Evaluation of struggle strategy in genetic algorithms for ground stations scheduling problem

Xhafa Xhafa, Fatos,Herrero, Xavier,Barolli, Admir,Barolli, Leonard,Takizawa, Makoto

Abstract

Ground station scheduling problem arises in spacecraft operations and aims to allocate ground stations to spacecraft to make possible the communication between operations teams and spacecraft systems. The problem belongs to the family of satellite scheduling for the specific case of mapping communications to ground stations. The allocation of a ground station to a mission (e.g. telemetry, tracking information, etc.) has a high cost, and automation of the process provides many benefits not only in terms of management, but in economic terms as well. The problem is known for its high complexity as it is an over-constrained problem. In this paper, we present the resolution of the problem through Struggle Genetic Algorithms – a version of GAs that distinguishes for its efficiency in maintaining the diversity of the population during genetic evolution. We present some computational results obtained with Struggle GA using the STK simulation toolkit, which showed the efficiency of the method in solving the problem.

Full text

Evaluation of Struggle Strategy in Genetic Algorithms for Ground Stations Scheduling Problem Fatos Xhafaa,∗, Xavier Herreroa, Admir Barollib, Leonard Barollic, Makoto Takizawab aTechnical University of Catalonia, Barcelona, Spain. bSeikei University, Tokyo, Japan. cFukuoka Institute of Technology, Fukuoka, Japan. Abstract Ground station scheduling problem arises in spacecraft operations and aims to allocate ground stations to spacecraft to make possible the communication between operations teams and spacecraft systems. The problem belongs to the family of satellite scheduling for the specific case of mapping communications to ground stations. The allocation of a ground station to a mission (e.g. telemetry, tracking information, etc.) has a high cost, and automation of the process provides many benefits not only in terms of management, but in economic terms as well. The problem is known for its high complexity as it is an over-constrained problem. In this paper, we present the resolution of the problem through Struggle Genetic Algorithms –a version of GAs that distinguishes for its efficiency in maintaining the diversity of the population during genetic evolution. We present some computational results obtained with Struggle GA using the STK simulation toolkit, which showed the efficiency of the method in solving the problem. Keywords: Ground station scheduling, Satellite scheduling, Struggle Genetic Algorithms, Constraint programming, Simulation. ∗Corresponding author. Email addresses: [email protected] (Fatos Xhafa), [email protected] (Xavier Herrero), [email protected] (Admir Barolli), [email protected] (Leonard Barolli), [email protected] (Makoto Takizawa) © 2013 Elsevier. This manuscript version is made available under the CC-BY-NC-ND 4.0 license http://creativecommons.org/licenses/by-nc-nd/4.0/ 1. Introduction Ground Station Scheduling is one of the most important problems in the field of Satellite-Scheduling. It consists in computing feasible planning of communications between satellites or spacecraft (SC) and operations teams of Ground Station (GS). The problem arises in many real life applications and projects, such as from ESA (European Space Agency) [7, 6, 2] (see Fig. 1 for ESA Tracking Network) and NASA [5]. In fact, there is a growing interest and need of the efficient resolution of the problem also from smaller projects from research institutions and universities. Ground Station Scheduling is a very complex problem due to its overconstrained nature. Indeed, there are several restrictions that make the planning of even small problem instances too complex to deal with manually or by brute force search algorithms. •The over-constrained nature: There is a large set of constraints. In fact, this is the first major difference between the problems of conventional scheduling and that of Ground Station scheduling. First, there are restrictions on the communication time required for each SC in a period of time. Secondly, there are restrictions on the visibility of each window on each Spacecraft Ground Station, i.e. the time at which each SC can communicate with each GS in a given time period. Resources are thus not available at all times for mission allocation. •Communication time variables: The second major difference with other planning algorithms is that in the case of Ground-Station Scheduling, the length of the communication is variable, where it should be at least the required communication time and at most the maximum time within which the window visibility ends or the visibility window of another communication starts. All scheduling variants, in their general formulations, are highly constrained problems and have been shown computationally hard [11, 9, 3, 13]. In this paper, we propose the resolution of Ground-Station Scheduling using Struggle Genetic Algorithms. Struggle GA is a version of GAs, which aims to keep a diverse population of individuals. For that, Struggle GA creates a new generation by replacing only a portion of the population with newly generated individuals. A new individual replaces the individual that is genetically most similar to it only in case the new individual obtains a better 2 Figure 1: ESA Tracking Network. fitness value than the one to be replaced. The aim is to avoid premature convergence and reach a better convergence point. Several similarity functions for individuals are considered (Hamming, Euclidean, Cosine and Hash-based functions) to identify the one that works best for the problem We have experimentally evaluated the Struggle GA using the STK simulation toolkit, by generating a family of instances of different sizes (small, medium, large) that tries to capture real features of the problem. The rest of the paper is organized as follows. In Section 2 we describe the Ground-Station Scheduling. The different fitness types for the problem are formulated in Section 3. The Struggle GA is given in Section 4 and its experimental evaluation in Section 5. We end the paper in Section 6 with some conclusions and remarks for future work. 2. The Ground-Station Scheduling Problem Problem input instance. The input instance is defined in Table 1. Objectives. Different types of objectives can be formulated, namely, maximizing matching of visibility windows of spacecrafts to communicate with ground stations, minimizing the clashes of different spacecrafts to one ground station, maximizing the communication time of spacecraft with ground station, and maximizing the usage of ground stations. The challenge here is to optimize several objectives. 3 Table 1: Parameters defining the input instance Parameter Description SC{i}List of Spacecrafts that participate in the planning GS{g}List of Ground Stations that participate in the planning Ndays Number of days for the schedule TAOS V IS(i)(g) Visibility time of GS to SC TLOS V IS(i)(g) Time from which a GS looses signal from SC TReq(i) Communication time required for spacecrafts Constraints. The most common constraint in Ground Station Scheduling is the clash of visibility windows caused by multiple spacecrafts willing to communicate to a ground station (see Table 2 for an example of time requirements for three spacecrafts). Table 2: Time Requirements for spacecrafts. 34 Ground Stations Scheduling with Genetic Algorithm 3.3 Data Pre-Process 3.3.1 Visibility Windows From those visibility windows, we can generate the visibility table from the ground station to its related spacecrafts. The table then is converted to a matrix format that can be processed by our computer program. The first column contains the numerical names of those satellites. The second column and third column are the TOS and LOS. Here shows a part of this matrix. € SC AOS TOS SC[1], TAOS [1]1,TLOS [1]1 SC[1], TAOS [1]2,TLOS [1]2  SC[1], TAOS [1]N,TLOS [1]N SC[2], TAOS [2]1,TLOS [2]1 SC[2], TAOS [2]2,TLOS [2]2  SC[i], TAOS [i]n,TLOS [i]n  SC[I], TAOS [I]N,TLOS [I]N ⎡ ⎣ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎤ ⎦ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ 3.3.2 Time Requirements To make the test case easy, we simplify the mission requirement. We are considering only one condition from the all the mission requirements, that is the communication link time. This defines how long the spacecraft has to communicate with the ground station in a short period. Table 3.1 Time Requirements of spacecrafts SC From (min) To (min) Require (min) Meaning 1 1 2880 60 1 hour / 2 days 1 2881 5760 60 1 hour / 2 days 1 5761 8640 60 1 hour / 2 days 1 8641 12960 60 1 hour / 2 days 2 1 2880 80 80 mins / 2 days 2 2881 5760 80 80 mins / 2 days 2 5761 8640 80 80 mins / 2 days 2 8641 12960 80 80 mins / 2 days 3 1 1440 120 2 hours / day 3 1441 2880 120 2 hours / day 3 2881 4320 120 2 hours / day 3 4321 5760 120 2 hours / day 3 5761 7200 120 2 hours / day 3 7201 8640 120 2 hours / day As an example, the data for the time windows of SC/GS is defined as in Table 3. Table 3: Resuming data specification for time windows GS SC AOS-VIS LOS-VIS TDur 11 08-FEB-2012. 12:00:00 08-FEB-2012. 14:00:00 120 min Problem output. A solution procedure to the problem should output the values of the parameters defined in Table 4. 4 Table 4: Parameters defining the problem output Parameter Description TStart(i)(g) Starting time of the communication of a SC(i) with a GS(g) TDur(i)(g) Duration time of the communication of a SC(i) with a GS(g) SC GS(i) The GS assigned to every SC(i). FitLessClash The fitness of minimizing the collision of two or more SC to the same GS for a given time period (measured from 0 to 100). FitT imeW in The fitness value corresponding to time access window for every pair GS −SC (measured from 0 to 100). FitReq Fitness value corresponding to satisfying the requirement on the mission communication time (measured from 0 to 100). FitGSU Fitness value corresponding to maximizing the usage of all GS during the planning (measured from 0 to 100). 3. Scheduling fitness types One of the major complexities of the mission operations scheduling comes from the many objectives that can be sought for the problem. These objectives are related to visibility window, communication clashes, communication time and ground station resource usage, among others. The total fitness function, besides being composed of multiple objectives, poses the challenge of how to combine them and in which order to evaluate them. For the combination, one can adopt a hierarchical optimization approach based on the priority of the objectives or a simultaneous optimization approach. In the former, objectives are sorted according to some priority criteria and are optimized according that ordering. In the later, objectives are simultaneously optimized, e.g. by summing up all fitness functions into one single fitness function. We define next the four main objectives that would compose the fitness function. 3.1. Access window fitness Visibility windows are the time periods when a GS has the possibility to setup a communication link with a SC. The objective is that all or the largest possible number of generated communication links to fall into access windows and thus achieve as many communications as possible. In the following equation, W(g,i)is the Access Window set for Ground Station gand Spacecraft i, TStart(s) and TEnd(s) are the start and end of each access window. 5 AW(g, i) = ∪S s=1[TAOS(g,i)(s), TLOS(g,i)(s)] Then, we define the final Access Window fitness of the scheduling solution (FitAW ) calculated as follows: f(n) = 1,if [TStart(n), TStart(n) + TDur(n)] ⊆AW(ng, ni), 0,otherwise. FitAW =PN n=1 f(n) N∗100, where nvalue corresponds to an event, Nis the total number of events of an entire schedule, gis a ground station and ia spacecraft (see Fig. 2). The fitness of access window is normalized so that it’s value is within 0 to 100. Figure 2: Access Window Fitness. 3.2. Communication clashes fitness Communications clash represents the event when the start of one communication task happens before the end of another one on the same ground station. The objective is to minimize the clashes of different spacecrafts to one ground station. To compute the number of clashes, SCs are sorted by their start time. If, as a result of the sorting: TStart(n+ 1) < TStart(n) + TDur(n),1≤n≤N−1 where nvalue corresponds to an event and Nis the total number of events of an entire schedule, then there is a clash. The fitness will be reduced, and 6 one of the clashed entries has to be removed from the solution (see Fig. 3 for an example). The total fitness of communication clashes is then: f(n) = −1,if TStart(n+ 1) < TStart(n) + TDur(n), 0 otherwise. FitCS =N+PN n=1 f(n) N Figure 3: Fitness communication clashes. 3.3. Communication time requirement fitness The objective is to maximize the communication time of spacecrafts with ground stations so that every spacecraft SC(i) will communicate at least Treq(i) time. Thus, a sufficient amount of time should be granted for TTC (Telemetry, Tracking and Command). For example, satellites that need to download huge amount of image data require more time for linking with ground stations. These communications, especially for data download tasks are usually periodical tasks (e.g. 2 hours communication for SC1 each day, 5 hours data downlink for SC2 every 2 days, etc.) A matrix is used to define those requirements, which is used as the input for the scheduling system (see Fig. 4 for an example.) The fitness is calculated by summing up all the communication link durations of each spacecraft, and dividing them in the required period to compare if the scheduled time matches requirements (see Eqs. (1) and also Fig 5). 7 46 Ground Stations Scheduling with Genetic Algorithm Time requirement is the most basic requirement of the spacecraft communicating with ground facilities. A sufficient amount of time should be guaranteed for TTC (Telemetry, Tracking and Command), also, depend on the mission type, there are different amount of data need to be downloaded from the spacecraft. For example, satellites that need to download huge amount of image data requires more time for linking with ground station. Some other scientific mission (such Mars Express) may need even more time to communication because the link capacity is less than usual near earth spacecraft. Those communications, especial for data download tasks are usually a periodical process. And provided as requirements like: 2 hours communication for SC1 each day, 5 hours data downlink for SC2 every 2 days, etc. Scheduling system need this information to be converted into a machine understandable format, and then process them. A matrix is used for define those requirement. It is the input for the scheduling system. The time requirements are shown as left. The fitness is calculated by summarizing all the communication link durations of each spacecraft, and divides them in the required period to compare if the scheduled time matches requirements. Following equations describes the mathematical process. For m and n in following conditions: € TStart (m)>TFrom (k) TStart (n)+TDur (n)<T TO (k) We have the communication time with the period TFrom(k) and TTO(k): € TComm (k)=TDur (j) j=m n ∑ Then we have the Fitness calculated: € f(k)=1, TComm (k)≥TREQ (k) 0, else ⎧ ⎨ ⎩ FitTR =f(k) k=1 K ∑ € SC From To TREQ[Min] SC[1] TFrom[1]1TTO[1]1TREQ [1]1 SC[1] TFrom[1]2TTO[1]2TREQ [1]2  SC[1] TFrom[1]NTTO[1]NTREQ [1]N SC[2] TFrom [2]1TTO[2]1TREQ [2]1 SC[2] TFrom [2]2TTO[2]2TREQ [2]2  SC[i]TFrom [i]nTTO[i]nTREQ [i]n  SC[I]TFrom [I]NTTO [I]NTREQ [I]N ⎡ ⎣ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎢ ⎤ ⎦ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ ⎥ Figure 4: Matrix representation of periodic tasks. TStart(m)> TF rom(k) TStart(n) + TDur(n)< TT O(k) TComm(k) = TDur(j) (1) f(k) = 1,if TComm(k)≥TREQ(k), 0 otherwise. FITT R =PK k=1 f(k) N·100. 3.4. Ground station usage fitness Given that the number of ground stations is usually smaller than the number of spacecrafts missions, the objective is to maximize the usage of ground stations, that is, try to reduce the idle time of a ground station. A maximized usage would contribute to provide additional time for SC communications (see Fig. 6 for an example). This fitness value is calculated as the percentage of ground stations occupied time by the total amount of the possible communication time. The more a GS is used, the better is the corresponding schedule. FitGU =PN n=1 TDur(n) PG g=1 TT otal(g)·100. 8 Figure 5: Fitness Requirements . Figure 6: Ground station usage. where Nis the number of events of an entire schedule, Gis the number of ground stations and TT otal(g)is the total available time of a ground station 3.5. Combination of fitness objectives The fitness objectives defined above (F ITAW ,FITCS,FITT R,F ITGU ) are conceived as fitness modules so as to facilitate the design phase of the scheduler to easily plug-in other fitness objectives. From the definition of the fitness objectives, we can observe that some of them can be applied in serial fashion (due dependencies, denoted serial-FM), while some others can be applied in parallel (denoted parallel-FM). Thus, in a hierarchical mode, one possible way to arrange fitness checking is that of Fig. 7. 9 c) Task-resource allocation key: In this case both information on tasks and ground stations is used. The key value is now the sum of the absolute values of the subtraction of each position and its precedent in the vector of task-ground station allocation (reading the vector in a circular way); we refer to this as ’c’ key. We give in Fig. 10 the graphical representation of the hash table design as well as the formulae definition of the hash function. Note that the corresponding position is obtained from a solution from the key value k;kmin and kmax correspond respectively to the key with smallest and largest value in the population. 63 4 2 4 1 2 3 1 1 2 3 |4 – 3|=1 |2 – 4|=2 2 3 1 1 2 0 1 1 Exemple 1: (10 tasques i 4 recursos) key = 1 + 2 + 2 + 3 + 1 + 1 + 2 + 0 + 1 + 1 = 14 De la mateixa manera que la clau b, aquesta clau té en compte totes les posicions del vector que conforma la representació genètica. Malauradament, cap de les claus definides fins ara no garanteix que dues solucions que puguin ser considerades poc similars, no obtinguin claus similars. Això no obstant, dues solucions que podrien ser considerades similars amb una alta probabilitat constaran de claus molt properes. Aquesta propietat ja és suficient per la taula de hash que requereix l’operador struggle, donat que una solució de la descendència sempre procedeix d’informació genètica continguda en solucions de la generació precedent, per tant hi ha d’haver sempre alguna solució vella que s’assembli més a la nova que la resta de les solucions velles, i per tant serà fàcilment identificable. 0 si k < kmin fhash (k) =                 − − minmax min kk kk N si kmin ≤ k < kmax N-1 si k ≥ kmax Figura 3.11 Representació de la taula de hash emprada juntament amb la funció de hash, amb la qual s’obté la posició corresponent d’una solució a partir de la clau k d’aquesta. kmax i kmin corresponen respectivament a la clau amb valor més petit i la clau amb valor més gran dins de la població La taula de hash emprada té una mida equivalent a la mida de la població global per tal d’obtenir un cost d’accés mig constant. El cas ideal és que hi hagi una posició per cadascun dels individus de la població, i com més ben definida estigui la clau més es tendirà a aquesta situació. La taula s’indexa fent correspondre cadascun dels indexes de la taula amb un rang de 0 1 2 i+1 N N -1 i s y s z s x Ø s q s t s u s r s s Figure 10: Representation of the hash table and the hash function definition. The hash table has the same size as the population in order to obtain constant time access (in average). If an access fails, a few individuals in the population are randomly chosen and the most similar to the new one is considered for the replacement. Hence, the constant access is always ensured even if a failed access occurs. Therefore, the computational cost of the hash-based struggle operator is linear time O(pop size + intermediate pop size). 16 4.4. Chromosome encoding and GA operators For the chromosome encoding, initial population and GA operators (crossover, mutation, selection) see [14, 15]. 5. Computational results 5.1. Problem instances We present some computational results obtained with Struggle GA for the ground stations scheduling problem. The Satellite Tool Kit (STK) [12] is used to generate some simulation scenarios of small, medium and large sizes, described in Table 5. Table 5: Different size instances description Small size Instances Number of Ground Stations 5 Spacecrafts number 10 Number of days 10 Medium size instances Number of Ground Stations 10 Spacecrafts number 15 Number of days 10 Large size instances Number of Ground Stations 15 Spacecrafts number 20 Number of days 10 5.2. GA parameters A total of 20 independent runs of the Struggle GA were performed (under the same parameter configuration –see Table 6) and average results are reported. 17 Table 6: Struggle GA parameter values Parameter Value Number of evolution steps 30000 Crosspoint chromosome A 10 Crosspoint chromosome B 3 Mutation rate chromosome A 15% Mutation rate chromosome B 5% Crossover probability 80% Mutation probability 20% 5.3. The effect of the population size We show in Fig. 11 the graphical representation of the evolution of the total fitness function for different population sizes (varying from 5 to 30) and different independent runs (only 5 independent runs are shown). As can be seen in the figure, when the population size exceeds a certain size, the results of total fitness becomes worse. This is due a large population requires more time to transmit good genes to offsprings when only one individual is replaced at once. The threshold of the population size is about 20 individuals. Figure 11: Evolution of total fitness for different population sizes. Obviously, the larger the population size, the greater is the time needed to processing a population. This is more critical in case of Struggle GA due the computation of similarity function. We study the increase of execution time to see the effect of the increase of population size. As can be seen from Fig. 12, the increase in execution time is almost linear, which confirms the efficiency of the implementation of the hash similarity measures. 18 Facultat Informàtica de Barcelona - Resolució de “Ground-Station Scheduling” amb mètodes heurístics 93 Com podem veure a la figura, tot i que hi ha la tendència de que per valors baixos obtenim pitjor resultats i conforme creix la població, tenim millors son els resultats; el que veiem és que la mida de la població no es un factor crucial en la millora dels resultats. Aquesta deducció la hem determinat perquè els resultats no segueixen cap regla establerta. A continuació, mirarem els temps d’execució segons la mida de la població. figura 6.3.2 – Evolució del temps d’ execució segons la mida de la població En aquest cas, la mida de la població afecta directament al temps d’execució, atès que s’hauran de mirar més individus a l’hora de calcular la funció de similaritat. Per a les proves agafarem una mida de 30 individus, que ha resultat ser el millor valor dels comparats, tot i sacrificar en part el temps d’execució. 6.1.4.1.2 Modificació del percentatge de mutació pel cromosoma A 6.1.4.1.2.1 Tstart A continuació, mirarem la configuració del percentatge de mutació (mutation rate) del Tstart del cromosoma A. Ajuntem la taula amb el context i la gràfica amb els diversos percentatges de mutació i com afecten al FitTOT. Paràmetre Configuració Número de passos evolutius 30000 Número d’execucions indp. 5 Crosspoint cromosoma A 10 Crosspoint cromosoma B 3 Mida de la població 30 Mutation rate A (Tdur) 5% Mutation rate B 5% Probabilitat de crossover 80% Probabilitat de mutation 20% I posteriorment una gràfica de com afecta el mutation rate del cromosoma A al FitTOT de StGA. Figure 12: Evolution of execution time for different population sizes (5 independent runs). 5.4. The effect of the mutation probability Given the importance of the mutation, we studied the variation of the total fitness for different values of the mutation probability. We show in Fig. 13 the graphical representation of the evolution of the total fitness function for different mutation probability values (varying from 1% to 5%) and different independent runs (only 5 independent runs are shown). Figure 13: Evolution of total fitness for different mutation probabilities. 5.5. The effect of different similarity measures The similarity measure is a key factor in Struggle GA as it determines the convergence speed of the algorithm. The experimental study showed that hash similarity function outperforms other similarity measures. On the other 19 hand, within hash version, the c key, which takes into account not only the tasks but also resources, is a better option than b key, which considers only the positions of the tasks within the schedule. Figure 14: Evolution of total fitness for different hash similarity measures. 5.6. Computational results for different instance sizes Based on the tuning of parameters presented in the above sections, computational results were obtained for each group of instances (small, medium and large –see Table 5). We give the computational results in Tables 7, 9 and 11, respectively. The standard deviation for each case is given in Tables 8, 10 and 12, respectively. Execution times (averaged) are in seconds. In the table instances are denoted by I t k , where tis the type (S–Small, M–Medium, L–Large size) , and kthe instance number (k=1 . . . 16). 5.7. Evaluation From the computation results, it can be observed that the Struggle GA computed high quality solutions in terms of different fitness values. This is mainly due the algorithm achieves to maintain a diverse population through the search process. In particular hash based similarity measures contribute to such population diversity even in case of large size instances. Compared to a base GA implementation, the Struggle GA performed much better and consistently on different groups of problem instances. 6. Conclusions and future work Window time scheduling problems are well-known for their computational complexity due they are over-constrained scheduling problems. One 20 Table 7: Fitness values for small size instances. Instance F itwin F itLessClash F itT imeReq F itGSU F itT OT Ex. Time I S 01 99 70 98.94 66.86 1096.6 39.84 I S 02 99 70 94.32 65.14 1091.97 40.02 I S 03 99 57 98.9 69.11 1095.29 39.86 I S 04 99 78 100 61.5 1098.42 39.66 I S 05 100 52 97.7 61.1 1103.51 39.83 I S 06 99 66 96.63 59.01 1093.82 40.91 I S 07 99 71 94.44 60.79 1092.15 39.71 I S 08 99 74 100 61.81 1098.02 40.17 I S 09 99 64 96.59 62.53 1093.62 40.08 I S 10 100 69 97.85 66.06 1105.41 39.98 I S 11 99 66 96.7 52.94 1093.83 41.07 I S 12 98 74 96.74 57.08 1084.71 40.22 I S 13 99 76 93.68 66.19 1091.95 40.05 I S 14 100 65 91.95 49.36 1098.95 41.73 I S 15 98 72 97.78 67.69 1085.65 40.14 I S 16 81 80 98.31 69.38 917 39.78 Table 8: Mean and std deviation for small size instances. Fitwin FitLessClash F itT imeReq FitGSU F itT OT Ex. Time Mean 99.07 68.27 96.82 61.81 1094.93 40.22 Std deviation 0.59 6.96 2.35 5.53 5.63 0.57 Table 9: Fitness values for medium size instances. Instance F itwin F itLessClash F itT imeReq F itGSU F itT OT Ex. Time I M 01 96.67 74 96.21 44.21 1070.72 104.12 I M 02 98.67 78 98.5 44.06 1093.4 108.45 I M 03 98 84 92.59 44.41 1081.44 105.07 I M 04 98 76 98.53 51.73 1086.65 106.78 I M 05 99.33 80 96.43 46.71 1098.23 104.15 I M 06 97.33 88 93.18 45.74 1075.77 104.15 I M 07 98 68.67 91.3 44.78 1078.62 104.34 I M 08 99.33 61.33 97.14 51.38 1097.12 104.3 I M 09 97.33 68 97.76 42.96 1078.32 104.42 I M 10 99.33 71.33 96.24 40.27 1097.11 107.06 I M 11 98 80 96.99 49.09 1085.48 104.23 I M 12 98 75.33 97.79 50.1 1085.83 105.52 I M 13 98.67 76 97.71 51.36 1092.49 104.77 I M 14 98.67 57.33 94.74 45.77 1087.59 105.89 I M 15 99.33 85.33 97.79 49.22 1100.15 105.07 I M 16 64 92.67 96.55 50.76 746.33 101.53 Table 10: Mean and std deviation for medium size instances. Fitwin FitLessClash F itT imeReq FitGSU F itT OT Ex. Time Mean 98.31 74.89 96.19 46.79 1087.26 105.22 Std deviation 0.83 8.54 2.24 3.5 9.05 1.31 21 Table 11: Fitness values for large size instances. Instance F itwin F itLessClash F itT imeReq F itGSU F itT OT Ex. Time I L 01 97 76.5 95.03 42.8 1073.11 198.53 I L 02 99 84.5 94.77 39.21 1093.61 202.21 I L 03 99 87.5 93.64 39.45 1092.79 200.21 I L 04 98 80 97.18 47.94 1085.65 198.36 I L 05 98.5 73.5 93.01 39.1 1085.75 199.68 I L 06 97 76.5 95.05 38.01 1073.09 198.24 I L 07 97.5 74.5 94.51 35.35 1077.31 198.46 I L 08 96 76 95.56 36.48 1063.52 200.92 I L 09 96 80.5 93.18 38.85 1061.62 200.05 I L 10 98 80 94.54 37.33 1082.91 201.25 I L 11 96 71 95.05 44.17 1062.6 200.43 I L 12 99 68.5 98.27 41.31 1095.53 201.72 I L 13 96.5 76.5 94.41 38.49 1067.45 198.78 I L 14 98.5 72 97.3 40.21 1089.9 202.92 I L 15 96 79 96.05 37.18 1064.32 198.28 I L 16 64 88.5 94.62 53.22 744.01 194.46 Table 12: Mean and std deviation for large size instances. Fitwin FitLessClash F itT imeReq FitGSU F itT OT Ex. Time Mean 97.47 77.1 95.17 39.73 1077.94 200 Std deviation 1.19 5.03 1.5 3.24 12.29 1.55 such problem is that of Ground Station Scheduling, which arises in mission operations for the efficient management of satellite/space missions for communication of spacecrafts with ground stations. The problem is to efficiently allocate a large number of missions (tasks) to a rather small number of ground stations (resources). Given the computational hardness of the problem, meta-heuristics are resolution methods to cope in practice with its efficient resolution. In this paper we have presented the evaluation of Struggle Genetic Algorithms for the problem. Struggle GA is a version of GAs in which an individual replaces another individual of the population only if it has better fitness but additionally should be genetically similar to the individual to be replaced. The aim in Struggle GA is to control the convergence of the GA and avoid premature convergence. This is done by implementing several similarity measures, including some hash-based functions, which achieve high efficiency. We have evaluated the Struggle GA using the STK simulation toolkit. Three groups of different size instances are generated, namely, small, medium and large, aiming to simulate realistic features of the problem. The Struggle GA was able to compute high quality schedules in very short times. 22 In our future work we would like to implement a parallel version of the Struggle GA to speed up the processing time due computations on populations and genetic operators. This speed up would benefit the proper search time of the GA algorithm. References [1] S. Badaloni, M. Falda and M. Giacomin Solving temporal over-constrained problems using fuzzy techniques. Journal of Intelligent and Fuzzy Systems, 18(3), 255-265, 2007 [2] L. Barbulescu, A. Howe, J. Watson, L. Whitley. Satellite Range Scheduling: A Comparison of Genetic, Heuristic and Local Search. Parallel Problem Solving from Nature –PPSN, VII: 611-620, 2002. [3] L. Barbulescu, J.-P. Watson, L. D. Whitley and A. E. Scheduling spaceground communications for the air force satellite control network. Journal of Scheduling, 7(1), 7-34, 2004. [4] L. Barbulescu, A.E. Howe, L.D. Whitley, and M. Roberts. Trading places: How to schedule more in a multi-resource oversubscribed scheduling problem. In Proceedings of the Fourteenth International Conference on Automated Planning and Scheduling (ICAPS-2004), 227-234, 2004. [5] L. Barbulescu, A.E. Howe, D. Whitley. AFSCN scheduling: How the problem and solution have evolved. Mathematical and Computer Modelling, 43(9-10): 1023-1037, 2006. [6] S. Damiani, H. Dreihahn, J. Noll, M. Nizette, and G.P. Calzolari. A Planning and Scheduling System to Allocate ESA Ground Station Network Services. The Int’l Conference on Automated Planning and Scheduling, USA, 2007. [7] ESA Science & Technology. http://www.esa.int/ [8] T. Grueninger. Multimodal optimization using genetic algorithms. Technical report. Department of Mechanical Engineering, MIT, Cambridge, MA, 1997. [9] J. C. Pemberton and F. Galiber. A constraint-based approach to satellite scheduling. In DIMACS workshop on Constraint programming and large scale discrete optimization, Eugene C. Freuder and Richard J. Wallace (Eds.). American Mathematical Society, Boston, MA, USA, 101-114, 2000. 23 [10] A. Sarkheyli, B.G. Vaghei, A. Bagheri. New tabu search heuristic in scheduling earth observation satellites. In Proceedings of 2nd International Conference on Software Technology and Engineering (ICSTE), V2-199 - V2-203, 2010. [11] W. T. Scherer, F. Rotman. Combinatorial optimization techniques for spacecraft scheduling automation. Annals of Operations Research, 50(1):525-556, 1994. [12] Satellite Tool Kit: http://www.agi.com/products/by-product- type/applications/stk/ [13] N. Zufferey, P. Amstutz, P. Giaccari. Graph Colouring Approaches for a Satellite Range Scheduling Problem. Journal of Scheduling, 11(4):263-277, 2008. [14] J. Sun, F. Xhafa: A Genetic Algorithm for Ground Station Scheduling. International Conference on Complex, Intelligent and Software Intensive Systems, CISIS 2011, June 30 - July 2, 2011, Korea, 138-145. [15] F. Xhafa, J. Sun, A. Barolli, M. Takizawa, K. Uchida: Evaluation of Genetic Algorithms for Single Ground Station Scheduling Problem. IEEE 26th International Conference on Advanced Information Networking and Applications, AINA-2012, Japan, March 26-29, 2012, 299-306. 24