Bound Function. The new beam Bis—at each step—chosen from Bext. This choice is implemented by function SelectSolutions(Bext,kbw) of Algorithm 2. First, the solutions in Bext are ranked with respect to increasing lower bound values LB(·). Then, the min{kbw,|Bext|} highest ranked partial solutions from Bext are selected. Let us denote by T⊆Tthe set of tasks that have not yet been assigned to work stations in partial solution S′. Then: LB(S′) = Pi∈Tti C(12) Note that this lower bound is inspired by splitting-based bounds for the one-dimensional bin-backing problem. 3.2 The Algorithmic Scheme The BS component outlined in the previous section is used by an iterative algorithmic scheme that is presented in Algorithm 3. Henceforth this algorithmic scheme is labelled iterated beam search (IBS). The first step consists in determining a starting cycle time C, which is computed in funcion DetermineStartingCycleTime() of Algorithm 3 as C:= max maxi∈T{ti},Pi∈Tti m .(13) The algorithm works in two phases. In the first phase (see lines 3-11 of Algorithm 3) the algorithm tries to quickly find a first cycle time Cfor which a valid solution can be found. For this purpose BS is applied with the setting kbw = 5 and kext = 2. Note that this setting was chosen after tuning by hand. Moreover, note that the first phase only takes a fraction of a second of computation time. This holds for all instances considered in Section 4. The second phase of the algorithm iteratively tries to find a valid solution for the next smaller cycle time. In this phase, the algorithm disposes over a certain time limit for each considered cycle time. Remember that the working of BS is partially probabilistic. Therefore, BS can repeatedly be applied to the same instance with potentially different outcomes. The first five percent of the above-mentioned time limit are spent by BS applications that use the setting kbw := 10 and kext := 5. This is done with the intention of not wasting too much computation time, if not necessary. However, if BS is not able to solve the given cycle time with this setting, the remaining 95% of the available time are spent by BS applications using the setting kbw := 150 and kext := 20. With this setting BS is considerably slower. However, the probability of finding feasible solutions is much higher than with the setting described before. The second phase of the algorithm ends when the time limit has passed without having found a feasible solution for the considered cycle time. 7
Algorithm 3 Iterative beam search (Ibs) for the SALBP-2 1: input: an instance (T, G, m) 2: C:= DetermineStartingCycleTime() 3: kbw := 5, kext := 2 4: success := false 5: while not success do 6: success := BeamSearch((T, G, m), C, kbw, kext){original instance} 7: if not success then 8: success := BeamSearch((T, Gr, m), C, kbw, kext){reverse instance} 9: if not success then C:= C+ 1 end if 10: end if 11: end while 12: C:= C−1 13: stop := false 14: while not stop do 15: success := false 16: while time limit not reached and not success do 17: if within 5% of time limit then kbw := 10, kext := 5 else kbw := 150, kext := 20 end if 18: success := BeamSearch((T, G, m), C, kbw, kext){original instance} 19: if not success then 20: success := BeamSearch((T, Gr, m), C, kbw, kext){reverse instance} 21: end if 22: end while 23: if success then C:= C−1else stop := true end if 24: end while 25: C:= C+ 1 26: output: cycle time C 4 Experimental Evaluation Ibs was implemented in ANSI C++, and GCC 3.4.0 was used for compiling the software. Experimental results were obtained on a PC with an AMD64X2 4400 processor and 4 Gb of memory. In the following we first describe the set of benchmark instances that we used for the experimental evaluation. Subsequently we present the tuning process that we conducted and the results of the proposed algorithm. 4.1 Benchmark Instances We used the usual set of 302 benchmark instances from the literature. They can be obtained— together with information about optimal and best-known solutions—from a website especially dedicated to all kind of assembly line balancing problems maintained by Armin Scholl, http: //www.assembly-line-balancing.de. Each instance consists of a precedence graph Gand a given number mof work stations. The benchmark set is composed of two subsets of instances, henceforth called Dataset1 and Dataset2.Dataset1 consists of 128 instances based on 9 different precedence graphs with a number of tasks between 29 to 111. Dataset2 is 8
Table 1: Values of parameters κ1and κ2for the final experiments. Graph κ1κ2Graph κ1κ2 Arcus1 0.0 1.0 Lutz2 -0.1 0.9 Arcus2 -0.5 0.9 Lutz3 0.0 1.0 Barthol2 0.0 1.0 Mukherje 0.0 1.0 Barthold 0.0 1.0 Sawyer 0.0 1.0 Buxey 0.0 1.0 Scholl 0.0 1.0 Gunther -0.4 0.8 Tonge -0.1 0.2 Hahn 0.0 1.0 Warnecke 0.0 1.0 Kilbridge 0.0 1.0 Wee-Mag 0.0 1.0 Lutz1 -0.1 0.9 composed of 174 instances based on 8 different precedence graphs with a number of tasks varying from 53 to 297. 4.2 Algorithm Tuning During preliminar experiments we realized that parameters kbw and kext have a rather low impact on the final results of Ibs. In other words it is easy to find a reasonable setting for these parameters quite quickly. Their setting dynamically changes during a run of the algorithm as specified in Section 3.2. On the contrary, parameters κ1and κ2(see Eq. 10) have a high impact on the algorithms’ performance. Remember that κ1is the weight of the greedy function concerning the task processing times, while κ2is the weight of the greedy function concerning the number of tasks that have to be processed after the task under consideration. As mentioned before, for both parameters we allowed values from [−1,1]. Instead of trying to find a good parameter setting for each instance, we decided for a tuning process based on precedence graphs, that is, we wanted to choose a single setting of κ1and κ2for all instances concerning the same precedence graph. For that purpose we applied a specific version of Ibs for all combinations of κ1, κ2∈ {−1.0,−0.9,...,0.0,...,0.9,1.0}to all 302 instances. This makes a total of 441 different settings for each instance. The specific version of Ibs that we applied for the tuning process differs from Ibs as outlined in Algorithm 3 in that lines 14-24 were replaced by a single, deterministic, application of beam search with kbw = 150 and kext = 20. This was done for the purpose of saving computation time. Based on the obtained results we chose the settings presented in Table 1 for the different precedence graphs. It is interesting to note that, apart from a few exceptions, the greedy heuristic based on task processing times does not seem necessary for obtaining good results. In Figure 1 tuning information is provided in graphical form for a few representative examples. The y-axis of the presented graphics varies over the different values of κ1, while the x-axis ranges over the allowed values of κ2. Note that each graphic consists of 441 squares representing the 441 different combinations of values for κ1and κ2. The gray level in which each square is painted indicates the quality of the algorithm when run with the corresponding parameter setting. In particular, black color denotes the worst setting, whereas white color indicates the best algorithm setting. In some cases such as (Buxey, m= 7) and (Tonge, m= 16), as shown in Figures 1(a) and 1(b), there is a wide range of good settings, which 9
[15] R. Pastor, L. Ferrer, and A. Garc´ıa. Evaluating optimization models to solve SALBP. In O. Gervasi and M. L. Gavrilova, editors, Proceedings of ICCSA 2007 – International Conference on Computational Science and Its Applications, volume 4705 of Lecture Notes in Computer Science, pages 791–803. Springer Verlag, Berlin, Germany, 2007. [16] I. Sabuncuoglu and M. Bayiz. Job shop scheduling with beam search. European Journal of Operational Research, 118:390–412, 1999. [17] M. E. Salveson. The assembly line balancing problem. Journal of Industrial Engineering, 6:18–25, 1955. [18] A. Scholl. Ein B&B-Verfahren zur Abstimmung von Einprodukt-Fließb¨andern bei gegebener Stationsanzahl. In H. Dyckhoff et al., editor, Operations Research Proceedings, pages 175–181. Springer Verlag, Berlin, Germany, 1994. [19] A. Scholl. Balancing and sequencing assembly lines. Physica Verlag, Heidelberg, Germany, 2nd edition edition, 1999. [20] A. Scholl and C. Becker. State-of-the-art exact and heuristic solution procedures for simple assembly line balancing. European Journal of Operational Research, 168(3):666– 693, 2006. [21] A. Scholl and S. Voss. Simple assembly line balancing—Heuristic approaches. Journal of Heuristics, 2:217–244, 1996. [22] H. F. Ugurdag, R. Rachamadugu, and C. A. Papachristou. Designing paced assembly lines with fixed number of stations. European Journal of Operational Research, 102:488– 501, 1997. [23] J. M. S. Valente and R. A. F. S. Alves. Filtered and recovering beam search algorithms for the early/tardy scheduling problem with no idle time. Computers & Industrial Engineering, 48(2):363–375, 2005. [24] T. Watanabe, Y. Hashimoto, L. Nishikawa, and H. Tokumaru. Line balancing using a genetic evolution model. Control Engineering Practice, 3:69–76, 1995. 16
Appendix A 17
Table 7: Detailed results of Ibs for 302 test instances (Part A). Graph mbks Iterative Beam Search (Ibs) Graph mbks Iterative Beam Search (Ibs) best avg std time (s) std best avg std time (s) std Arcus1 (83) 3 25236 25236 25236.00 (0.00) 0.56 (0.29) Barthold (148) 9 626 626 626.00 (0.00) 0.13 (0.03) 418927 18927 18927.00 (0.00) 6.16 (3.92) 10 564 564 564.00 (0.00) 0.10 (0.02) 515142 15142 15142.00 (0.00) 80.08 (16.69) 11 513 513 513.00 (0.00) 0.09 (0.00) 612620 12620 12620.00 (0.00) 15.52 (5.76) 12 470 470 470.00 (0.00) 0.09 (0.00) 710826 10826 10826.00 (0.00) 59.80 (19.89) 13 434 434 434.00 (0.00) 0.16 (0.02) 89554 ∗9555 9555.55 (0.51) 120.54 (63.16) 14 403 403 403.00 (0.00) 0.14 (0.01) 98499 8499 8500.70 (0.80) 130.73 (117.23) 15 383 383 383.00 (0.00) 0.05 (0.00) 10 7580 7580 7580.95 (0.60) 311.89 (109.87) Buxey (29) 7 47 47 47.00 (0.00) 0.46 (0.51) 11 7084 ∗7086 7086.70 (0.47) 71.13 (52.77) 8 41 41 41.00 (0.00) 0.00 (0.00) 12 6412 ∗6413 6414.10 (0.72) 362.32 (66.26) 9 37 37 37.00 (0.00) 0.01 (0.00) 13 5864 5864 5864.00 (0.00) 129.18 (12.99) 10 34 34 34.00 (0.00) 0.00 (0.00) 14 5441 5441 5441.00 (0.00) 2.02 (0.41) 11 32 32 32.00 (0.00) 0.00 (0.00) 15 5104 5104 5104.45 (0.60) 222.29 (73.92) 12 28 28 28.00 (0.00) 0.01 (0.00) 16 4850 4850 4850.00 (0.00) 33.84 (9.59) 13 27 27 27.00 (0.00) 0.01 (0.00) 17 4516 ∗4524 4526.20 (0.89) 282.49 (100.96) 14 25 25 25.00 (0.00) 0.00 (0.00) 18 4317 ∗4322 4323.20 (0.77) 291.73 (111.23) Gunther (35) 6 84 84 84.00 (0.00) 0.00 (0.00) 19 4068 ∗4073 4074.80 (1.01) 326.78 (125.49) 7 72 72 72.00 (0.00) 0.03 (0.00) 20 3882 ∗3886 3889.25 (2.05) 594.21 (204.09) 8 63 63 63.00 (0.00) 0.01 (0.00) 21 3691 3691 3691.00 (0.00) 5.58 (0.81) 9 54 54 54.00 (0.00) 0.05 (0.04) 22 3691 3691 3691.00 (0.00) 0.02 (0.00) 10 50 50 50.00 (0.00) 0.01 (0.00) Arcus2 (111) 3 50133 50133 50133.00 (0.00) 0.09 (0.03) 11 48 48 48.00 (0.00) 0.00 (0.00) 437600 37600 37600.00 (0.00) 0.41 (0.02) 12 44 44 44.00 (0.00) 0.01 (0.00) 530080 30080 30080.00 (0.00) 0.43 (0.22) 13 42 42 42.00 (0.00) 0.01 (0.00) 625067 25067 25067.00 (0.00) 1.13 (0.59) 14 40 40 40.00 (0.00) 0.02 (0.00) 721486 21486 21486.00 (0.00) 1.76 (1.04) 15 40 40 40.00 (0.00) 0.01 (0.00) 8 18800 18800 18800.00 (0.00) 11.36 (2.86) Hahn (53) 3 4787 4787 4787.00 (0.00) 0.00 (0.00) 916711 16711 16711.00 (0.00) 28.03 (12.51) 4 3677 3677 3677.00 (0.00) 0.08 (0.01) 10 15040 15040 15040.00 (0.00) 38.67 (15.08) 5 2823 2823 2823.00 (0.00) 0.01 (0.00) 11 13673 13673 13673.00 (0.00) 49.47 (12.83) 6 2400 2400 2400.00 (0.00) 0.05 (0.01) 12 12534 12534 12534.00 (0.00) 43.34 (15.17) 7 2336 2336 2336.00 (0.00) 0.29 (0.01) 13 11570 11570 11570.00 (0.00) 32.60 (14.63) 8 1907 1907 1907.00 (0.00) 0.09 (0.03) 14 10747 ∗10748 10748.00 (0.00) 62.69 (16.17) 9 1827 1827 1827.00 (0.00) 0.00 (0.00) 15 10035 ∗10036 10036.40 (0.50) 112.54 (63.37) 10 1775 1775 1775.00 (0.00) 0.00 (0.00) 16 9412 ∗9416 9416.60 (0.68) 290.35 (90.83) Kilbridge (45) 3 184 184 184.00 (0.00) 0.00 (0.00) 17 8855 ∗8864 8864.90 (0.31) 87.41 (52.86) 4 138 138 138.00 (0.00) 0.01 (0.00) 18 8377 8377 8377.00 (0.00) 8.11 (1.00) 5 111 111 111.00 (0.00) 0.00 (0.00) 19 7928 7924 7925.60 (0.60) 205.09 (76.12) 6 92 92 92.00 (0.00) 0.00 (0.00) 20 7526 7524 7524.40 (0.50) 159.72 (57.92) 7 79 79 79.00 (0.00) 0.01 (0.00) 21 7188 ∗7192 7193.40 (0.82) 318.78 (89.64) 8 69 69 69.00 (0.00) 0.01 (0.00) 22 6859 6858 6858.20 (0.41) 226.94 (75.52) 9 62 62 62.00 (0.00) 0.01 (0.00) 23 6561 6560 6563.10 (1.45) 428.68 (168.53) 10 56 56 56.00 (0.00) 0.01 (0.00) 24 6289 6284 6285.65 (1.46) 311.77 (144.55) 11 55 55 55.00 (0.00) 0.01 (0.00) 25 6106 ∗6112 6114.15 (0.99) 305.50 (90.99) Lutz1 (32) 8 1860 1860 1860.00 (0.00) 0.14 (0.00) 26 5856 ∗5858 5860.45 (1.76) 661.48 (192.47) 9 1638 1638 1638.00 (0.00) 2.41 (0.34) 27 5689 5689 5689.00 (0.00) 9.29 (0.17) 10 1526 1526 1526.00 (0.00) 0.18 (0.01) Barthol2 (148) 27 157 157 157.00 (0.00) 0.31 (0.03) 11 1400 1400 1400.00 (0.00) 0.01 (0.00) 28 152 152 152.00 (0.00) 0.44 (0.07) 12 1400 1400 1400.00 (0.00) 0.00 (0.00) 29 146 146 146.00 (0.00) 0.80 (0.32) Lutz2 (89) 9 54 54 54.00 (0.00) 0.02 (0.01) 30 142 142 142.00 (0.00) 0.15 (0.03) 10 49 49 49.00 (0.00) 0.03 (0.00) 31 137 137 137.00 (0.00) 0.67 (0.09) 11 45 45 45.00 (0.00) 0.04 (0.00) 32 133 133 133.00 (0.00) 0.57 (0.07) 12 41 41 41.00 (0.00) 0.03 (0.00) 33 129 129 129.00 (0.00) 0.52 (0.06) 13 38 38 38.00 (0.00) 0.03 (0.00) 34 125 125 125.00 (0.00) 0.47 (0.05) 14 35 35 35.00 (0.00) 0.03 (0.00) 35 121 121 121.00 (0.00) 0.94 (0.15) 15 33 33 33.00 (0.00) 0.03 (0.00) 36 118 118 118.00 (0.00) 0.87 (0.11) 16 31 31 31.00 (0.00) 0.02 (0.00) 37 115 115 115.00 (0.00) 0.92 (0.19) 17 29 29 29.00 (0.00) 0.04 (0.00) 38 112 112 112.00 (0.00) 0.76 (0.06) 18 28 28 28.00 (0.00) 0.04 (0.00) 39 109 109 109.00 (0.00) 0.70 (0.13) 19 26 26 26.00 (0.00) 0.04 (0.01) 40 106 106 106.00 (0.00) 0.91 (0.32) 20 25 25 25.00 (0.00) 0.04 (0.00) 41 104 104 104.00 (0.00) 0.72 (0.05) 21 24 24 24.00 (0.00) 0.02 (0.00) 42 101 101 101.00 (0.00) 2.77 (5.43) 22 23 23 23.00 (0.00) 0.04 (0.00) 43 99 99 99.00 (0.00) 0.84 (0.23) 23 22 22 22.00 (0.00) 0.05 (0.00) 44 97 97 97.00 (0.00) 0.59 (0.15) 24 21 21 21.00 (0.00) 0.05 (0.00) 45 95 95 95.00 (0.00) 0.76 (0.25) 25 20 20 20.00 (0.00) 0.02 (0.00) 46 93 93 93.00 (0.00) 0.68 (0.29) 26 19 19 19.00 (0.00) 0.05 (0.02) 47 91 91 91.00 (0.00) 0.67 (0.15) 27 19 19 19.00 (0.00) 0.03 (0.00) 48 89 89 89.00 (0.00) 1.17 (0.47) 28 18 18 18.00 (0.00) 0.05 (0.00) 49 87 87 87.00 (0.00) 0.83 (0.26) Lutz3 (89) 3 548 548 548.00 (0.00) 0.01 (0.00) 50 85 85 85.90 (0.31) 3.28 (10.33) 4 411 411 411.00 (0.00) 0.03 (0.00) 51 84 84 84.00 (0.00) 2.60 (2.09) 5 329 329 329.00 (0.00) 0.01 (0.00) Barthold (148) 3 1878 1878 1878.00 (0.00) 0.01 (0.00) 6 275 275 275.00 (0.00) 0.01 (0.00) 41409 1409 1409.00 (0.00) 0.02 (0.00) 7 236 236 236.00 (0.00) 0.02 (0.00) 51127 1127 1127.00 (0.00) 0.02 (0.00) 8 207 207 207.00 (0.00) 0.04 (0.00) 6939 939 939.00 (0.00) 0.06 (0.01) 9 184 184 184.00 (0.00) 5.54 (4.14) 7805 805 805.00 (0.00) 0.11 (0.00) 10 165 165 165.00 (0.00) 0.09 (0.01) 8705 705 705.00 (0.00) 0.04 (0.01) 11 151 151 151.00 (0.00) 0.06 (0.00) 18
Table 8: Detailed results of Ibs for 302 test instances (Part B). Graph mbks Iterative Beam Search (Ibs) Graph mbks Iterative Beam Search (Ibs) best avg std time (s) std best avg std time (s) std Lutz3 (89) 12 138 138 138.00 (0.00) 0.02 (0.00) Tonge (70) 6 585 585 585.00 (0.00) 0.03 (0.02) 13 128 128 128.00 (0.00) 0.05 (0.03) 7 502 502 502.00 (0.00) 0.06 (0.01) 14 118 118 118.00 (0.00) 0.67 (0.52) 8 439 439 439.00 (0.00) 0.04 (0.01) 15 110 110 110.00 (0.00) 0.80 (0.66) 9 391 391 391.00 (0.00) 0.05 (0.00) 16 105 105 105.00 (0.00) 0.34 (0.30) 10 352 352 352.00 (0.00) 0.06 (0.01) 17 98 98 98.00 (0.00) 0.19 (0.05) 11 320 320 320.00 (0.00) 0.06 (0.02) 18 93 93 93.00 (0.00) 0.16 (0.05) 12 294 294 294.00 (0.00) 0.09 (0.01) 19 89 89 89.00 (0.00) 0.05 (0.03) 13 271 271 271.00 (0.00) 0.06 (0.01) 20 85 85 85.00 (0.00) 0.14 (0.05) 14 251 251 251.80 (0.41) 20.25 (45.26) 21 80 80 80.00 (0.00) 0.11 (0.02) 15 235 235 235.00 (0.00) 0.35 (0.16) 22 76 76 76.00 (0.00) 4.20 (3.30) 16 221 221 221.00 (0.00) 0.97 (0.93) 23 74 74 74.00 (0.00) 0.29 (0.18) 17 208 208 208.00 (0.00) 1.02 (0.95) Mukherje (94) 3 1403 1403 1403.00 (0.00) 0.01 (0.00) 18 196 196 196.15 (0.37) 46.76 (39.05) 41052 1052 1052.00 (0.00) 0.10 (0.00) 19 186 186 186.35 (0.49) 87.09 (64.62) 5844 844 844.00 (0.00) 0.02 (0.00) 20 177 177 177.90 (0.31) 9.46 (39.39) 6704 704 704.00 (0.00) 0.02 (0.00) 21 170 170 170.00 (0.00) 8.71 (9.43) 7621 621 621.00 (0.00) 0.12 (0.00) 22 162 162 162.00 (0.00) 2.52 (2.45) 8532 532 532.00 (0.00) 0.09 (0.01) 23 156 156 156.00 (0.00) 0.11 (0.04) 9471 471 471.00 (0.00) 0.09 (0.01) 24 156 156 156.00 (0.00) 0.02 (0.00) 10 424 424 424.00 (0.00) 0.02 (0.00) 25 156 156 156.00 (0.00) 0.02 (0.00) 11 391 391 391.00 (0.00) 0.10 (0.01) Warnecke (58) 3 516 516 516.00 (0.00) 0.02 (0.00) 12 358 358 358.00 (0.00) 0.05 (0.01) 4 387 387 387.00 (0.00) 0.08 (0.08) 13 325 325 325.00 (0.00) 0.17 (0.06) 5 310 310 310.00 (0.00) 0.03 (0.00) 14 311 311 311.00 (0.00) 0.08 (0.01) 6 258 258 258.00 (0.00) 0.10 (0.06) 15 288 288 288.00 (0.00) 0.09 (0.02) 7 222 222 222.00 (0.00) 0.03 (0.00) 16 268 268 268.00 (0.00) 0.20 (0.02) 8 194 194 194.00 (0.00) 0.05 (0.01) 17 251 251 251.00 (0.00) 0.45 (0.05) 9 172 172 172.00 (0.00) 2.40 (2.28) 18 239 239 239.00 (0.00) 0.24 (0.02) 10 155 155 155.00 (0.00) 0.05 (0.01) 19 226 226 226.00 (0.00) 0.03 (0.01) 11 142 142 142.00 (0.00) 0.04 (0.00) 20 220 220 220.05 (0.22) 57.07 (43.23) 12 130 130 130.00 (0.00) 0.07 (0.01) 21 208 208 208.00 (0.00) 0.12 (0.00) 13 120 120 120.00 (0.00) 0.08 (0.01) 22 200 200 200.00 (0.00) 0.13 (0.06) 14 111 111 111.00 (0.00) 0.29 (0.24) 23 189 189 189.00 (0.00) 0.12 (0.02) 15 104 104 104.00 (0.00) 0.27 (0.13) 24 179 179 179.00 (0.00) 0.48 (0.41) 16 98 98 98.00 (0.00) 0.08 (0.01) 25 172 172 172.00 (0.00) 0.43 (0.18) 17 92 92 92.00 (0.00) 0.26 (0.14) 26 171 171 171.00 (0.00) 0.27 (0.03) 18 87 87 87.00 (0.00) 0.27 (0.14) Sawyer (30) 7 47 47 47.00 (0.00) 0.14 (0.11) 19 84 84 84.00 (0.00) 0.10 (0.06) 841 41 41.00 (0.00) 0.06 (0.03) 20 79 79 79.00 (0.00) 0.13 (0.03) 937 37 37.00 (0.00) 0.03 (0.01) 21 76 76 76.00 (0.00) 0.08 (0.04) 10 34 34 34.00 (0.00) 0.02 (0.00) 22 73 73 73.00 (0.00) 0.53 (0.36) 11 31 31 31.00 (0.00) 0.82 (0.85) 23 69 69 69.00 (0.00) 18.10 (21.25) 12 28 28 28.00 (0.00) 0.03 (0.01) 24 66 66 66.90 (0.31) 2.88 (9.10) 13 26 26 26.00 (0.00) 0.02 (0.00) 25 64 ∗65 65.00 (0.00) 12.30 (11.87) 14 25 25 25.00 (0.00) 0.02 (0.00) 26 64 64 64.00 (0.00) 0.05 (0.01) Scholl (297) 25 2787 2787 2787.00 (0.00) 37.11 (6.11) 27 60 60 60.00 (0.00) 1.61 (0.73) 26 2680 2680 2680.00 (0.00) 32.56 (4.71) 28 59 59 59.00 (0.00) 0.16 (0.06) 27 2580 2580 2580.00 (0.00) 58.06 (8.65) 29 56 56 56.00 (0.00) 1.43 (1.15) 28 2488 2488 2488.00 (0.00) 53.78 (12.43) Wee-Mag (75) 3 500 500 500.00 (0.00) 0.01 (0.00) 29 2402 2402 2402.00 (0.00) 45.57 (9.93) 4 375 375 375.00 (0.00) 0.03 (0.00) 30 2322 2322 2322.30 (0.47) 96.86 (53.36) 5 300 300 300.00 (0.00) 0.02 (0.00) 31 2247 ∗2248 2248.00 (0.00) 51.23 (4.32) 6 250 250 250.00 (0.00) 0.03 (0.00) 32 2177 2177 2177.50 (0.51) 91.50 (63.17) 7 215 215 215.00 (0.00) 0.01 (0.00) 33 2111 2111 2111.80 (0.41) 57.19 (39.95) 8 188 188 188.00 (0.00) 0.04 (0.01) 34 2049 2049 2049.20 (0.41) 117.47 (53.03) 9 167 167 167.00 (0.00) 0.01 (0.00) 35 1991 1991 1991.00 (0.00) 95.54 (17.19) 10 150 150 150.00 (0.00) 0.08 (0.02) 36 1935 ∗1936 1936.00 (0.00) 61.22 (8.78) 11 137 137 137.00 (0.00) 0.06 (0.01) 37 1883 1883 1883.05 (0.22) 140.57 (34.46) 12 125 125 125.00 (0.00) 0.10 (0.02) 38 1834 1834 1834.00 (0.00) 125.92 (34.53) 13 116 116 116.00 (0.00) 0.02 (0.00) 39 1787 1787 1787.35 (0.49) 192.12 (55.85) 14 108 108 108.00 (0.00) 0.54 (0.60) 40 1742 1742 1742.00 (0.00) 153.02 (29.66) 15 100 100 100.00 (0.00) 0.24 (0.19) 41 1700 1700 1700.00 (0.00) 81.51 (18.06) 16 94 94 94.00 (0.00) 0.05 (0.01) 42 1659 ∗1660 1660.00 (0.00) 146.58 (32.11) 17 89 89 89.00 (0.00) 0.42 (0.28) 43 1621 1621 1621.00 (0.00) 149.08 (21.75) 18 87 87 87.00 (0.00) 0.07 (0.01) 44 1584 1584 1584.15 (0.37) 127.52 (54.06) 19 85 85 85.00 (0.00) 0.08 (0.02) 45 1549 1549 1549.00 (0.00) 150.65 (32.59) 20 77 77 77.00 (0.00) 0.13 (0.04) 46 1515 ∗1516 1516.00 (0.00) 121.28 (20.06) 21 72 72 72.00 (0.00) 0.08 (0.01) 47 1483 ∗1484 1484.00 (0.00) 165.44 (28.64) 22 69 69 69.00 (0.00) 0.06 (0.01) 48 1452 1452 1452.70 (0.47) 151.98 (60.76) 23 67 67 67.00 (0.00) 4.34 (3.58) 49 1427 1424 1424.00 (0.00) 113.46 (22.47) 24 66 66 66.00 (0.00) 0.25 (0.14) 50 1394 1394 1394.85 (0.37) 143.63 (53.48) 25 65 65 65.00 (0.00) 11.36 (26.58) 51 1386 1386 1386.00 (0.00) 2.23 (0.09) 26 65 65 65.00 (0.00) 0.05 (0.01) 52 1386 1386 1386.00 (0.00) 0.17 (0.01) 27 65 65 65.00 (0.00) 0.02 (0.00) Tonge (70) 3 1170 1170 1170.00 (0.00) 0.01 (0.00) 28 64 64 64.00 (0.00) 0.02 (0.00) 4878 878 878.00 (0.00) 0.02 (0.00) 29 63 63 63.00 (0.00) 0.02 (0.00) 5702 702 702.00 (0.00) 0.05 (0.02) 30 56 56 56.00 (0.00) 0.07 (0.00) 19