TFG Report Viability, design and implementation and business plans of a regional airport in Europe Aerospace Technologies Engineering Degree Student: Vlad Tudoran Pavalan Director: Rubén Martínez Sevillano Date of delivery: 13th January 2021
UPC-ESEIAAT ABSTRACT Although being the continent with the highest number of airports, Europe has some problems in terms of air transport. There are a few zones which have the need of being better communicated in terms of air transit and there are other zones which are too saturated, which cause the airport of that zone to be congested. This congestion slows down the evolution of air traffic in that particular zone, which causes great losses of revenue and a poor level of service. To solve these problems, this project aims to demonstrate that these issues can still be found in Europe, to find a location in need of a regional airport and to develop it in all the aspects that are involved. The project begins with the selection and justification of the location of the new airport, where it is demonstrated that Europe is still in need of airports. Then, traffic forecasts will be performed so as to calculate the demand of the airport. Once the results are obtained, the airside and the landside are described and defined, as well as the reserved airport zone. Next, an environmental and social impact study will be performed to see what how the new airport can affect its location. Last but not least, a business plan and an implementation plan will be made to analyse the economic viability of the project and how it will evolve over time. The development of this project is based on the sources of the main airport authorities: the International Civil Aviation Organisation and the International Air Transport Association. Therefore, their documentation has been used to ensure that all the regulations are fulfilled. It is hoped that this project helps the reader to have a more in-depth insight of the new regional airport that is proposed in Europe. It is also hope that it encourages to spread the word, which would help fund this project. TFG Report Page 1 of 167
UPC-ESEIAAT HONOUR DECLARATION I declare that, the work in this Degree Thesis is completely my own work, no part of this Degree Thesis is taken from othe people’s work without giving them credit, all references have been clearly cited, I understand that an infringement of this declaration leaves me subject to the foreseen disciplinary actions by The Universitat Politècnica de Catalunya - BarcelonaTECH. Title of the Thesis: Viability, design and implementation and business plans of a regional airport in Europe. TFG Report Page 2 of 167
UPC-ESEIAAT CONTENTS Contents List of Tables 6 List of Figures 8 Executive summary 10 1 Introduction 18 1.1 Aimoftheproject ................................ 18 1.2 Scopeoftheproject ............................... 18 1.3 General requirements of the project . . . . . . . . . . . . . . . . . . . . . . . 18 1.4 Background and justification of the project . . . . . . . . . . . . . . . . . . 19 2 Selection and justification of the airport’s location 20 2.1 Establishment of the airport’s requirements . . . . . . . . . . . . . . . . . . 20 2.1.1 Technical factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 2.1.2 Socioeconomic factors . . . . . . . . . . . . . . . . . . . . . . . . . . 22 2.1.3 Final requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23 2.2 Proposal of potential locations for the regional airport . . . . . . . . . . . . 24 2.2.1 First filter: contrast of the population density map and the airport map .................................... 24 2.2.2 Second filter: purchasing power . . . . . . . . . . . . . . . . . . . . . 25 2.3 Comparison among the potential locations for the regional airport . . . . . . 27 2.3.1 Germany ................................. 27 2.3.2 Netherlands................................ 30 2.3.3 Czechia .................................. 33 2.3.4 Belgium.................................. 36 2.3.5 Ireland................................... 38 2.3.6 Comparative table for the potential locations . . . . . . . . . . . . . 40 2.4 Selection and justification of the final decision of the airport’s location . . . 41 3 General characterisation of the regional airport 45 3.1 Benefits of the airport for its region . . . . . . . . . . . . . . . . . . . . . . . 45 3.2 Identification of the effects of locating the airport in the zone . . . . . . . . 45 3.3 Establishment of the regulations that will be followed . . . . . . . . . . . . . 46 3.4 New airport system in Munich . . . . . . . . . . . . . . . . . . . . . . . . . . 46 4 Traffic forecast 47 4.1 Study of the peak scenarios of the regional airport . . . . . . . . . . . . . . 47 4.1.1 First filter: Star Alliance remains in the Airport of Munich . . . . . 47 4.1.2 Second filter: wide-bodied aircraft remain in the airport of Munich . 48 4.1.3 Filtered results: absorbed traffic of the new airport . . . . . . . . . . 48 4.2 Forecast of the annual traffic expected . . . . . . . . . . . . . . . . . . . . . 58 4.2.1 Similarity of the airport system of Munich and others in Germany . 58 4.2.2 Stages of the airport’s growth . . . . . . . . . . . . . . . . . . . . . . 60 5 Description of the airside 67 5.1 Definition of the design aircraft and of the aerodrome reference code . . . . 67 5.2 Description of the runway system . . . . . . . . . . . . . . . . . . . . . . . . 68 5.2.1 Length................................... 69 5.2.2 Orientation and denomination . . . . . . . . . . . . . . . . . . . . . . 70 5.2.3 Capacity.................................. 72 TFG Report Page 3 of 167
UPC-ESEIAAT CONTENTS 5.2.4 Typeofoperations............................ 77 5.2.5 Configuration............................... 77 5.2.6 Dimensions ................................ 77 5.3 Description of the taxiway system . . . . . . . . . . . . . . . . . . . . . . . . 79 5.3.1 Types of taxiways . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80 5.3.2 Dimensions ................................ 81 5.3.3 Final decision of the taxiway system . . . . . . . . . . . . . . . . . . 83 5.4 Description of the bypass system . . . . . . . . . . . . . . . . . . . . . . . . 84 5.4.1 Types of bypasses . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 5.4.2 Dimensions ................................ 86 5.4.3 Final decision of the bypass system . . . . . . . . . . . . . . . . . . . 86 5.5 Description of the apron system . . . . . . . . . . . . . . . . . . . . . . . . . 87 5.5.1 Typesofaprons.............................. 88 5.5.2 Types of apron layouts . . . . . . . . . . . . . . . . . . . . . . . . . . 88 5.5.3 Size of the apron area . . . . . . . . . . . . . . . . . . . . . . . . . . 91 5.5.4 Final decision of the apron system . . . . . . . . . . . . . . . . . . . 94 5.6 Visual aids in the airport . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97 5.7 Other factors concerning the airside . . . . . . . . . . . . . . . . . . . . . . . 99 5.7.1 Strength of pavement . . . . . . . . . . . . . . . . . . . . . . . . . . 99 5.7.2 Surface of pavement . . . . . . . . . . . . . . . . . . . . . . . . . . . 99 5.7.3 Slopes................................... 99 5.8 Description of the obstacle limitation surfaces . . . . . . . . . . . . . . . . . 99 6 Description of the landside 104 6.1 Design of the terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 104 6.2 Planning of the terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105 6.3 Airport terminal Level of Service . . . . . . . . . . . . . . . . . . . . . . . . 106 6.4 Airport terminal capacity . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108 6.5 Landside access systems and forecourts . . . . . . . . . . . . . . . . . . . . . 109 6.6 Trafficflows....................................110 6.6.1 Departures ................................110 6.6.2 Arrivals ..................................115 6.6.3 Transfers .................................117 6.7 Other considerations and facilities . . . . . . . . . . . . . . . . . . . . . . . . 117 6.7.1 Security requirements in airport terminal . . . . . . . . . . . . . . . 117 6.7.2 Commercial and retail businesses . . . . . . . . . . . . . . . . . . . . 117 6.7.3 Access to air travel for person with reduced mobility . . . . . . . . . 118 6.7.4 Toilet provisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118 6.7.5 Passenger wayfinding and signage . . . . . . . . . . . . . . . . . . . . 118 6.8 Capacity equations for sizing the terminal building facilities . . . . . . . . . 118 6.8.1 Sizing of self-service kiosks . . . . . . . . . . . . . . . . . . . . . . . . 119 6.8.2 Sizing of baggage drop facilities . . . . . . . . . . . . . . . . . . . . . 121 6.8.3 Sizing of traditional check-in facilities . . . . . . . . . . . . . . . . . 123 6.8.4 Sizing of emigration facilities . . . . . . . . . . . . . . . . . . . . . . 125 6.8.5 Sizing of passenger security screening facilities . . . . . . . . . . . . . 127 6.8.6 Sizing of boarding gates lounges facilities . . . . . . . . . . . . . . . 128 6.8.7 Sizing of immigration facilities . . . . . . . . . . . . . . . . . . . . . 130 6.8.8 Sizing of baggage claim facilities . . . . . . . . . . . . . . . . . . . . 131 6.8.9 Sizing of customs facilities . . . . . . . . . . . . . . . . . . . . . . . . 132 6.8.10 Sizing of arrivals hall facilities . . . . . . . . . . . . . . . . . . . . . . 134 6.8.11 Sizing of the commercial concessions . . . . . . . . . . . . . . . . . . 134 6.8.12 Summary of the sizing of facilities . . . . . . . . . . . . . . . . . . . 134 TFG Report Page 4 of 167
UPC-ESEIAAT CONTENTS 6.9 Distribution of the facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . 138 7 Description of the reserved airport zone 140 8 Additional airport facilities and infrastructures 142 8.1 Rescue and firefighting service . . . . . . . . . . . . . . . . . . . . . . . . . . 142 8.2 De-icing and anti-icing facilities . . . . . . . . . . . . . . . . . . . . . . . . . 144 8.3 Controltower...................................145 9 Environmental and social impact study 147 9.1 Environmental impact associated with aviation activities . . . . . . . . . . . 147 9.1.1 Aircraft noise and its management . . . . . . . . . . . . . . . . . . . 147 9.1.2 Air quality and its management . . . . . . . . . . . . . . . . . . . . . 148 9.1.3 Greenhouse gases and climate change . . . . . . . . . . . . . . . . . . 148 9.1.4 Water and soil pollution and its management . . . . . . . . . . . . . 148 9.1.5 Waste and its management . . . . . . . . . . . . . . . . . . . . . . . 149 9.1.6 Flora and fauna and its management . . . . . . . . . . . . . . . . . . 149 9.1.7 Energy management . . . . . . . . . . . . . . . . . . . . . . . . . . . 149 9.2 Social impact associated with aviation activities . . . . . . . . . . . . . . . . 149 9.2.1 Landuse .................................149 9.2.2 Land use decisions and management . . . . . . . . . . . . . . . . . . 150 9.2.3 Heritage..................................152 10 Business plan 153 10.1 Capital expenditure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153 10.2 Operational expenditure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 154 10.3Revenues .....................................154 11 Implementation plan 156 11.1 Phase 0: pre-construction considerations . . . . . . . . . . . . . . . . . . . . 156 11.2 Phase 1: construction of the airside . . . . . . . . . . . . . . . . . . . . . . . 156 11.3 Phase 2: construction of the landside . . . . . . . . . . . . . . . . . . . . . . 156 11.4 Phase 3: additional infrastructures and facilities . . . . . . . . . . . . . . . . 156 11.5Ganttchart....................................157 12 Suggestions for the follow-up of the project 159 13 Conclusions and recommendations 161 14 Bibliography 164 TFG Report Page 5 of 167
UPC-ESEIAAT LIST OF TABLES List of Tables 1 Annual forecasts for passengers and aircraft movements for each scenario . . 14 2 Countries of Europe and application of the first filter . . . . . . . . . . . . . 25 3 Flights per year based on the net monthly average salary and the population for each country (year 2018)........................... 26 4 Comparative table with the marks for all the factors for all the countries . . 41 5 Application of the OWA Method ........................ 41 6 Relevant information about the airlines from arrivals after applying the filters 48 7 Relevant information about the aircraft from arrivals after applying the filters 49 8 Relevant information about the hours of arrivals after applying the filters . 49 9 Relevant information about the airlines from departures after applying the filters ....................................... 50 10 Relevant information about the aircraft from departures after applying the filters ....................................... 50 11 Relevant information about the hours of departures after applying the filters 51 12 Relevant information about the airlines from the mixture of arrivals and departures after applying the filters . . . . . . . . . . . . . . . . . . . . . . . 51 13 Relevant information about the aircraft from the mixture of arrivals and departures after applying the filters . . . . . . . . . . . . . . . . . . . . . . . 52 14 Relevant information about the hours of the mixture of arrivals and departures after applying the filters . . . . . . . . . . . . . . . . . . . . . . . . . . 52 15 Number of flights per hour for arrivals, departures and their mixture . . . . 53 16 Correction factor as a function of the number of aircraft movements in the mixture of arrivals and departures . . . . . . . . . . . . . . . . . . . . . . . 54 17 Hourly distribution of aircraft movements in a no-COVID-19 scenario . . . . 54 18 Hourly distribution of passengers in a no-COVID-19 scenario . . . . . . . . 55 19 Traffic figures of Berlin Schönefeld and Berlin Tegel [37] . . . . . . . . . . . 59 20 Traffic figures of Munich [10] . . . . . . . . . . . . . . . . . . . . . . . . . . 60 21 Comparison of CAGR between the airports of Munich and Tegel (from 1992 to 2019)...................................... 60 22 Duration and CAGR for aircraft movements and passengers for each stage . 61 23 Annual growth rate of the flights for the three above-mentioned scenarios from2020to2024[42] .............................. 63 24 Annual forecasts for aircraft movements and passengers for the new airport forthethreescenarios .............................. 64 25 Duration of each stage for each scenario . . . . . . . . . . . . . . . . . . . . 64 26 List of aircraft ordered from largest to smallest frequency . . . . . . . . . . 67 27 Direction, velocity and number of yearly hours of the blowing wind (from 2007 to 2020)................................... 71 28 Direction, velocity and number of yearly frequency of the blowing wind (from 2007 to 2020) ............................... 71 29 Classifications of aircraft [46] . . . . . . . . . . . . . . . . . . . . . . . . . . 74 30 Outer main gear wheel span and wheel base of all the aircraft that the new airportwillserve ................................. 82 31 Landing field lengths for all the aircraft that the new airport serves . . . . . 84 32 Type or aircraft stand for each aircraft and other information . . . . . . . . 95 33 Type or aircraft stand for each aircraft and percentage of use . . . . . . . . 95 34 Dimensions and slopes of obstacle limitation surfaces for a runway of aerodrome reference code 4C with precision approach category III [43] . . . . . 101 35 Acronyms, definitions and values of the data used to size the self-service kiosks119 TFG Report Page 6 of 167
UPC-ESEIAAT LIST OF TABLES 36 Correction factor (CF) for demand variability (when less than 30-minute peak)[64] .....................................120 37 QMAX calculation factor (QF)[64].......................120 38 Acronyms, definitions and values of the data used to size the bag drop facilities121 39 Acronyms, definitions and values of the data used to size the traditional check-infacilities .................................123 40 Acronyms, definitions and values of the data used to size the emigration facilities......................................125 41 Acronyms, definitions and values of the data used to size the passenger security screening facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 42 Acronyms, definitions and values of the data used to size the boarding gates loungesfacilities .................................128 43 Acronyms, definitions and values of the data used to size the immigration facilities......................................130 44 Acronyms, definitions and values of the data used to size the baggage claim facilities......................................131 45 Acronyms, definitions and values of the data used to size the customs facilities132 46 Acronyms, definitions and values of the data used to size the arrivals hall facilities......................................134 TFG Report Page 7 of 167
UPC-ESEIAAT LIST OF FIGURES List of Figures 1 Hourly distribution of aircraft movements at the new airport without COVID- 19 ......................................... 12 2 Hourly distribution of passengers at the new airport without COVID-19 . . 13 3 Gantt chart of the implementation plan (zoom to better visualise) . . . . . 16 4 European airports with more than 1,000,000 annual passengers (2009) [1] . 19 5 Average passenger fare in euros for different airlines (year 2019) [6] . . . . . 26 6 Map of German airports that have scheduled service on commercial airlines [4] and proposed location for Germany (red dot) . . . . . . . . . . . . . . . 28 7 German population density map [11] . . . . . . . . . . . . . . . . . . . . . . 29 8 Network of roads of the German area of influence . . . . . . . . . . . . . . . 30 9 Map of Dutch airports that have scheduled service on commercial airline [4] and proposed location for the Netherlands (red dot) . . . . . . . . . . . . . 31 10 Dutch population density map [14] . . . . . . . . . . . . . . . . . . . . . . . 31 11 Network of roads of the Dutch area of influence . . . . . . . . . . . . . . . . 32 12 Map of Czech airports that have scheduled service on commercial airlines [4] and proposed location for the Czechia (red dot) . . . . . . . . . . . . . . 33 13 Czech population density map [19] . . . . . . . . . . . . . . . . . . . . . . . 34 14 Network of roads of the Czech area of influence . . . . . . . . . . . . . . . . 35 15 Map of Belgian airports that have scheduled service on commercial airlines [4] and proposed location for Belgium (red dot) . . . . . . . . . . . . . . . . 36 16 Belgian population density map [23] . . . . . . . . . . . . . . . . . . . . . . 36 17 Network of roads of the Belgian area of influence . . . . . . . . . . . . . . . 37 18 Map of Irish airports that have scheduled service on commercial airlines [4] and proposed location for the Ireland (red dot) . . . . . . . . . . . . . . . . 38 19 Irish population density map [28] . . . . . . . . . . . . . . . . . . . . . . . . 39 20 Network of roads of the Irish area of influence . . . . . . . . . . . . . . . . . 40 21 Location of the regional airport . . . . . . . . . . . . . . . . . . . . . . . . . 42 22 Elevation profile for runway 1.......................... 42 23 Elevation profile for runway 2.......................... 42 24 Runway and time from Munich to the regional airport . . . . . . . . . . . . 43 25 Hourly distribution of aircraft movements at Airport of Munich during COVID-19 (busy day during 2020) ....................... 56 26 Hourly distribution of aircraft movements at the new airport without COVID- 19 (busy day during 2020)............................ 57 27 Hourly distribution of passengers at the new airport without COVID-19 (busy day during 2020).............................. 58 28 Forecast of flights in Europe for the next years [40] . . . . . . . . . . . . . . 62 29 Forecast of annual aircraft movements for the new airport . . . . . . . . . . 65 30 Forecast of annual passengers for the new airport . . . . . . . . . . . . . . . 66 31 Take-off runway length as a function of the take-off weight for the A321 [52] 68 32 Landing runway length as a function of the gross weight for the A321 [52] . 69 33 Wind rose of Munich [59] . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70 34 Flight possibility due to crosswind as a function of the wind direction . . . . 72 35 Runway configuration that are suitable for the new airport [46] . . . . . . . 73 36 Information to calculate the hourly capacity for one runway with VFR [46] . 74 37 Information to calculate the hourly capacity for one runway with IFR [46] . 75 38 Information to calculate the hourly capacity for two parallel runways with VFR [46] ..................................... 76 39 Information to calculate the hourly capacity for two parallel runways with IFR [46]...................................... 76 TFG Report Page 8 of 167
UPC-ESEIAAT LIST OF FIGURES The apron system will consist of a passenger terminal apron, a remote parking apron and an isolated aircraft apron. The concept of the terminal area will be a pier concept with double apron taxiways. Aircraft will be parked taxi-in and push out and there will be 14 type VII and 12 type V aircraft stands at the passenger terminal apron and 5aircraft stands at the remote parking apron. The capacity of the gates is 47 operations per hour at gates. Regarding the visual aids, the new airport will be provided with indicators and signalling devices, markings, lights, signs and markers. To finish, the obstacle limitation surfaces have been analysed together with the topography of the new airport’s location. It can be stated that there are no dangerous obstacles within these surfaces. Description of the landside The new airport will be an origin and destination terminal, considering that it focuses on departing and arriving passengers rather than on transfer passengers. Moreover, it will also be considered a low-cost terminal, since the need of reducing operating costs will be constantly present, seeing that it is a secondary airport and low-cost companies will operate there. It is of paramount importance to note that all the facilities have been designed to reach an optimum level of service. The flow of the passengers has been analysed. On the one hand, the departing passenger flow consists of the following steps: 1. Departures forecourt. 2. Departure hall: traditional check-in, self service kiosks and bag drop facilities. 3. Emigration control facilities. 4. Security screening facilities. 5. Departure lounge. 6. Boarding gates. On the other hand, the arriving passenger flow consists of the following steps: 1. Immigration control. 2. Baggage claim. 3. Customs control. 4. Arrivals hall. 5. Arrivals forecourt. The terminal building needs to segregate the the arrival flow and the departing flow, which has been made by separating the arrival flow from the departing flow in two floors. At the beginning of both floors, there is a free circulation space which is intended to connect both floors. Description of the reserved airport zone The area intended for the airport presented at the beginning of the project is by far larger than the area that occupies the infrastructure which has been explained until now. The remaining area is the reserved airport zone and is intended for future expansions of the airport when the demand increases and requires for more capacity. It must be noted that this expansion does not need to be made at once but should be gradually implemented to avoid large sums of capital investment. Additional airport facilities and infrastructures TFG Report Page 15 of 167
UPC-ESEIAAT LIST OF FIGURES The new airport will have additional airport facilities and infrastructures. For instance, the rescue and firefighting service which, considering that the aerodrome’s category is 7, it will require two vehicles. The rescue and firefighting service should arrive to any point of the operational runway in a response time not exceeding two minutes and to any point of the movement area in less than three minutes. Another additional infrastructure is the de-icing and anti-icing facilities, which will be remote for the new airport and it will have capacity for two aircraft. Last but not least, the control tower, which will be high enough to let the controllers see all the movement area. Environmental and social impact study On the one hand, the main environmental impacts are: the aircraft noise, the air quality, the greenhouse gases and the climate change, the water and soil pollution, the amount of waste, the effect on the flora and fauna and the energy consumption. On the other hand, the main social impacts are: the interaction between the airport and the landowners, the consequences of the environmental effects of an airport on the land owners and the necessity to protect heritage. For all these issues, solutions that suppose a common ground for both parties must be found. Business plan The design of the airport has an important impact on its capital expenditure and operational expenditure. The CapEx and OpEx should be minimised, while the revenues should be maximised. CapEx is minimised by minimising the size of the building and ensuring optimal spatial efficiency, whereas OpEx is minimised by the intelligent use of natural light and the optimisation of circulation spaces. Regarding the aeronautical revenues, at short term (2025), the forecasts for annual revenues are 400,370 and 320 million Euros, respectively, for each scenario; at medium term (2030), 550,470 and 400 million Euros, respectively; and at long term (2040), 750,700 and 650 million Euros, respectively. Implementation plan Once the project on paper has been finished, the implementation plan can begin. It will consists of four phases: •Phase 0: pre-construction considerations. It lasts for 5years or 60 months. •Phase 1: construction of the airside. It lasts for 3years or 36 months. •Phase 2: construction of the landside. It lasts for 5.5years or 42 months. •Phase 4: additional infrastructures and facilities. It lasts for 1.5years or 15 months. The total duration of the project is 9.5years or 114 months, which is less than the sum of the previously stated periods of time because the construction work can be done simultaneously. Figure 3 depict the Gantt chart of the project. Figure 3: Gantt chart of the implementation plan (zoom to better visualise) TFG Report Page 16 of 167
UPC-ESEIAAT LIST OF FIGURES Suggestions for the follow-up of the project Suggestions for the follow-up of the project include aspects of: •Improvements of the land accessibility for public transportation. •Improvements of the business and implementation plans. •Improvements of the level of design of the airport: airside and landside.. •Improvement of the techniques and methods used for traffic forecasts. •The use of simulation modelling so as to improve the overall design. •In the future, keep track over time of the environmental and social considerations. •New studies to perform that have not been done due to the scope of the project. For instance, topics such as: cargo terminal, pavement, parking facilities, systems, baggage handling system, among others. •Analysis of a new concept: touch-less passenger processing. TFG Report Page 17 of 167
UPC-ESEIAAT 1 INTRODUCTION 1 Introduction 1.1 Aim of the project The aim of this project is to propose a new regional airport in Europe that would be sustainable from the point of view of business and that would be technically viable. So as to do so, potential locations for the airport will be proposed. After debating which is the best one, a predesign of this airport will be carried out as well as a business and an implementation plans for the new infrastructure. Moreover, it is worth saying that the proposed regional airport aims to satisfy real necessities of the proposed location for the airport. 1.2 Scope of the project The scope for the present study is the following: •To take into account only the airports that have scheduled service on commercial airlines when comparing potential locations. •To propose several potential locations for the regional airport. •To choose among the potential locations the final decision by using airport-coherent comparative criteria. •To make a general characterisation of the regional airport. •To perform a traffic forecast. •To describe the airside. •To perform a wind analysis in order to establish the orientation of the runway. •To describe the landside. •To describe the reserved airport zone. •To describe the additional airport facilities. •To perform an economic viability analysis and business plan for the project. •To perform an implementation plan for the project. 1.3 General requirements of the project The requirements for the present study are the following: •The airport that will be designed must be a regional airport. •The airport that will be designed must be located in Europe. •The airport that will be designed must solve a real necessity for the region and its citizens. •The technical viability and business viability of the airport must be demonstrated. This will be done via a predesign of the airport and by performing a business plan and an implementation plan. •The airport must be designed strictly according to the regulations of IATA, for the landside, and of the OACI, for the airside. It will be assumed that the regional/national regulations are already fulfilled by fulfilling the aforementioned regulations. TFG Report Page 18 of 167
UPC-ESEIAAT 1 INTRODUCTION 1.4 Background and justification of the project While it is true that nowadays Europe is the continent with the highest number of airports, there are still zones that are not very well connected from the airport point of view. If a closer look is taken to Figure 4, which shows all the European airports with more than 1,000,000 annual passengers, it is clear that there are blank zones. For instance, the surrounding areas of Madrid and Paris as well as some zones in Germany do not have airports with more than 1,000,000 annual passengers. Figure 4: European airports with more than 1,000,000 annual passengers (2009) [1] Nevertheless, the number of airports with more than 1,000,000 annual passengers is not the only factor to take into account when it comes to deciding if building a new airport is suitable or not. Other factors that have to be taken into account are: •Gross domestic product, which is a clear indicator of the economic power necessary to build a new airport. •Growth of population, which is an indicator that a zone will need a new airport in the future. •Risk of traffic congestion in nearby airports, which can be solved by proposing a new airport which can absorb the exceeding traffic. Thus, this project intends to sweep Europe and analyse these factors among many others in order to find the best location in need of a new regional airport and develop it. This new regional airport will enhance the economical activity of its area of influence by promoting the creation of new infrastructures such as transportation means, which will greatly improve the communication of the region. All these factor will revalue the zone and the citizens around this airport will be able to enjoy all these benefits. TFG Report Page 19 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION 2 Selection and justification of the airport’s location The very first step of an airport design is, obviously, to find a location that is optimal, which means that there has to be a need that an airport can solve and a niche market from which the airport can profit so as to economically thrive. This section is devoted to find this type of location. Firstly, the requirements of the airport will be established. Next, after gathering information about the area of influence of the most appealing zones of Europe, five potential airport locations that fulfil the airport requirements will be proposed. Afterwards, by analysing the technical and socioeconomic factors, a comparison among the potential locations will be done. So as to do so, comparative criteria will be applied for all the potential airport locations. Finally, based on the comparative analysis done, the final location of the airport will be justified and defined. 2.1 Establishment of the airport’s requirements To begin with this project it is needed to establish the airport’s requirements in terms of its location. In general, an airport must be located in a place that offers the most secure and efficient environment for the aircraft, while minimising the costs of the construction project. Nevertheless, there are other factors that influence the location of an airport, such as the technical factors and the socioeconomic factors of the airport’s area of influence [2][3]. Additionally, it is important for the airport to have a need to fulfil, considering that there will be no demand if there is none. As a consequence, the airport would be pointless. The decision whether one factor applies or not to the project depends of its scope. If it does not apply, it could be either because it is obvious that it will be accomplished2or because there are not sufficient means to study them. Thus, those factors that do not apply will be assumed to be fulfilled. All the factors will be explained next and for those that apply for this project the minimum requirements will be determined. Furthermore, they will be studied either from a qualitative or from a quantitative point of view. 2.1.1 Technical factors The most important technical factors can be divided in two groups: aeronautic feasibility and environmental suitability. They will be presented below. Aeronautic feasibility •Climatologic studies. Meteorologic phenomena can strictly reduce the visibility of pilots and, as a consequence, the capacity of the airport and the safety of the operations. For instance, the characteristics of the winds is important when it comes to orientate the runways. These studies will not be performed, considering they are out of the scope, but the climate will be analysed from a qualitative point of view. For this project, a zone which has an adequate climate will be sought. Nevertheless, a wind analysis will be performed. •Earth studies. Before beginning with the construction of the airport, several studies of the portion of earth where it will be located must be performed3. These studies will not be performed, considering they are out of the scope. Nevertheless, for this project, simply the flattest possible floor will be sought. 2For instance, the availability of resources: if there is no availability of resources, the airport has no sense. 3For instance, cartographic, geotechnic, orographic, geologic, geomorphic and topographic studies. TFG Report Page 20 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION •Air accessibility. The aircraft must have adequate accessibility to the airport so as to safely perform their operations in its surroundings. Therefore, obstacles in the airport and in its environments must be studied and eliminated, if necessary. For this reason, the obstacle-free surfaces will be plotted on the map. By doing so, any potentially dangerous obstacle will be detected. Furthermore, the necessary take-off and landing procedures will be defines so as to allow a the operational safety. This factor is related to the previous one and will be taken into account. Thus, the flattest possible floor and a safe airspace will be sought by analysing the obstacle-free surfaces. •Presence of other airports in the surrounding area and compatibility with the available airspace. Airports must be sufficiently away from each other so as to avoid interference between their operations. Otherwise, the operations should be restricted and the capacity of the runways would decrease, which is a factor that should be maximised in order to also maximise the income of the airport. This factor will be taken into account. The minimum distance between the nearest airport should be 20 NM, which is roughly 37 km. This number is a simplification that has been accepted, considering that it depends on several factors that will not be studied. Environmental suitability •Ecologic impact. The construction of an airport will always have a direct impact in the environment of the zone, which is a factor that should be minimised. This factor will be taken into account but only from a qualitative point of view. The affectations of the construction of the airport should be minimum in terms of the environment. These affectations will be studied in the future. •Acoustic impact. The construction and operation of an airport will have an acoustic impact in the surroundings of this infrastructure. Thus, the objective is to minimise the acoustic impact. This can be achieved by using natural or artificial barriers or by locating the airport away from urban zones. This factor will be taken into account but only from a qualitative point of view. The acoustic impact of the airport for its surroundings must be minimum by trying to locate the airport at least 2km away from any city or village. •Availability of resources. The airport needs basic resources in order to correctly work. This factor will not be taken into account. It will be assumed that the location will be supplied with basic resources such as potable water, electricity and fuel. •Land accessibility. The vast majority of passengers arrive to an airport by car or by public transport. For this reason, access to land transportation must be guaranteed. This factor will be taken into account but only from a qualitative point of view. The zone where the airport will be located must be well communicated. •Proximity to the city. The proximity to the city or the demand generating sources have a direct effect on the amount of time that a passenger takes from door to door (door of his house to the gates of the airport), which should be the minimum possible. This factor is strictly related to the previous point and will be taken into account from a qualitative point of view. Thus, the solution is to find the best communicated zone. •Availability of land for a possible future expansion of the airport. Due to TFG Report Page 21 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION the vast extension of land that the construction of an airport requires, lands that offer the maximum possibilities of expansion at long term with the minimum financial costs are sought. This factor will be taken into account. The zone where the airport will be located must be prepared for a possible future expansion and be at least 4km ×2km. This dimensions are an initial estimation based on the preliminary traffic and airport concept expected to have. •Existing infrastructure plans. The area that surrounds the airport must be protected from any construction of infrastructure that could compromise the safety of the operations or the correct functionality of the airport. What is more, the existing infrastructure plans should help the airport’s future development by being compatible with it and its environment and by connecting the area of influence with the airport for all the transportation means. This factor will not be taken into account, seeing that it is out of the scope. It will be assumed that no buildings are planned to be constructed in the nearest zone of the airport. •Legally protected areas. Occasionally there are protected areas on which it is forbidden to construct any infrastructure. This factor will not be taken into account, seeing that it is out of the scope. It will be assumed that permission to construct on all the land is given. 2.1.2 Socioeconomic factors The most important socioeconomic factors will be presented below. •GDP (Gross Domestic Product). The GDP of the country is an indicator of its economic growth and its capacity of investing in new infrastructures such as airports. This is a factor that will be taken into account. The GDP of the country should be high enough so as to be able to invest in the construction of a new airport. •Net monthly average salary. The net monthly average salary of a country is a clear indicator of how many times a person can afford to travel per year. Thus, countries with the higher net monthly average salary possible will be sought. This is a factor that will be taken into account. The net monthly average salary of the people of a country must be high enough so as to allow the person to travel many times per year. •Economic activities: growth rate per sectors. The growth rate of each sector of the economy is a clear indicator of how well the country is economically speaking. Especially, the growth rate of the third sector of the economy is important, which includes all the tourism. This factor will be taken into account. Once the potential five locations are found, their economic activities will be compared so as to decide the optimum location for the airport. •Factors for the economic viability and business plan development. The following economic factors will be analysed more deeply in the future, when the economic viability analysis and business plan development will be done. –Expropriation of land: infrastructure, costs and periods. It is highly probable that when the final location of the airport is decided, the land will be owned by a private particular and it will have to be expropriated. The infrastructure, the TFG Report Page 22 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION cost of expropriation and the period of time that is taken to be done should be analysed. This factor will not be taken into account, as it is out of the scope of this project. – Capital Expenditure (CaPex), which is the capital investment intended to plan the airport; buy the necessary materials, land and equipment, and construct the infrastructure and facilities. A cost is considered as capital expenditures during the initial construction of the airport but also when expanding the already existing infrastructure. – Operational Expenditure (OpEx), which is an expenditure intended to run and maintain the airport during its lifetime. The operational expenditure can be divided in fixed costs and variables costs (which depend on the number of operations). –Revenues, which is the income that the airport receives from two main sources: aeronautical income, which depends of the traffic and the airport taxes, and non-aeronautical income, which depends of the commercial concessions. This factor and the previous two must be analysed to see whether it is a profitable investment or not. Therefore, they will be taken into account and studied more in depth during the business plan. –Investment in ground transportation. The airport needs to be well connected and thus new roads and public transportation infrastructure must be constructed. This factor will not be taken into account, as it is out of the scope of this project. •Population. The population of the area of influence is strictly related to the potential customers of the airport. This is a factor that will be taken into account. The population of the area of influence should be high enough so as to generate the necessary demand for an airport. •Unemployment rate. The unemployment rate is another indicator of the amount of customers the airport will have. The higher the unemployment rate, the less money people have and the less they will travel. This factor will be taken into account. The unemployment rate of the area of influence should be low so that the inhabitants have enough purchasing power to travel. 2.1.3 Final requirements To sum up, the requirements of the airport’s location are: •It must have a nice climate, which will demonstrated with climate data and a wind analysis. •Its floor must be the flattest possible. •The minimum distance between the nearest airport should be 20 NM, which is roughly 37 km. •It must minimise the acoustic impact by locating the airport far enough. •It must minimise the ecologic impact. •It must be well communicated with the surrounding cities. •It must be vast enough to have space for future expansions of the airport and be at least 4km ×2km. TFG Report Page 23 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION •The GDP of the country should be high enough so as to be able to invest in the construction of a new airport. •The net monthly average salary of the people of a country must be high enough so as to allow the person to travel many times per year. •The population of the area of influence should be high enough so as to generate the necessary demand for an airport. •The unemployment rate of the area of influence should be low so that the inhabitants have enough purchasing power to travel. 2.2 Proposal of potential locations for the regional airport The selection of the five airport’s locations will be mainly focused on population density maps, maps that plot all the airports of the country with scheduled service on commercial airlines and the technical and socioeconomic factors that apply. As mentioned in the Project Charter, a sweep of Europe will be done so as to find the best location for the regional airport of this project. Initially, all the countries will be analysed and will pass two different filters. 2.2.1 First filter: contrast of the population density map and the airport map For each country, the airports that have scheduled service on commercial airlines will be plotted on the map [4]. Additionally, a population density map of the corresponding country will be used. Next, both maps will be compared and potential locations for the airport will be sought. These potential locations refer to highly populated zones (more than 1,000 inhabitants per square kilometre) where no airports are found and that could benefit from the construction of one. Seeing that there are a lot of countries, the maps that are used for this comparison will be shown in the Attachments document of this project as well as some comments of the author regarding whether it is wise to build an airport in the corresponding country or not. In the Attachments document there is also a table with a great deal of information of all the European countries. Note that there are some countries which will not been analysed: •Andorra, Liechtenstein, Monaco, San Marino and the Vatican City. These micro-states have been excluded because they are extremely small and because they have airports with scheduled commercial service from other countries nearby. •Armenia, Azerbaijan, Georgia, Kazakhstan and Russia. These countries are located in the far east of Europe and it has been considered that they are too different from a typical European country. After the application of the first filter, the result is shown in Table 2. TFG Report Page 24 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION Figure 9: Map of Dutch airports that have scheduled service on commercial airline [4] and proposed location for the Netherlands (red dot) Figure 10: Dutch population density map [14] Aeronautic feasibility factors TFG Report Page 31 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION •Climate [15]. Throughout the year, temperatures oscillate (in average) from 0.2◦C to 22.6◦C and precipitations oscillate from 13 mm to 17 mm (monthly). There is an average of 25 snowy days per year and the average humidity is 82%. Temperatures are adequate and the precipitations are very low. The snowy days could compromise a bit the operations but they only happen during the 7% of the year and with the necessary infrastructures it would not be a problem at all. Humidity is a bit high. •Orographic aspects [16]. This factor comprises the flatness of the ground and the air transportation accessibility factors. Netherlands is popular for being the flattest country in Europe and third in the world, so the orographic aspects will not be a problem when building an airport. Nevertheless, Google Earth Pro has been used and it has been seen that there is plenty of flat zones where an airport could be built. Furthermore, no mountainous zones are spotted in the area of influence. •Presence of other airports. There are no airports in the surroundings of the area of influence. The closest one is 90 km away, so there would be no operational problems if the airport were to be built here. Environmental suitability factors •Communication and connectivity of the airport [17]. This factor comprises the land transportation accessibility and the proximity to the city factors. Taking into account that the area of influence is located among three medium-sized cities which are considerably apart from each other, public transport is not very developed and it would be necessary to build new infrastructure. There are some train routes but they are not very well connected. In terms of private transport, as seen in Figure 11, it is a well-connected region with a great deal of roads that connect all three cities. Figure 11: Network of roads of the Dutch area of influence •Availability of ground for future expansions. Google Earth Pro has demonstrated that there are several locations in the area of influence of the required dimensions to build a regional airport with the possibility of future expansions. Socioeconomic factors TFG Report Page 32 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION •Economic level [17]. This zone is mainly devoted to the tertiary sector of economy (shopping centres and markets, festivals, a bit of tourism, etc.) although it has a few factories like the brewery of Grolsch beer and the headquarters of the tyre manufacturer Apollo Vredestein B.V.. Regarding the numbers, the net monthly average salary is 2,152 eand Netherlands’s GDP is 966,742 Me. In terms of the unemployment rate [15], it is 3.4%. •Population [18]. The area of influence would be the provinces of Gelderland and Overijssel, whose population is 1,999,135 and 1,113,529, respectively, with a total of 3,112,664 inhabitants. •Yearly flights indicator. The total yearly flights for the area of influence is 1,685,145,391. See the Attachments document for the calculations of this number. 2.3.3 Czechia Based on the map with all the airports that have scheduled service on commercial airlines (Figure 12) and on the population density map (Figure 13), the potential location suggested for Czechia is České Budějovice, which is also shown in Figure 12 (red dot). Although the surrounding zone is not so populated, this city has over 1,000 inhabitants per square kilometre and it could be worth analysing the possibility of building and airport here. Figure 12: Map of Czech airports that have scheduled service on commercial airlines [4] and proposed location for the Czechia (red dot) TFG Report Page 33 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION Figure 13: Czech population density map [19] Aeronautic feasibility factors •Climate [20]. Throughout the year, temperatures oscillate (in average) from −5.1◦C to 24.0◦C and precipitations oscillate from 42 mm to 98 mm (monthly). Temperatures are adequate while precipitations are acceptable. •Orographic aspects. This factor comprises the flatness of the ground and the air transportation accessibility. By using Google Earth Pro, it has been seen that there are a few flat zones around the area of influence that could be used to build and airport. Regarding the mountainous zones, there are no dangerous orographic irregularities. •Presence of other airports. The closest airport is the Airport of Praga, which is 130 km away. It is obvious that if the airport were to be built in this area of influence, there would be no problem as regards to the operations. Environmental suitability factors •Communication and connectivity of the airport [20]. This factor comprises the land transportation accessibility and the proximity to the city factors. Regarding the public transport, there is a network of train routes and busses that connect nearby cities. In terms of private transport, as seen in Figure 14, it is acceptably well-connected, considering that there are only a few highways and roads departing from České Budějovice. TFG Report Page 34 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION Figure 14: Network of roads of the Czech area of influence •Availability of ground for future expansions. Google Earth Pro has shown that there are a few locations in the area of influence of the required dimensions to build a regional airport with the possibility of future expansions. Socioeconomic factors •Economic level [21]. This region is focused on the industry (31%), the trade (13%) and the construction (10%) sectors. The tourism sector is becoming more and more strong. The industry sector is mainly formed by food and drink processing industries, automotive industry, production of machinery and appliances and textile and clothing industries. Jihočeský also holds the Czech Academy of Sciences, which provides a good foundation for the development of science. Moreover, the Bohemian Region produces the 11% of the national agricultural production, which focuses on plant production, animal husbandry and fishpond cultivation. Regarding the numbers, the net monthly average salary is 959 eand Czechia’s GDP is 395,868 Me. The unemployment rate [22] of Czechia is 2.4%, which is the lowest of the European Union. •Population [22]. The region of České Budějovice is Jihočeský, although the area of influence will also be the regions of Vysočina, Středočeský and Plzeňský. The population of the area of influence will be formed by all the population of Jihočeský and of half the population of the other regions. Respectively, the populations are 628,336,505,565,1,289,211 and 570,401, therefore the population of the area of influence will be 1,810,925 inhabitants. •Yearly flights indicator. The total yearly flights for the area of influence is 436,899,893. See the Attachments document for the calculations of this number. TFG Report Page 35 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION 2.3.4 Belgium Based on the map with all the airports that have scheduled service on commercial airlines (Figure 15) and on the population density map (Figure 16), the potential location suggested for Belgium is between Ghent and Kortrijk. The proposed location for the airport is also shown in Figure 15 (red dot). As seen in Figure 15, between Ghent and Kortrijk there is no airport although being two relatively highly populated cities, both with more than 1,000 inhabitants per square kilometre. Figure 15: Map of Belgian airports that have scheduled service on commercial airlines [4] and proposed location for Belgium (red dot) Figure 16: Belgian population density map [23] TFG Report Page 36 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION Aeronautic feasibility factors •Climate [24][25]. Throughout the year, temperatures oscillate (in average) from 0.5◦C to 23.1◦C and precipitations oscillate from 50.5mm to 81.9mm (monthly). There is an average of 136 rainy days per year. Temperatures are adequate but the precipitations are bit high. •Orographic aspects. This factor comprises the flatness of the ground and the air transportation accessibility factors. By using Google Earth, it has been seen that, as happens with the Netherlands, the zones around the area of influence are extremely flat and they could be used to build and airport. As to the mountainous zones, there are none. •Presence of other airports. There is no presence of other airports in the surroundings of the area of influence, taking into account that the closest airport is 50 km away. Consequently, if the airport were to be built here, there would be no problems regarding the operations. Environmental suitability factors •Communication and connectivity of the airport. This factor comprises the land transportation accessibility and the proximity to the city factors. This area of influence is extremely connected in terms of public transport. Both cities and the villages between them are connected with railways, trams and busses. Furthermore, there are several highways and roads that connect both cities and other towns. As for the private transportation, Figure 17 show the network of roads and highways of the area of influence. Figure 17: Network of roads of the Belgian area of influence •Availability of ground for future expansions. Google Earth Pro shows that it is flat zone with a lot of ground of the necessary dimensions to build a generic regional airport with the possibility of future expansions. Socioeconomic factors TFG Report Page 37 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION •Economic level[26][25]. This zone is mainly devoted to the textile industry and it has the port of Ghent. Regarding the numbers, the net monthly average salary is 2,170 eand Belgium’s GDP is 550,664 Me. As for the unemployment rate of Belgium, it is 8.5% [27]. •Population [27]. The area of influence would be the provinces of West Flanders, East Flanders and Hainaut, whose population is 1,195,796,1,515,064 and 1,344,241, respectively, with a total of 4,055,101 inhabitants. •Yearly flights indicator. The total yearly flights for the area of influence is 2,213,728,093. See the Attachments document for the calculations of this number. 2.3.5 Ireland Based on the map with all the airports that have scheduled service on commercial airlines (Figure 18) and on the population density map (Figure 19), the potential location suggested for Ireland is between Waterford and Wexford. This zone is shown in Figure 18 (red dot). As seen in Figure 18, between Cork and Dublin there is no airport although being a relatively highly populated zone for Ireland, with between 100 and 1,000 inhabitants per square kilometre. Figure 18: Map of Irish airports that have scheduled service on commercial airlines [4] and proposed location for the Ireland (red dot) TFG Report Page 38 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION Figure 19: Irish population density map [28] Aeronautic feasibility factors •Climate [29]. Troughout the year, temperatures oscillate (in average) from 2◦C to 20 ◦C and precipitations oscillate from 49 mm to 131 mm (monthly). There is an average of 151 rainy days per year. In general, visibility is very good due to the proximity of industry to the coast, considering that it disperses any smog. Mist and fog often occur but they do not last very long. Temperatures are adequate but the precipitations are bit high. The rainy days could compromise a bit the operations, while the mist and fog do not help at all. •Orographic aspects. This factor comprises the flatness of the ground and the air transportation accessibility factors. By using Google Earth, it has been seen that there are some flat ground around the area of influence that could be used to build and airport. As for the mountainous zones, there are some minor irregularities that should be avoided. •Presence of other airports. The closest airport is 100 km away, so it can be considered that the operations would not be affected if the airport were to be constructed in this area of influence. Environmental suitability factors •Communication and connectivity of the airport. This factor comprises the land transportation accessibility and the proximity to the city factors. This area of influence is connected by public transport such as railways and busses. Furthermore, the area of influence has a network of a few highways and roads that connect the cities of Waterford and Wexford, which are shown in Figure 20. TFG Report Page 39 of 167
UPC-ESEIAAT 2 SELECTION AND JUSTIFICATION OF THE AIRPORT’S LOCATION Figure 20: Network of roads of the Irish area of influence •Availability of ground for future expansions. By using Google Earth Pro, it can be seen that there are a few patches ground of the required dimensions to build a regional airport with the possibility of future expansions. Socioeconomic factors •Economic level [30][31][32]. This area of influence is devoted to numerous sectors of the economy: the primary sector consists of the agricultural industry, the secondary sector consists of the activities of Waterford’s and Wexford’s ports and the manufacturing of Waterford Crystals, and the tertiary sector consists of shops and markets. Furthermore, famous multinational companies such as Dell, Amazon, Motorola, Coca-Cola, Apple Computer, Siemens, Sony, Blizzard Entertainment, among others, are established in the area. Regarding the numbers, the net monthly average salary is 2,911 eand Irelands’s GDP is 381,720 Me. As for the unemployment rate [33] of Ireland, it is 8.6%. •Population [34][32]. The area of influence would be half the provinces of Leinster and Munster, whose population is 2,630,720 and 1,280,020, respectively. This is because the potential locations is found between the two provinces, which already have their airports. Thus, the population of the area of influence is 1,955,370 inhabitants. •Yearly flights indicator. The total yearly flights for the area of influence is 1,926,547,401. See the Attachments document for the calculations of this number. 2.3.6 Comparative table for the potential locations Table 4 shows all the marks given for each factor for each country analysed. This marks have been given based on the information exposed above. TFG Report Page 40 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST 4 Traffic forecast An airport is only viable if there are potential customers that are willing to use it. Thus, the next step in order to design the regional airport is to make a traffic forecast. The author of this thesis made contact with the authorities of the International Airport of Munich and they provided part of the necessary information to make the traffic forecast. With this data and together with the information of the airport’s website [35] a study of the peak scenarios has been done and a forecast of the annual traffic expected has been made for the regional airport proposed. 4.1 Study of the peak scenarios of the regional airport In this subsection the peak scenarios will be studied, which are the limiting factor when it comes to sizing the airport. So as to do so, daily information about the Airport of Munich was needed and extracted from [35]. From the 11th of November to the 17th of November of 2020, all the flights have been analysed. More precisely, for both departures and arrivals, the following parameters have been considered: airline, origin and destination city, time of departure and arrival and brand and model of the aircraft used. If the reader desires to see the information tables, see the Attachments document. Nevertheless, it is obvious that not all the information of these tables are relevant for the purpose of this project and so two filters have been applied in order to obtain the most important data. 4.1.1 First filter: Star Alliance remains in the Airport of Munich After analysing the information, it has been observed that about 61% of the scheduled flights belong to Lufthansa, which suggests that the major client of this airport is this airline11. Lufthansa is partner of Star Alliance and, considering that the partners of a same airline alliance use to make transfer flights between them, the first filter applied consists in subtracting all the airlines that belong to Star Alliance and have scheduled flights in the Airport of Munich: •AEGEAN. •Air Dolomiti. •Austrian Airlines. •Croatian Airlines. •EgyptAir. •Eurowings. •Lufthansa. •SAS. •SunExpress. •TAP Air Portugal. •Turkish Airlines. •United. It is worth noting that Air Dolomiti and Eurowings are low-cost subsidiaries of Lufthansa and SunExpress is a low-cost subsidiary that belongs to Lufthansa and Turkish Airlines. This suggests that maybe it could be worth absorbing this airlines to the new regional airport. Nonetheless, after studying the airlines that operate in several German cities which have both an international airport and a regional airport, it has been observed that this airlines remain together with their parent company at their international airport. For this reason, it has been finally decided that all the airlines belonging to Star Alliance will be excluded from this project. If the reader desires to see the information tables after applying the first filter, see the Attachments document. 11The second one is Eurowings with 5.76%, although it is a subsidiary of Lufthansa, and the third one is KLM with 3.38%. TFG Report Page 47 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST 4.1.2 Second filter: wide-bodied aircraft remain in the airport of Munich At this point, it would be wise to analyse the aircraft that the remaining airlines use. It is well known that a regional flight is usually flown with narrow-body aircraft. Thus, the regional airport of this project will be designed to serve this type of aircraft. After analysing again the information tables, it has been observed that Qatar Airways, Emirates and Etihad Airways use Airbus A350-900, Boeing 777-300 ER and Boeing 787-9 Dreamliner, respectively, which are all wide-body aircraft. For this reason, these three airlines will be excluded from the regional airport that is being planned. 4.1.3 Filtered results: absorbed traffic of the new airport The following tables depict a great deal of information of the remaining air traffic that will be absorbed. Arrivals Tables 6, 7 and 8 show relevant information about the arrivals after applying the filters. Table 6: Relevant information about the airlines from arrivals after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Airline Flights Flights Flights Flights Flights Flights Flights Flights Percentage Aer Lingus 0 0 0 0 1 0 0 1 1.12 Air Europa 0 1 1 0 1 1 0 4 4.49 Air France 1 0 1 0 1 1 0 4 4.49 Air Malta 1 0 1 1 1 1 0 5 5.62 Air Mediterranean 1 0 0 1 1 0 0 3 3.37 airBaltic 0 1 1 1 1 1 0 5 5.62 Alitalia 1 1 1 1 1 0 1 6 6.74 Belavia 0 0 1 0 1 0 0 2 2.25 British Airways 1 0 1 0 1 0 0 3 3.37 Condor 0 0 0 1 1 0 0 2 2.25 Finnair 0 1 0 0 1 0 0 2 2.25 Holiday Europe 1 0 0 0 0 2 0 3 3.37 Iberia 1 0 1 0 0 1 1 4 4.49 KLM 3 2 3 3 3 2 2 18 20.22 LOT 1 1 1 0 1 1 0 5 5.62 Lübeck Air / Air Alsie 0 0 1 0 1 1 0 3 3.37 Luxair 0 0 1 0 1 1 0 3 3.37 Pegasus Airlines 1 0 1 0 1 0 0 3 3.37 Tarom 0 0 1 0 0 0 0 1 1.12 TUIfly 0 0 2 3 0 1 1 7 7.87 Tunisair 0 0 1 0 0 0 0 1 1.12 Ukraine Intl. Airlines 0 0 1 0 0 1 0 2 2.25 UR Airlines 0 1 0 0 0 0 0 1 1.12 Vueling 0 0 1 0 0 0 0 1 1.12 Total 12 8 21 11 18 14 5 89 100 TFG Report Page 48 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Table 7: Relevant information about the aircraft from arrivals after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Brand and model aircraft aircraft aircraft aircraft aircraft aircraft aircraft aircraft Percentage A20N 1 0 1 0 1 1 0 4 4.49 A318 0 0 1 0 0 0 0 1 1.12 A319 2 0 2 0 0 1 1 6 6.74 A320 0 0 2 2 4 0 0 8 8.99 A321 2 0 0 1 1 2 0 6 6.74 AT76 0 0 1 0 1 1 0 3 3.37 B734 0 1 0 0 0 0 0 1 1.12 B737 0 0 0 0 0 2 1 3 3.37 B738 1 1 4 3 1 1 1 12 13.48 BCS3 0 1 1 1 1 1 0 5 5.62 DH8D 0 0 1 0 1 1 0 3 3.37 E170 1 0 1 0 1 2 0 5 5.62 E190 0 1 2 1 2 1 1 8 8.99 E195 0 0 1 0 0 1 0 2 2.25 E75L 3 2 2 2 3 0 0 12 13.48 E75S 2 2 2 1 2 0 1 10 11.24 Total 12 8 21 11 18 14 5 89 100 Table 8: Relevant information about the hours of arrivals after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Hour Flights Flights Flights Flights Flights Flights Flights Flights Mean 7:00 0 0 0 0 0 1 0 1 0.14 8:00 0 1 1 1 0 1 0 4 0.57 9:00 0 1 0 0 0 0 0 1 0.14 10:00 2 2 3 1 3 1 1 13 1.86 11:00 2 0 2 1 2 2 0 9 1.29 12:00 0 0 1 0 1 0 0 2 0.29 13:00 0 0 0 1 0 0 0 1 0.14 14:00 0 0 1 0 0 0 0 1 0.14 15:00 0 0 0 0 1 0 0 1 0.14 16:00 2 0 4 1 3 2 1 13 1.86 17:00 1 3 3 1 3 5 2 18 2.57 18:00 2 0 2 2 1 1 0 8 1.14 19:00 1 0 2 2 2 0 1 8 1.14 20:00 1 0 1 0 0 0 0 2 0.29 21:00 1 1 1 1 1 1 0 6 0.86 22:00 0 0 0 0 0 0 0 0 0.00 23:00 0 0 0 0 1 0 0 1 0.14 Total 12 8 21 11 18 14 5 89 12.71 Departures Tables 9, 10 and 11 show relevant information about the departures after applying the filters. TFG Report Page 49 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Table 9: Relevant information about the airlines from departures after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Airline Flights Flights Flights Flights Flights Flights Flights Flights Percentage Aer Lingus 0 0 0 0 1 0 0 1 1.11 Air Europa 0 1 1 0 1 1 0 4 4.44 Air France 1 0 1 0 1 1 0 4 4.44 Air Malta 1 0 1 2 1 1 0 6 6.67 Air Mediterranean 1 0 0 1 0 0 0 2 2.22 airBaltic 0 1 1 1 1 1 0 5 5.56 Alitalia 1 1 1 1 1 0 1 6 6.67 Belavia 0 0 1 0 1 0 0 2 2.22 British Airways 0 1 0 1 0 1 0 3 3.33 Condor 0 1 0 1 1 0 0 3 3.33 Finnair 0 1 0 0 1 0 0 2 2.22 Holiday Europe 1 0 0 0 0 2 0 3 3.33 Iberia 1 0 1 0 0 1 1 4 4.44 KLM 3 2 3 3 3 2 3 19 21.11 LOT 1 1 1 0 1 1 0 5 5.56 Lübeck Air / Air Alsie 0 0 1 0 1 1 0 3 3.33 Luxair 0 0 1 0 1 1 0 3 3.33 Pegasus Airlines 1 0 1 0 1 0 0 3 3.33 Tarom 0 0 1 0 0 0 0 1 1.11 TUIfly 0 0 2 3 0 1 1 7 7.78 Tunisair 0 0 0 0 0 0 0 0 0.00 Ukraine Intl. Airlines 0 0 1 0 0 1 0 2 2.22 UR Airlines 0 1 0 0 0 0 0 1 1.11 Vueling 0 0 1 0 0 0 0 1 1.11 Total 11 10 19 13 16 15 6 90 100 Table 10: Relevant information about the aircraft from departures after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Brand and model aircraft aircraft aircraft aircraft aircraft aircraft aircraft aircraft Percentage A20N 1 0 1 0 0 2 0 4 4.44 A318 0 0 1 0 0 0 0 1 1.11 A319 1 1 1 1 0 1 1 6 6.67 A320 0 1 1 3 4 0 0 9 10.00 A321 2 0 0 1 0 2 0 5 5.56 AT76 0 0 1 0 1 1 0 3 3.33 B734 0 1 0 0 0 0 0 1 1.11 B737 0 0 0 0 0 1 2 3 3.33 B738 1 1 4 3 1 1 1 12 13.33 BCS3 0 1 1 1 1 1 0 5 5.56 DH8D 0 0 1 0 1 1 0 3 3.33 E170 1 0 1 0 1 2 0 5 5.56 E190 1 1 1 2 2 1 1 9 10.00 E195 0 0 1 0 0 1 0 2 2.22 E75L 2 2 3 1 3 1 0 12 13.33 E75S 2 2 2 1 2 0 1 10 11.11 Total 11 10 19 13 16 15 6 90 100 TFG Report Page 50 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Table 11: Relevant information about the hours of departures after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Hour Flights Flights Flights Flights Flights Flights Flights Flights Mean 7:00 1 2 1 2 1 4 2 13 1.86 8:00 0 0 0 1 0 1 0 2 0.29 9:00 0 1 2 2 0 1 0 6 0.86 10:00 0 1 0 0 0 0 0 1 0.14 11:00 2 1 1 1 3 0 1 9 1.29 12:00 2 1 2 2 3 3 0 13 1.86 13:00 0 0 1 0 1 0 0 2 0.29 14:00 0 0 1 1 0 1 0 3 0.43 15:00 0 1 1 1 0 0 0 3 0.43 16:00 0 0 0 0 1 0 0 1 0.14 17:00 1 0 2 2 1 2 1 9 1.29 18:00 1 2 2 0 1 0 1 7 1.00 19:00 3 1 4 0 3 2 1 14 2.00 20:00 0 0 2 0 2 1 0 5 0.71 21:00 1 0 0 1 0 0 0 2 0.29 22:00 0 0 0 0 0 0 0 0 0.00 23:00 0 0 0 0 0 0 0 0 0.00 Total 11 10 19 13 16 15 6 90 12.86 Mixture Tables 12, 13 and 14 show relevant information about the mixture of arrivals and departures after applying the filters. Table 12: Relevant information about the airlines from the mixture of arrivals and departures after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Airline Flights Flights Flights Flights Flights Flights Flights Flights Percentage Aer Lingus 0 0 0 0 2 0 0 2 1.12 Air Europa 0 2 2 0 2 2 0 8 4.47 Air France 2 0 2 0 2 2 0 8 4.47 Air Malta 2 0 2 3 2 2 0 11 6.15 Air Mediterranean 2 0 0 2 1 0 0 5 2.79 airBaltic 0 2 2 2 2 2 0 10 5.59 Alitalia 2 2 2 2 2 0 2 12 6.70 Belavia 0 0 2 0 2 0 0 4 2.23 British Airways 1 1 1 1 1 1 0 6 3.35 Condor 0 1 0 2 2 0 0 5 2.79 Finnair 0 2 0 0 2 0 0 4 2.23 Holiday Europe 2 0 0 0 0 4 0 6 3.35 Iberia 2 0 2 0 0 2 2 8 4.47 KLM 6 4 6 6 6 4 5 37 20.67 LOT 2 2 2 0 2 2 0 10 5.59 Lübeck Air / Air Alsie 0 0 2 0 2 2 0 6 3.35 Luxair 0 0 2 0 2 2 0 6 3.35 Pegasus Airlines 2 0 2 0 2 0 0 6 3.35 Tarom 0 0 2 0 0 0 0 2 1.12 TUIfly 0 0 4 6 0 2 2 14 7.82 Tunisair 0 0 1 0 0 0 0 1 0.56 Ukraine Intl. Airlines 0 0 2 0 0 2 0 4 2.23 UR Airlines 0 2 0 0 0 0 0 2 1.12 Vueling 0 0 2 0 0 0 0 2 1.12 Total 23 18 40 24 34 29 11 179 100 TFG Report Page 51 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Table 13: Relevant information about the aircraft from the mixture of arrivals and departures after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Brand and model aircraft aircraft aircraft aircraft aircraft aircraft aircraft aircraft Percentage A20N 2 0 2 0 1 3 0 8 4.47 A318 0 0 2 0 0 0 0 2 1.12 A319 3 1 3 1 0 2 2 12 6.70 A320 0 1 3 5 8 0 0 17 9.50 A321 4 0 0 2 1 4 0 11 6.15 AT76 0 0 2 0 2 2 0 6 3.35 B734 0 2 0 0 0 0 0 2 1.12 B737 0 0 0 0 0 3 3 6 3.35 B738 2 2 8 6 2 2 2 24 13.41 BCS3 0 2 2 2 2 2 0 10 5.59 DH8D 0 0 2 0 2 2 0 6 3.35 E170 2 0 2 0 2 4 0 10 5.59 E190 1 2 3 3 4 2 2 17 9.50 E195 0 0 2 0 0 2 0 4 2.23 E75L 5 4 5 3 6 1 0 24 13.41 E75S 4 4 4 2 4 0 2 20 11.17 Total 23 18 40 24 34 29 11 179 100 Table 14: Relevant information about the hours of the mixture of arrivals and departures after applying the filters 11/11 12/11 13/11 14/11 15/11 16/11 17/11 Total week Hour Flights Flights Flights Flights Flights Flights Flights Flights Mean 7:00 1 2 1 2 1 5 2 14 7.00 8:00 0 1 1 2 0 2 0 6 3.00 9:00 0 2 2 2 0 1 0 7 3.50 10:00 2 3 3 1 3 1 1 14 7.00 11:00 4 1 3 2 5 2 1 18 9.00 12:00 2 1 3 2 4 3 0 15 7.50 13:00 0 0 1 1 1 0 0 3 1.50 14:00 0 0 2 1 0 1 0 4 2.00 15:00 0 1 1 1 1 0 0 4 2.00 16:00 2 0 4 1 4 2 1 14 7.00 17:00 2 3 5 3 4 7 3 27 13.50 18:00 3 2 4 2 2 1 1 15 7.50 19:00 4 1 6 2 5 2 2 22 11.00 20:00 1 0 3 0 2 1 0 7 3.50 21:00 2 1 1 2 1 1 0 8 4.00 22:00 0 0 0 0 0 0 0 0 0.00 23:00 0 0 0 0 1 0 0 1 0.50 Total 23 18 40 24 34 29 11 179 89.5 Hourly distributions By analysing Tables 6, 7, 8, 9, 10, 11, 12, 13 and 14, the hourly distribution for departures, arrivals and the mixture will be done, for both aircraft movements and passengers. Firstly, it is necessary to choose the busy day12. The busy day for the studied week will be the 13th of November. For this day, the number of departures, arrivals and their mixture for each hour is shown in Table 15. 12The busy day is defined as the second peak day of the average week of the peak month. The peak month of the Airport of Munich is distributed between July, August and September for the past 11 years. Nonetheless, this project started on October and thus it has been impossible to gather information from those months. As a consequence, instead of selecting the second peak day of the average week, the first day will be selected. TFG Report Page 52 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Table 15: Number of flights per hour for arrivals, departures and their mixture Hour Departures Arrivals Mixture 7:00 1 0 1 8:00 0 1 1 9:00 2 0 2 10:00 0 3 3 11:00 1 2 3 12:00 2 1 3 13:00 1 0 1 14:00 1 1 2 15:00 1 0 1 16:00 0 4 4 17:00 2 3 5 18:00 2 2 4 19:00 4 2 6 20:00 2 1 3 21:00 0 1 1 Total 19 21 40 From Table 15 there are several issues to point out. Firstly, this distribution has been obtained during the COVID-19 pandemic, which has greatly struck the aviation sector and dramatically reduced the flights. Thus, these numbers are not realistic and will have to be transformed to non-COVID-19 numbers. Secondly, there are hours in which the number of departures or arrivals is 0. Whatever manipulations were made to transform the number to a more realistic scenario, the number 0will remain as such. For this reason, it has been decided that wherever there is a 0, it will we substituted for half of the value next to it. For instance, if a 0is found for departures, half of the value of the arrivals will be considered and viceversa. Having made these comments, the procedure13 to transform these number to a more realistic scenario is the following: 1. Firstly, the number of aircraft movements for November 2019 and 2020 [10] has been divided in order to obtain their ratio. Aircraft movements November 2019 Aircraft movements November 2020 =31,673 4,376 = 7.24 This means that in November 2019 there where 7.24 times more aircraft movements than in November 2020. 2. Secondly, the number of aircraft movements of the mixture of departures and arrivals has been multiplied by the previously calculated ratio. 3. Next, it has to be taken into account that by multiplying the numbers by a factor, the peaks and valleys of the hourly distribution are maximised and thus the original hourly distribution is distorted. For this reason, a correction factor will be applied following the criteria of Table 16: 13The author cannot stress and emphasise enough the difficulty of gathering information during this pandemic and converting it to a non-pandemic scenario. Therefore, it has to be understood that this calculations are an approximation of a real scenario. TFG Report Page 53 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Table 16: Correction factor as a function of the number of aircraft movements in the mixture of arrivals and departures Number of aircraft movements Correction factor 1 1.3 2 1.2 3 1.1 4 0.9 5 0.8 6 0.7 Thus, this correction factors will be multiplied by the mixture column as a function of how many aircraft movement there were initially, before multiplying by the ratio calculated in point 1.. 4. Then, all the aircraft movements have been added to obtain the number of aircraft movements of a busy day in a no-COVID-19 scenario. 5. Afterwards, as previously mentioned, wherever there is a 0in Table 15, it will we substituted for half of the value next to it. 6. Then, the proportion of departures and mixture and arrivals and mixtures will be calculated and then multiplied by the number of aircraft movements calculated in 4.. 7. To finish up, the numbers are rounded off, considering that for both aircraft movements and passengers, fractions of a unit have no sense. The result of the conversion is shown in Table 17. Table 17: Hourly distribution of aircraft movements in a no-COVID-19 scenario Hour Departures Arrivals Mixture 7:00 6 3 9 8:00 3 6 9 9:00 12 6 17 10:00 8 16 24 11:00 8 16 24 12:00 16 8 24 13:00 6 3 9 14:00 9 9 17 15:00 6 3 9 16:00 9 17 26 17:00 12 17 29 18:00 13 13 26 19:00 20 10 30 20:00 16 8 24 21:00 3 6 9 Total 147 142 289 Percentage of total 50.79 49.21 100.00 The next step is to calculate the hourly distribution of passengers for the same no-COVID- 19 scenario, which can be easily done by manipulating Table 17. For this part, two param- TFG Report Page 54 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST eters will be necessary, the load factor and the seating capacity. The first one is obtained from [36], whereas the seating capacity is obtained from doing the weighted arithmetic mean of the seating capacity of all the aircraft that will operate in the new airport based on their frequency of operation. The latter information can be found on Table 26. Once it is known that the load factor is LF = 0.775 and that the average seating capacity is SC = 129, it is only necessary to multiply all the numbers of Table 17 by LF and SC. The result is shown in Table 18 Table 18: Hourly distribution of passengers in a no-COVID-19 scenario Hour Departures Arrivals Mixture 7:00 624 312 936 8:00 312 624 936 9:00 1,152 576 1,728 10:00 792 1,584 2,376 11:00 792 1,584 2,376 12:00 1,584 792 2,376 13:00 624 312 936 14:00 864 864 1,728 15:00 624 312 936 16:00 864 1,728 2,592 17:00 1,152 1,728 2,880 18:00 1,296 1,296 2,592 19:00 2,016 1,008 3,024 20:00 1,584 792 2,376 21:00 312 624 936 Total 14,591 14,135 28,726 Percentage of total 50.79 49.21 100.00 Figures 25, 26 and 27 show the hourly distributions of aircraft movements at Airport of Munich during COVID-19, of aircraft movements at the new airport without COVID-19 and of passengers at the new airport without COVID-19, respectively. TFG Report Page 55 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Hourly distribution of aircraft movements for departures at Munich 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 Hour 0 1 2 3 4 5 6 7 Number of aircraft movements Hourly distribution of aircraft movements for arrivals at Munich 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 Hour 0 1 2 3 4 5 6 7 Number of aircraft movements Hourly distribution of aircraft movements for the mixture at Munich 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 Hour 0 1 2 3 4 5 6 7 Number of aircraft movements Figure 25: Hourly distribution of aircraft movements at Airport of Munich during COVID-19 (busy day during 2020) Figure 25 shows a scenario of the aircraft movements which is not plausible when COVID- 19 will end, considering that there are hours when there are no departures or arrivals. Furthermore, the number of operations per hour are very low. For this reason, it has been necessary to extrapolate the present case to a non-COVID-19 scenario. TFG Report Page 56 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Table 23: Annual growth rate of the flights for the three above-mentioned scenarios from 2020 to 2024 [42] Year Scenario 1 Scenario 2 Scenario 3 2020 -57.0% -58.0% -58.0% 2021 66.0% 17.0% 14.0% 2022 21.0% 42.0% 17.0% 2023 8.1% 14.0% 15.0% 2024 6.4% 12.0% 12.0% With the whole information that has been gathered, the annual forecasts for aircraft movements and passengers for the new airport and for the three scenarios has been made and they can be observed in Table 24, which has been made by following these steps: 1. First, it has been necessary to calculate the number of passengers and aircraft movements with which the new airport would begin its operations in 2020. Previously, it has been stated that in a non-COVID-19 scenario, the airport would have 10,484,867 passengers and 105,409 aircraft movements, approximately. Thus, these are the number with which the COVID-19 recovery stage will end. Then, to calculate the initial values, the percentages of Table 23 have been used. 2020 values ·1.66 ·1.21 ·1.081 ·1.064 = 2024 values 2024 values are the number when the COVID-19 recovery stage will end. Thus, by simply isolating the 2020 values, the initial values are obtained. 2. All three scenarios have began with the same numbers and then the corresponding percentage from Table 23 has been applied until 2024. For scenarios 2and 3, from 2025 to 2026 and from 2025 to 2029, respectively, a linear interpolation has been calculated, considering that the final value is known: 10,484,867 passengers and 105,409 aircraft movements. 3. For the following stages, the corresponding CAGR from Table 22 have been used until completing the three stages and arriving to 2040. TFG Report Page 63 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST Table 24: Annual forecasts for aircraft movements and passengers for the new airport for the three scenarios Scenario 1 Scenario 2 Scenario 3 Year Passengers Aircraft movements Passengers Aircraft movements Passengers Aircraft movements 2020 4,538,394 45,626 4,538,394 45,626 4,538,394 45,626 2021 7,533,733 75,740 5,309,920 53,383 5,173,769 52,014 2022 9,115,817 91,645 7,540,087 75,804 6,053,309 60,857 2023 9,854,199 99,069 8,595,699 86,416 6,961,306 69,985 2024 10,484,867 105,409 9,627,183 96,786 7,796,662 78,383 2025 11,021,134 106,922 10,056,025 101,098 8,334,303 83,788 2026 11,584,829 108,457 10,484,867 105,409 8,871,944 89,193 2027 13,083,576 116,058 11,021,134 106,922 9,409,585 94,599 2028 14,776,219 124,191 11,584,829 108,457 9,947,226 100,004 2029 16,687,840 132,894 13,083,576 116,058 10,484,867 105,409 2030 18,846,772 142,207 14,776,219 124,191 11,021,134 106,922 2031 21,285,007 152,173 16,687,840 132,894 11,584,829 108,457 2032 22,360,668 156,763 18,846,772 142,207 13,083,576 116,058 2033 23,490,689 161,492 21,285,007 152,173 14,776,219 124,191 2034 24,677,816 166,364 22,360,668 156,763 16,687,840 132,894 2035 25,924,936 171,382 23,490,689 161,492 18,846,772 142,207 2036 27,235,081 176,552 24,677,816 166,364 21,285,007 152,173 2037 28,611,435 181,878 25,924,936 171,382 22,360,668 156,763 2038 30,057,345 187,365 27,235,081 176,552 23,490,689 161,492 2039 31,576,325 193,017 28,611,435 181,878 24,677,816 166,364 2040 33,172,069 198,839 30,057,345 187,365 25,924,936 171,382 Table 25 shows the duration of each stage for each scenario. Table 25: Duration of each stage for each scenario Year Scenario 1 Scenario 2 Scenario 3 COVID-19 recovery 2020-2024 2020-2026 2020-2029 Opening stage 2025-2026 2027-2028 2030-2031 Rapid growth stage 2027-2031 2029-2033 2032-2036 Consolidation stage 2032-2040 2034-2040 2037-2040 Figures 29 and 30 depict the graphics that can be extracted from Table 24: the forecast of annual aircraft movement and passengers for the new airport for the three scenarios presented. It is evident that Scenario 1 is the most favourable, considering that the the recuperation from COVID-19 affections is the fastest of all and the normal growth that a new airport experiences can begin earlier. Scenario 2 is similar to Scenario 1 although a bit slower. Regarding Scenario 3, it is the worst case scenario, considering that the recuperation from COVID-19 affection is the slowest. The differences between the results for each scenario magnifies with time, so the most desirable scenario is Scenario 1. TFG Report Page 64 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040 Year 40 60 80 100 120 140 160 180 200 Number of aircraft movements [thousands] Annual traffic forecast for aircraft movements in three scenarios Scenario 1 Scenario 2 Scenario 3 Figure 29: Forecast of annual aircraft movements for the new airport As observed, all the scenarios begin at the same point but evolve differently. At short term (2025), the forecasts for annual aircraft movements are 104,100 and 82 thousand, respectively, for each scenario; at medium term (2030), 141,122 and 104 millions, respectively; and at long term (2040), 200,184 and 166. TFG Report Page 65 of 167
UPC-ESEIAAT 4 TRAFFIC FORECAST 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040 Year 0 5 10 15 20 25 30 35 Number of passengers [millions] Annual traffic forecast for passengers in three scenarios Scenario 1 Scenario 2 Scenario 3 Figure 30: Forecast of annual passengers for the new airport As with the previous case, all the scenarios begin at the same point but evolve differently. At short term (2025), the forecasts for annual passengers are 12,10 and 7millions, respectively, for each scenario; at medium term (2030), 18,15 and 12 millions, respectively; and at long term (2040), 34,30 and 26. TFG Report Page 66 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE 5 Description of the airside This section’s contents are based on the Annex 14 - Aerodromes - Volume 1: Aerodrome Design and Operations [43], the Aerodrome Design Manual - Part 1: Runways [44], the Aerodrome Design Manual - Part 2: Taxiways, Aprons and Holding Bays [45] and the Airport Capacity and Delay Advisory Circular [46]. The airside is one of the two main pillars of an airport and, as expected, it is of paramount importance to describe and explain how it will be defined. Firstly, the design aircraft has been defined based on the gathered information, which is a crucial point, seeing that all the airport will serve this type or aircraft. Next, the runways, taxiways, bypasses and aprons systems will be defined. To finish up, an analysis of the airport’s obstacle limitation surfaces will be made. 5.1 Definition of the design aircraft and of the aerodrome reference code In order to define the design aircraft for the regional airport, the flights from the 11th of November to the 17th of November of the Airport of Munich have been analysed from its website [35]. It is obvious that due to COVID-19 the number of flights is strictly reduced, but it has been considered that the proportion of aircraft has been maintained. With this information, Table 26 has been made, which depicts the brand and model of the aircraft used during the studied period of time, the number of times it has been used and the percentage that it represents from the total. Table 26: List of aircraft ordered from largest to smallest frequency Nomenclature Aircraft Wingspan Length MTOW Seating Capacity Percentage B738 [47] Boeing 737-800 Scimitar Winglets 35.79 39.47 79016 160 13.41 E75L [48] Embraer ERJ 170-200 / E175 Long Wing 26.00 29.90 37200 78 13.41 E75S [48] Embraer ERJ 170-200 / E175 Short Wing 28.65 29.90 37200 78 11.17 A320 [49] Airbus A320-100/200 35.80 37.57 79000 180 9.50 E190 [50] Embraer ERJ 190-100 / E190 28.72 36.24 51800 106 9.50 A319 [51] Airbus A319 35.80 33.84 76500 156 6.70 A321 [52] Airbus A321-100/200 35.80 44.51 97000 202 6.15 BCS3 [53] Airbus A220-300 35.10 38.70 69900 160 5.59 E170 [54] Embraer ERJ 170-100 / E170 26.00 29.90 37200 78 5.59 A20N [49] Airbus A320-Neo 35.80 37.57 79000 180 4.47 B737 [47] Boeing 737-700 Winglets 35.79 36.63 70080 148 3.35 DH8D [55] De Havilland Canada Dash 8-400 28.42 32.83 29257 86 3.35 AT76 [56] ATR 72 27.05 27.17 22800 78 3.35 E195 [50] Embraer ERJ 190-200 / E195 28.72 38.67 52290 118 2.23 A318 [57] Airbus A318 34.10 31.45 68000 132 1.12 B734 [47] Boeing 737-400 28.88 36.40 68039 159 1.12 Note that the “Aircraft characteristics and Airport and Maintenance Planning Manuals”15 for all the aircraft has been consulted in order to obtain all the information shown in Table 26. Although the Embraer aircraft are the most used (41.90%), they are not, by far, the most restrictive. However, the Airbus aircraft, which are the second most used (32.55%) are the most restrictive in terms of MTOW and wingspan. Thus, the design aircraft will be of Airbus’ family. Furthermore, the Boeing aircraft comprise 17.88% and the rest of the aircraft (ATR 72 and De Havilland Dash 8) make the remaining 6.70%. It is obvious that if the A321-100 aircraft has to be defined as the design aircraft due to its wingspan and MTOW. As a consequence, the requirements will automatically be fulfilled for the rest of the aircraft. Therefore, the code letter for the regional airport will be C and it will be able to serve the 100% of the aircraft that are planned to operate in the new 15They are referenced in the first column of Table 26. TFG Report Page 67 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE airport. The next step is to find the code number of the regional airport, which depends of the airplane reference field length. The reference field length is defined as the minimum necessary field length in order to take-off with the following standard conditions [43]: •At maximum certificated take-off weight. •At sea level. •At standard atmospheric conditions or ISA conditions (International Standard Atmosphere). •With still air. •With a zero runway slope. •With a dry runway surface. So as to calculate the reference field length, the MTOW (Maximum Take-Off Weight) is required. By reading [52], it has been seen that the weight variant WV011 of the A321 is the heaviest of the A321 family: 93,500 kg. Figure 31 depicts the runway length as a function of the take-off weight for the A321 in the aforementioned conditions. Taking into account the MTOW of the aircraft is 93,500 kg or 206,133 lbs and that the altitude of the International Airport of Munich is 448 mor 1,470 ft [58], the red lines can be drawn. Figure 31: Take-off runway length as a function of the take-off weight for the A321 [52] Thus, it is observed that the reference field length is 10,000 ft or 3,048 m. Since it is greater than 1,800 m, the code number of the runway will be 4. As a consequence, the aerodrome reference code is 4C. 5.2 Description of the runway system This subsection will be devoted to fully describe the runways, with all the aspects it concerns. TFG Report Page 68 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE 5.2.1 Length Although the length of the runway has been previously calculated and equal to 3,048 m, it must be noted that this length is real since the conditions under which it has been calculated are ideal. Therefore, correction factors must be applied. The Aerodrome Design Manual of the ICAO [44] dictates the following correction due to temperature: “The length of runway determined in the previous point should be further increased at the rate of 1% for every 1◦C by which the aerodrome reference temperature exceeds the temperature in the standard atmosphere for the aerodrome elevation”. As for other corrections, the correction due to elevation have been already taken into account in the calculations of the reference field length made with Figure 31, while the correction due to slope will be neglected as the slope will be considered to be 0%. Returning to the temperature correction, [58] dictates that the aerodrome reference temperature is 22.8◦C. Furthermore, seeing that the reference field length has been calculated in ISA conditions the base temperature will be 15.0◦C. Thus: 3,048 ·(1 + 0.01 ·(22.8−15.0)) = 3,285.7m At this moment, a factor of 1.15 will be applied to the previous number so as to obtain the total take-off runway length: 3,778.6m. This correction also accounts for the case in which the runway is wet. The previous number will be rounded up and thus the final runway length will be 3,780 m. The previous length has been calculated based on take-off conditions. Nevertheless, it must be assured that the design aircraft’s landing distance is not higher than this number, which will be calculated from Figure 32. Figure 32: Landing runway length as a function of the gross weight for the A321 [52] The worst case scenario, in which the gross weight of the aircraft will be equal to the MLW (77,800 kg or 171,520 lb), will be assumed. Furthermore, if the altitude of the TFG Report Page 69 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE International Airport of Munich is 448 mor 1,470 ft, the red lines can be drawn. The result is a landing runway distance of 5,700 ft or 1,734 m. Note that this distance has to be divided by 0.6, as to obtain the landing field. Thus, the landing field length is 2,890 m. Considering that the take-off distance is greater than the landing field, it can be finally assumed that the runway length will be 3,780 m. 5.2.2 Orientation and denomination The orientation of an airport’s runway is strictly related to the direction from which the wind blows more frequently. This information can be comprised in a wind rose, which is seen in Figure 33 and which has been made based on the winds of Munich. This wind rose has been extracted from a website named “meteoblue”, which is a company that has been archiving weather model data since 2007. Furthermore, in 2014 they started to calculate weather models with historical data from 1985 and generated a continuous history with hourly weather data. For this reason, the author believes that the source of this information is reliable and solid. Figure 33: Wind rose of Munich [59] In [59], if the mouse is hovered over the wind rose, the amount of yearly hours from every direction of the wind is displayed and categorised as a function of its velocity. With this information, Table 27 and Table 28 have been elaborated. TFG Report Page 70 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Table 27: Direction, velocity and number of yearly hours of the blowing wind (from 2007 to 2020) Direction of the wind Wind velocity in km/h Total 0 >1 >5 >12 >19 >28 >38 >50 >61 N 7 74 73 22 4 0 0 0 0 180 NNE 4 63 79 24 5 0 0 0 0 175 NE 2 62 120 64 18 4 0 0 0 270 ENE 7 115 309 271 137 46 8 1 0 894 E 0 91 266 157 54 17 3 0 0 588 ESE 6 127 233 80 15 1 0 0 0 462 SE 2 113 215 59 9 0 0 0 0 398 SSE 0 119 264 71 10 0 0 0 0 464 S 14 176 417 121 11 1 0 0 0 740 SSW 1 100 272 118 28 4 0 0 0 523 SW 6 97 257 195 117 51 17 2 0 742 WSW 0 72 234 297 298 214 115 48 22 1,300 W 6 108 260 339 260 128 67 30 14 1,212 WNW 2 61 144 128 58 21 8 3 1 426 NW 5 62 101 55 17 4 1 0 0 245 NNW 0 45 65 30 7 1 0 0 0 148 Total 62 1,485 3,309 2,031 1,048 492 219 84 37 8,767 Table 28: Direction, velocity and number of yearly frequency of the blowing wind (from 2007 to 2020) Direction of the wind Wind velocity in km/h Total 0 >1 >5 >12 >19 >28 >38 >50 >61 N 0.08 0.84 0.83 0.25 0.05 0.00 0.00 0.00 0.00 2.05 NNE 0.05 0.72 0.90 0.27 0.06 0.00 0.00 0.00 0.00 2.00 NE 0.02 0.71 1.37 0.73 0.21 0.05 0.00 0.00 0.00 3.08 ENE 0.08 1.31 3.52 3.09 1.56 0.52 0.09 0.01 0.00 10.20 E 0.00 1.04 3.03 1.79 0.62 0.19 0.03 0.00 0.00 6.71 ESE 0.07 1.45 2.66 0.91 0.17 0.01 0.00 0.00 0.00 5.27 SE 0.02 1.29 2.45 0.67 0.10 0.00 0.00 0.00 0.00 4.54 SSE 0.00 1.36 3.01 0.81 0.11 0.00 0.00 0.00 0.00 5.29 S 0.16 2.01 4.76 1.38 0.13 0.01 0.00 0.00 0.00 8.44 SSW 0.01 1.14 3.10 1.35 0.32 0.05 0.00 0.00 0.00 5.97 SW 0.07 1.11 2.93 2.22 1.33 0.58 0.19 0.02 0.00 8.46 WSW 0.00 0.82 2.67 3.39 3.40 2.44 1.31 0.55 0.25 14.83 W 0.07 1.23 2.97 3.87 2.97 1.46 0.76 0.34 0.16 13.82 WNW 0.02 0.70 1.64 1.46 0.66 0.24 0.09 0.03 0.01 4.86 NW 0.06 0.71 1.15 0.63 0.19 0.05 0.01 0.00 0.00 2.79 NNW 0.00 0.51 0.74 0.34 0.08 0.01 0.00 0.00 0.00 1.69 Total 0.71 16.94 37.74 23.17 11.95 5.61 2.50 0.96 0.42 100.00 The election of the optimum direction for the runway is of paramount importance. For instance, when the wind blows against the aircraft, the generated lift during take-offs and the generated drag during landings are increased, which favour both operations, respectively. For this reason, the runways must be oriented to the direction from which the wind blows more frequently and, if possible, with more velocity. Moreover, for safety reasons, the runways must also be oriented in such directions that operations with crosswind or tailwind are minimised and/or could be avoided. The number and orientation of the runways of an aerodrome should be those that allow a TFG Report Page 71 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE usability factor of 95% or superior for the design aircraft of the airport. In case it cannot be reached with a single runway, another one with another direction must be built. To take into account all this aspects and requirements, the information of Table 28 has been analysed by coding a computer program with MATLAB, which will be shown in the Attachments document. The aim of this code is to analyse the provided information and see which directions of the wind minimise the crosswind and, as a consequence, are safer. It has been calculated for large-sized, medium-sized and small-sized aircraft assuming that the maximum crosswind allowed is 37 km/h,24 km/h and 19 km/h, respectively. The results are shown in Figure 34. N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW Runway direction 75 80 85 90 95 100 Flight possibility [%] Flight possibility due to transversal wind Flight possibility for small-sized aircrafts Flight possibility for medium-sized aircrafts Flight possibility for large-sized aircrafts Critical line of the usability factor Figure 34: Flight possibility due to crosswind as a function of the wind direction As observed, there are multiple directions that fulfil the requirement of a minimum usability factor of 95% for all sizes of aircraft. Nevertheless, the best direction is WSW and the opposed ENE, which correspond to 67.7◦and 247.5◦, respectively and geographically. The magnetic declination in Munich is 3◦400E[60] and, as a consequence, this degree has to be subtracted from the aforementioned geographical degree and thus the magnetic degrees are 63.84◦and 243.84◦for WSW and ENE, respectively. Therefore, the runway that goes from WSW to ENE will be denominated as 06 and the runway that goes from ENE to WSW will be denominated as 24. This performed study is a preliminary study of winds. A more advanced study (which would be out of the scope of this project) should take into account the prevalence and nature of gusts and turbulence, the width of the runway, the condition of the runway surface and the poor visibility or low cloud base conditions. 5.2.3 Capacity “Hourly airport capacities computations are needed to design and evaluate airport development projects. The throughput method for calculating airport capacity is derived from computer models used by the Federal Aviation Administration (FAA) to analyse airport capacity” [46]. TFG Report Page 72 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE will used. Stopways The stopway is an area located at the end of the runway which can be used for deceleration in the event of a rejected takeoff. The length of the stopway depends on the accelerationstop distance and the decision speed, which depend on the aircraft performance. Considering that this information is not provided, it will be assumed that the acceleration-stop distance available is inferior to the take-off run available. As a consequence, no stopway is necessary. Declared distances Figure 43 shows the different distances that form a runway. Considering that the runway of the new airport has no displaced threshold, no clearway and no stopway, the present situation is Figure 43A. Thus, all the declared distances are the same: •LDA (Landing Distance Available): 3,781 m. •TORA (Take-Off Runway Available): 3,781 m. •ASDA (Acceleration-Stop Distance Available): 3,781 m. •TODA (Take-Off Distance Available): 3,781 m. Figure 43: Declared distances for a runway [43] 5.3 Description of the taxiway system The taxiway system is an airport element that links the runways with the passenger terminals, aircraft storage and servicing areas. Its objective is to achieve maximum capacity, efficiency and safety in the airport and therefore maximise the utilisation of the aerodrome. Thus, it should be designed in a way that minimises the restriction of aircraft movement in order to maintain a continuous and smooth flow of aircraft ground traffic at maximum practical speed and with minimum acceleration or deceleration. Taxiways are, as runways, the least flexible elements of an airport. As a consequence, they need to be designed as a function of the future rate of aircraft movements, nature of the traffic and the type of aircraft, among other factors. Thus, rather than focusing on the present need of the airport, the previously made forecasts will be considered when designing the taxiway system. When planning the layout of the taxiway system, some principles must be followed: •Taxiways should connect airport elements by the shortest distances, which minimises TFG Report Page 79 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE taxiing time and cost in fuel and maximises safety and aircraft utilisation. •Taxiways should be as simple as possible so that pilots do not get confused or need complex instructions. •When possible, taxiways should always be straight, which is safer. Thus, changes in direction should be as few as possible. •When possible, crossings with runways and other taxiways should be minimised so as to maximise safety and minimise taxiing delays. •When possible, taxiways should only have a one-way direction in order to minimise conflicts and delay. •The taxiway system must be designed so that every element of the system has the longest life possible so as to minimise costs. •Taxiways should avoid getting into areas where the public could easily access to the aircraft. The intention is to avoid aircraft sabotage or aggression. •“A chain is as strong as its weakest link”. This set-phrase refers to a taxiway system in the sense that its performance is as good as the performance of the least efficient element. As a consequence, these bottlenecks should be recognised and eliminated. •The taxiway system must be fully visible from the control tower. •The taxiway system layout must be design so that interference with navigation aids are minimised. •Entrance taxiways should be perpendicular to a runway so as to provide pilots with an unobstructed view of the entire runway, in both directions, to confirm that the runway and approach are clear of conflicting traffic before proceeding towards the runway. 5.3.1 Types of taxiways There are several types of taxiways and they will be explained next. Entrance and exit taxiways Entrance and exit taxiways are directly connected to the runway and are used to enter the runway in order to take off or to exit the runway after landing. Thus, their objective is to minimise the runway occupancy time of a departing or arriving aircraft. The number of this type of taxiway must be sufficient enough to achieve a good capacity during the peak-hour. Exactly as with runways, the taxiway system is designed to achieve maximum operational quality. When designing this type of taxiways, some principles must be considered: •The location of exit taxiways depends on the type of aircraft the airport serves. Thus, the optimum number and separation must be determined by grouping these aircraft by classes based on the landing speed and deceleration after touchdown. •The angle between the exit taxiway and the runway can be right or acute. The first one requires the aircraft to decelerate to a very low speed before exiting the runway while the second one allows the aircraft to exit the runway at higher speeds, which reduces the occupancy time of the runway more than for the first right-angle exit taxiway and thus the capacity of the runway is increased. The latter type of exit taxiway is called “rapid exit taxiway” and they will be better explained later. •Generally, a single entrance taxiway at the end of the runway is enough to cover the demand of take-offs. Nevertheless, if the traffic volume requires so, holding bays, TFG Report Page 80 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE bypasses or multiple runway entrances can be used. Rapid exit taxiways When planning rapid exit taxiways, some principles must be taken into account: •The main factor that limits the runway capacity is the time separation between landing and departing aircraft. •One of the most important criterion when locating the rapid exit taxiways is the aircraft mix index, considering that each type of aircraft requires different landing distances. •The number of exit taxiways depends on the types of aircraft and their frequency of operation during the peak hour. •Other factors to take into account when locating the rapid exit taxiways are the location of the terminal and apron area and avoidance of unnecessary taxi detours, among others. •A rapid exit taxiway must include a straight distance clear of any intersecting taxiway after the turn-off curve in order to allow the aircraft that uses it to arrive to a full stop. Taxiways located on aprons Apron taxiways can be divided in two type: •Apron taxiways, whose objective is to provide an access route across the apron or to access an aircraft stand taxilane. •Aircraft stand taxilane, which is a part of an apron whose objective is to provide access to aircraft stands. 5.3.2 Dimensions Rapid exit taxiways The radius of turn-off curve for airport with code number 4must be 550 mso as to enable an exit speed under wet condition of 93 km/h [43]. Additionally, the intersection angle of a rapid exit taxiway with the runway should not be greater than 45◦nor less than 25◦and preferably should be 30◦[43]. Thus, for the present airport, the angle will be 30◦.Figure 44 depicts a rapid exit taxiway with all its elements. Figure 44: Rapid exit taxiway with all its elements [43] TFG Report Page 81 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Taxiway minimum separation distances Figure 45 depicts a table with the taxiway minimum separation distances that must be applied. Note that the distances that apply for the airport of the present project are marked with red squares. Figure 45: Taxiway minimum separation distances [43] Fillets Fillets are an additional pavement on taxiway curves and taxiway junctions and intersections (with runways, other taxiways and aprons) used to achieve the minimum clearance distances between the outer main wheels of the aircraft and the edge of the taxiway when the cockpit of the aircraft remains over the taxiway centre line markings. This minimum distance is 3mfor aircraft with an outer main gear wheel span between 6mand 9mand with a wheel base less than 18 m(see Table 30 to see the outer main gear wheel span and wheel base of all the aircraft that the new airport will serve). An example of fillet can be seen in Figure 46. Table 30: Outer main gear wheel span and wheel base of all the aircraft that the new airport will serve Nomenclature Aircraft OMGWS Wheel base A321 [52] Airbus A321-100/200 8.97 16.90 A320 [49] Airbus A320-100/200 8.95 12.64 A20N [49] Airbus A320-Neo 8.95 12.64 A319 [51] Airbus A319 8.95 11.04 A318 [57] Airbus A318 8.95 10.25 DH8D [55] De Havilland Canada Dash 8-400 8.80 13.99 E195 [61] Embraer ERJ 190-200 / E195 5.94 14.64 E190 [50] Embraer ERJ 190-100 / E190 5.94 13.81 B738 [47] Boeing 737-800 Scimitar Winglets 5.72 15.60 B737 [47] Boeing 737-700 Winglets 5.72 12.60 B734 [47] Boeing 737-400 5.23 14.27 E170 [48] Embraer ERJ 170-100 / E170 5.20 10.60 E75L [54] Embraer ERJ 170-200 / E175 Long Wing 5.20 10.60 E75S [54] Embraer ERJ 170-200 / E175 Short Wing 5.20 10.60 AT76 [62] ATR 72 4.1 10.77 TFG Report Page 82 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Figure 46: Taxiway widening with a fillet [43] Taxiway width, shoulders and strips The taxiway width for aircraft with an outer main gear wheel span between 6mand 9m is 15 m. “A shoulder is an area adjacent to the edge of a full strength paved surface so prepared as to provide transition between the full strength pavement and the adjacent surface” [45]. The objectives of taxiway shoulders are: to avoid the ingestion of objects by the jet engines, which could damage them, to avoid erosion of the area adjacent to the taxiway and to provide a safe surface for the occasional passage of an aircraft. For airport with code letter C, the overall width of the taxiway with shoulder must be 25 m. A strip is an area that includes the taxiway whose objective is to protect the aircraft and to reduce the risk of damaging an aircraft when it accidentally runs off the taxiway. The overall width of the taxiway strips must be 52 m. 5.3.3 Final decision of the taxiway system Configuration of the taxiway system The taxiway system will be provided with two entrance taxiways, four rapid exit taxiways (two for each way) and two exit taxiways. The taxiway minimum separation distances have been applied to the taxiway system and fillets have been used to comply with the regulations. The decision of the location and number of the rapid exit taxiways has been made by analysing the landing field lengths for all the aircraft that the new airport serves, which can be seen in Table 31. The same process as for the Airbus A321 has been followed. TFG Report Page 83 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Table 31: Landing field lengths for all the aircraft that the new airport serves Aircraft Landing field length Boeing 737-800 Scimitar Winglets 1,905 Boeing 737-400 1,752 Airbus A321-100/200 1,734 Airbus A320-100/200 1,600 Airbus A320-Neo 1,600 Boeing 737-700 Winglets 1,600 Embraer ERJ 190-200 / E195 1,575 Airbus A319 1,525 Airbus A318 1,500 Embraer ERJ 190-100 / E190 1,450 Embraer ERJ 170-100 / E170 1,400 Embraer ERJ 170-200 / E175 Long Wing 1,400 Embraer ERJ 170-200 / E175 Short Wing 1,400 Considering that the landing field lengths range from 1,400 mto 1,900 m, it has been considered that three rapid exit taxiway would be too tight and thus only two will be used. The two rapid exit taxiways will be located at 1,500 mand 1,900 mfrom the runway threshold. Drawings The result of the taxiway system can be seen in Figure 40. For more details of the taxiway system, see the Drawings document. 5.4 Description of the bypass system Usually, departures are cleared in the order in which they are ready to take-off. Nevertheless, when efficiency can be maximised and delay can be minimised, this order can be altered. If the aerodrome has a single taxiway and no holding bays or other types of bypasses, the aerodrome control units cannot change the sequence of departures once the aircraft have left the apron. Moreover, if the apron area is large, it is difficult to command the exit of aircraft from the apron in such a way that they will arrive at the end of the runway in the same order. The use of holding bays and other bypasses provides flexibility for the air traffic services units in adjusting the take-off sequence to overcome delays. As a consequence, the capacity of the airport is increased. Other advantages of holding bays and other bypasses are that they give time to do the pre-flight checks needed to ensure the safety of the flight. When designing bypasses, some principles must be considered: •The minimum centre line to centre line separations between taxiways and runways must be maintained. •The cost of construction any bypass is directly related to the area of new pavement required. •Whichever bypass is selected, there must always exist an entrance to the beginning of the runway so that the most restrictive aircraft can use all the runway length. TFG Report Page 84 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE 5.4.1 Types of bypasses There are several types of bypasses and they will be explained next. Holding bays A holding bay is an area where aircraft can be held or bypassed. Holding bays allow the aircraft to leave and re-enter the departure stream. Examples of holding bay configurations are shown in Figure 47. Figure 47: Holding bay configuration examples [45] Dual taxiways Dual taxiways consist in a second taxiway used to bypass the normal parallel taxiway. Dual taxiways can alter the departure priority by separating the departure stream into two parts, although the flexibility is not very high. Examples of dual taxiways configurations are shown in Figure 48. Figure 48: Dual taxiways configuration examples [45] TFG Report Page 85 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Dual runway entrances Dual runway entrances consist in duplicating the taxiway entrance to the runway. Dual runway entrances reduce the take-off run available for the aircraft that uses the entrance not located at the extremity of the runway, although it is not a great disadvantage if the corresponding aircraft does not need all the runway to take-off. The combination of dual taxiways with dual runway entrances offer a great degree of flexibility. Examples of dual runway entrances configurations are shown in Figure 49. Figure 49: Dual runway entrances configuration examples [45] 5.4.2 Dimensions Size and location of holding bays The needed space for a holding bay depends on the number of aircraft positions to be provided, the size of the corresponding aircraft and the frequency of utilisation. The dimensions must allow enough space between aircraft to enable them to manoeuvre independently. Nevertheless, the wing tip clearance between a parked aircraft and a moving aircraft should not be less than 5mfor the code number 4. As for the location of the holding bay, the most beneficial location is adjacent to the taxiway serving the runway end. Note that the minimum distance from the runway centre line to a holding bay, runwayholding position or road-holding position must be 90 mfor airports of code number 4and precision approach category III. 5.4.3 Final decision of the bypass system Configuration of the bypass system For the present project, a combination of all three types of bypass will be used: a holding bay that can host two aircraft will be provided on the taxiway that leads to the runway entrance and dual taxiways and entrances will be used. Drawings The result of the bypass system can be seen in Figure 50. For more details of the bypass system, see the Drawings document. TFG Report Page 86 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Figure 50: Double entrance, dual taxiways and holding bay 5.5 Description of the apron system An apron is the area where aircraft are accommodated for the purpose of loading and unloading passengers, mail, cargo, fuelling and parking or maintenance. When designing an apron, some design requirements must be considered: •Safety. Safety procedures for aircraft manoeuvring on the apron are of paramount importance. Thus, aircraft must maintain specified clearances and follow the declared procedures to enter, move within and depart from apron areas. Services provided to parked aircraft on the airport must follow safety procedures too. Furthermore, apron areas must be physically separated from public access areas so as to make sure no unauthorised personnel has access to the aprons and to maximise the security of aircraft. •Efficiency. The efficiency of aircraft movements and services is strictly related to the design of the apron. Freedom of movement, minimum taxi distances and minimum delay are the result of a well-designed apron. As a consequence, greater utilisation of the apron area will be ensured and maximum economic value will be achieved. •Geometry. The geometry of the aircraft that the airport is intended to serve is directly related to the the apron layout that should be used. Other factors that must be taken into account when designing the apron area are the clearances between the aircraft and other aircraft or objects, the geometric arrangements of aircraft stand taxilanes and other taxiways, among others. •Flexibility. The number and size of aircraft stands should be determined by the number and size of the aircraft types that the airport is intended to serve. There are two methods for designing the apron stands: –Use one size of aircraft stand large enough to cover the largest aircraft type. TFG Report Page 87 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE –Use a size of aircraft stand for each type of aircraft that the airport is intended to serve. The first method is highly inefficient in terms of area usage while the second provides low operational flexibility. Another important factor (in terms of flexibility) to take into account when designing the apron area is allowance for expansion to meet future needs. As a consequence future restrictions of the airport’s growth potential will be minimised. Additionally, if the apron area is designed by using modular stages, the future additions will have a minimum impact on the disruption to ongoing activities. 5.5.1 Types of aprons There are many types of aprons and the will be explained next. Passenger terminal apron A passenger terminal apron is an area adjacent or accessible to passenger terminal facilities in order to allow passengers to board the aircraft. It is also used for aircraft fuelling and maintenance as well as loading and unloading of cargo, mail and baggage. Cargo terminal apron A cargo terminal apron is an area adjacent to a cargo terminal building and is used by aircraft that only carry freight and mail. Remote parking apron A remote parking apron is an area intended for aircraft that need to be parked for extended periods of time. It should be located as close to the terminal area as possible to minimise the time of passenger loading/unloading as well as from a security point of view. Isolated aircraft apron An isolated aircraft apron is a parking position intended to aircraft that are known or believed to be the subject of unlawful interference or, for other reasons, need isolation from normal airport activities. It should be located the farthest possible and under no circumstance closer than 100 mto other parking positions, buildings or public areas. Furthermore, it must be made sure that under the isolated aircraft apron there are no underground utilities that could be hazardous. Service aprons A service apron is an uncovered area adjacent to an aircraft hangar where aircraft maintenance can be performed. Hangar aprons A hangar apron is an area that aircraft use as a storage hangar. General aviation aprons The last type of apron is the general aviation apron, which is used for business and personal flying. These aprons require several categories to support different general aviation activities. 5.5.2 Types of apron layouts The election and design of the type of terminal apron parking layout for airport is strictly dependant on the type of terminal design, and vice versa. One must pay attention to the volume of aircraft traffic using the terminal, which is an important factor when it comes TFG Report Page 88 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Table 32: Type or aircraft stand for each aircraft and other information Aircraft Width Length Type of aircraft stand Percentage Airbus A321-100/200 40.3 49.01 V 6.15 Airbus A220-300 40.3 42.07 VI 5.59 Airbus A319 40.3 38.34 VI 6.70 Airbus A320-100/200 40.3 42.07 VI 9.50 Airbus A320-Neo 40.29 41.13 VI 4.47 Boeing 737-800 Scimitar Winglets 40.29 43.97 VI 13.41 Boeing 737-700 Winglets 39.6 43.2 VII 3.35 Embraer ERJ 170-200 / E175 Short Wing 38.6 35.95 VII 11.17 Airbus A318 33.38 40.9 VII 1.12 Boeing 737-400 33.22 40.74 VII 1.12 Embraer ERJ 190-200 / E195 33.22 43.17 VII 2.23 Embraer ERJ 190-100 / E190 32.92 37.33 VII 9.50 De Havilland Canada Dash 8-400 33.15 34.4 VIII 3.35 Embraer ERJ 170-200 / E175 Long Wing 31.55 31.666 VIII 13.41 ATR 72 30.5 34.4 VIII 3.35 Embraer ERJ 170-100 / E170 30.5 34.4 VIII 5.59 In Table 32 all the aircraft that operate in the new airport are shown, together with several information: •The first and second columns depict the wingspan and length of the aircraft plus the aircraft stand clearances required, which has been previously mentioned: 4.5m. •The third column depicts the type or aircraft stand in which it fits, based on the data of Figure 60. •The fourth column depicts the percentage of use of each aircraft. Focusing on the aircraft stands, the results are shown in Table 33. Table 33: Type or aircraft stand for each aircraft and percentage of use Type of aircraft stand Percentage V 6.15 VI 39.66 VII 28.49 VIII 25.70 Based on this result, four types of aircraft stand must be used. Nevertheless, as previously stated, the more types of aircraft stand are used, the lower the operational flexibility is. As a consequence, it has been decided to use only two types of aircraft stand: type V, comprising 45.81% of aircraft, and type VII, comprising 54.19% of aircraft. By doing so, the usage of the apron area is more efficient. At this moment, the type and size of aircraft stands are defined. The next step is to find how many aircraft stands are needed for the passenger terminal apron and for the remote parking apron. So as to do so, the table of arrivals and departures of the Airport of Munich after applying all the filters from the Attachments document has been used. The table of arrivals and departures has been compared in order to find, for each aircraft, the time spent on the apron since the arrival to the departure. If the time spent was less than 2hours, it has been considered that the aircraft was parked on the passenger terminal apron; if the time spent was more than 2hours, it has been considered that the aircraft was parked on a nearby remote parking apron, and if the time spent was all the night, it has been TFG Report Page 95 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE considered that the aircraft was parked on a far away remote parking apron. From all the 79 aircraft used during the week18,82.28% were parked on a passenger terminal apron, 13.92% were parked on a far away remote parking apron and 3.80% were parked on a nearby remote parking apron. As for the parking time, the average time parked on a passenger terminal apron was 67 minutes, whereas the average time parked on a nearby remote parking apron was 166 minutes. If the apron has to be design as a function of the peak hour, it must be taken into account that during this hour there will be around 30 operations. Applying the above-mentioned percentages 25 aircraft will park on a passenger terminal apron, 4will park on the far way remote parking apron and 1will park on the nearby remote parking apron. Thus, the number of aircraft stands will be 25,4and 1, on the passenger terminal apron, the far away remote parking and the nearby remote parking apron, respectively. Furthermore, the hourly capacity of the gates on the apron can be calculated by using Figure 61 so as to make sure that there will be no congestion. Figure 61: Hourly capacity of gates [46] If operations do not include widebody aircraft, which is the present case, the gate mix is 100 and R= 1. Then, using the graphics for a gate occupancy of 67 minutes19, it is obtained that G∗= 1.8and S= 1. From the 25 aircraft stands, 45.81% will be type V and 54.19% will be type VII, which correspond to 11.5and 13.5aircraft stands, respectively. It is obvious that the latter numbers must be entire and thus they will be rounded up to 12 type V and 14 type VII aircraft stands, with a total of 26. If there are 26 aircraft stands, the number of gates is N= 26 and the hourly capacity of 18This number may seem low but it was during the pandemic. 19Note that this number is not in the graphic, so a linear interpolation has been made. TFG Report Page 96 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE the gates is G=G∗·S·N= 46.8≈47 operations per hour. This number far exceeds the operations per hour during the peak hour. Nevertheless, it will be maintained because, in the future, the operations per hour during the peak hour will increase. Drawings The result of the apron system can be seen in Figure 62. For more details of the apron system, see the Drawings document. Figure 62: Terminal building with the aircraft stands 5.6 Visual aids in the airport Visual aids can be classified in five types: indicators and signalling devices, markings, lights, signs and markers [43]. The visual aids that will be used in the airport will be mentioned below. For more information about each one of them (application, location and characteristics) see the Attachments document. The markings visual aids have been already shown in Figures 40, 50 and 62. For more details, see the Drawings document20. •Indicators and signalling devices. –Wind direction indicator. –Landing direction indicator. –Signalling lamp. –Signal panels and signal area. •Markings. –Runway designation marking. 20Indicators and signalling devices, lights, signs and markers are not drawn. TFG Report Page 97 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE –Runway centre line marking. –Threshold marking. –Aiming point marking. –Touchdown zone marking. –Runway side stripe marking. –Taxiway centre line marking. –Runway-holding position marking. –Intermediate holding position marking. –Aircraft stand marking. –Mandatory instruction marking. –Information marking. •Lights. –Emergency lighting. –Aeronautical beacons. –Approach lighting systems. –Visual approach slope indicator systems. –Runway lead-in lighting systems. –Runway edge lights. –Runway threshold and wing bar lights. –Runway end lights. –Runway centre line lights. –Runway touchdown zone lights. –Simple touchdown zone lights. –Rapid exit taxiway indicator lights. –Taxiway centre line lights. –Taxiway edge lights. –Stop bars. –Intermediate holding position lights. –De-icing and anti-icing facility exit lights. –Runway guard lights. –Apron floodlighting. –Advanced docking guidance system. –Aircraft stand manoeuvring guidance lights. –No-entry bar. –Runway status lights. •Signs. –Mandatory instruction signs. –Information signs. TFG Report Page 98 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE –Aerodrome identification sign. –Aircraft stand identification sign. •Markers. –Edge-markers for snow-covered runways. 5.7 Other factors concerning the airside There are other factors concerning the airside that are not part of the scope of the present project but can be superficially commented. 5.7.1 Strength of pavement The pavement of each system of the airside must be capable of withstanding the traffic of aircraft which is intended to serve and without inducing structural damage to the aircraft. 5.7.2 Surface of pavement The surface of each system of the airside shall be constructed without irregularities that would impair the runway surface friction characteristics, cause structural damage to the aircraft or affect the take-off or landing of an aircraft. Moreover, it should resist erosion so that it does not break into pieces which can be ingested by engines. 5.7.3 Slopes Regarding the slopes of the movement area, the objective is to reduce it to 0%, although the final result depends on the construction work. Nevertheless, under no circumstance the slops shall surpass the limits that the Annex 14 stipulates. Other considerations concerning the slopes that must be taken into account are: •The transition between slope changes should be as gradual as practicable and abrupt changes or reversals in slope should avoided. •To promote the rapid drainage of water, the surface of the runway and of the taxiway systems surface should be cambered. As for the apron, the slope should be enough so as to avoid water accumulation. •Regarding the sight distance, a person which is 3mabove the runway should be able to see at a distance of at least half the length of the runway at the same height. 5.8 Description of the obstacle limitation surfaces This subsection is intended to establish the airspace around the new airport that must be cleared from obstacles in order to allow aircraft operations to be performed safely. So as to achieve so, various obstacle limitation surfaces, which establish the limits where objects can be, must be established. The obstacle limitation surfaces are listed below and their shape are shown in Figures 63, 64 and 65. •Conical surface. •Inner horizontal surface. •Inner approach surface. •Approach surface. •Transitional surface. TFG Report Page 99 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE •Inner transitional surface. •Balked landing surface. •Take-off climb surface. Figure 63: Obstacle limitation surfaces: view 1 [43] Figure 64: Obstacle limitation surfaces: view 2 [43] TFG Report Page 100 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Figure 65: Obstacle limitation surfaces: view 3 [43] The dimensions of each obstacle limitation surface is shown in Table 34. Note that all dimensions are measured horizontally unless specified otherwise. For more information about the characteristic of each surface, consult [43] Chapter 4. Table 34: Dimensions and slopes of obstacle limitation surfaces for a runway of aerodrome reference code 4C with precision approach category III [43] CONICAL APPROACH Slope 5% Length of inner edge 280 m Height 100 mDistance from threshold 60 m INNER HORIZONTAL Divergence (each side) 15% Height 45 mFirst section Radius 4,000 mLength 3,000 m INNER APPROACH Slope 2% Width 120 mSecond section Distance from threshold 60 mLength 3,600 m Length 900 mSlope 2.5% Slope 2% Horizontal section TRANSITIONAL Length 8,400 m Slope 14.3% Total length 15,000 m INNER TRANSITIONAL TAKE-OFF CLIMB Slope 33.3% Length of inner edge 180 m BALKED LANDING SURFACE Distance from runway end 60 m Length of inner edge 120 mDivergence (each side) 12.5% Distance from threshold 1,800 mFinal width 1,200 m Divergence (each side) 10% Length 1,800 m Slope 3.33% Slope 2% The result of the obstacle limitation surfaces applied to the case of the new airport can be TFG Report Page 101 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE observed in Figures 66, 67 and 68. Figure 66: Obstacle limitation surfaces for the new airport: view 1 Figure 67: Obstacle limitation surfaces for the new airport: view 2 TFG Report Page 102 of 167
UPC-ESEIAAT 5 DESCRIPTION OF THE AIRSIDE Figure 68: Obstacle limitation surfaces for the new airport: view 3 After analysing the shape of these obstacle limitation surfaces and the topography of the new airport’s location, it can be stated that there are no dangerous obstacles within these surfaces, in terms of topographic obstacles. As a conclusion of this subsection, any object situated in any system of the airside that may endanger aircraft should be considered as an obstacle and, if possible, be removed. The only objects allowed are the visual aids required for air navigation and for aircraft safety purposes, and they must be frangible, mounted as low as possible and located on the strip. These objects should be removed except when the appropriate authority or an aeronautical study states that the object does not adversely affect the safety and regularity of the operations of the aircraft. Objects that are beyond the obstacle limitation surfaces but are higher than 150 mabove the ground elevation should also be considered as an obstacle and an aeronautical study should investigate if it supposes a hazard to aircraft or not. Additionally, any object that affect the performance of visual or non-visual aids should be removed. TFG Report Page 103 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE 6 Description of the landside This section’s contents are based on the Airport Development Reference Manual [64]. The landside or terminal area is the other main pillar of an airport and, consequently, it is as important as the airside. The passenger terminal is a building that has many aims. Nonetheless, for all of them, it must be functionally and operationally efficient, commercially viable and must offer the best travel experience possible for the passengers. As a consequence, the airport’s landside needs to be able to adjust to the dynamic industry to which civil aviation belongs. In order to achieve these objectives, some key elements will be discussed: the terminal building configuration, the level of service, the balance between demand and capacity and the flow of passengers and its segregation, among other topics. 6.1 Design of the terminal When designing the terminal, the configuration of the movement areas well as the operational strategies of the most important airlines must be taken into account, since they complement each other and thus must be balanced. It is especially important to highlight the need to facilitate efficient and profitable operations for the airlines. Conceptual design principles When it comes to designing the terminal, there are some key conceptual principles and concepts that must be followed: •Modularity and expandibility. Airports should be able to expand incrementally so as to allow future growth in a logical and phased manner. Furthermore, each of the subsystems of an airport must be balanced with the others, seeing that it has no sense to have additional capacity in a subsystem if there is another one that bottlenecks it. By adopting a modular building philosophy, expansion can be performed without disrupting too much the other unaffected subsystems. •Compatibility and flexibility. Every subsystem has to be designed with flexibility in order to be able to adapt to future changes and still be compatible with the other subsystems. The physical constraints that every subsystem imposes on future expansion must be minimised so as to ensure flexibility. •Cost-effective design solutions. Whenever an expansion is planned, the benefits must be demonstrated and quantified by means of a business case and a cost-benefit analysis. These studies must show the benefits that the expansion will have on capacity, air traffic growth, operational efficiency and increased revenues or savings. •Centralisation. This issue consists in locating all the major subsystems in a single passenger terminal complex so that airlines do not need to duplicate activities and facilities. As a result, the expenses are optimised and the benefit is common for both the airlines and the passengers. Physical design principles “The simplest decision is “no decision”” [64]. This sentence can translate into the fact that the lesser the choices available there are for passenger when orienting themselves, the better. In order to apply this philosophy to the physical design of the terminal area, the physical principles and concepts listed below must be followed: •Passenger flow routes should be intuitive, simple and easily understood so as to avoid confusions and getting lost. •Passenger flow routes should be as short, straightforward, clear and unobstructed as possible. Furthermore, ample circulation space and resting points with seating TFG Report Page 104 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE wish to buy tickets or modify the already bought one. They will be oriented along the passenger flow in such a way that they do not interrupt it. •Airline offices, which offer support to passenger in the processing area and are located close to the other facilities of the airline. •Baggage handling system, where the baggage is handled. •Ancillary functions, which is a zone for other types of facilities or simply space for future functions. Departures passenger processing: check-in The scenario of processing facilities has evolved dramatically during the last years due to the continuous air traffic growth and progress in technology. Nowadays, passengers have more control and choice and can deal with the processing remotely, as opposed to how it was done before, when passenger had to physically assist to the processing facilities. This fact has allowed to reduce the number of processing facilities, which reduces congestion and costs and improves the processing times. As a consequence, the passenger flow is smoother and the travelling experience and level of service is enhanced. Therefore, it has been clearly demonstrated that the use of latest technologies is the best way to facilitate and accelerate the processes. For instance, the traditional check-in counters are being substituted by: •Mobile services. •Mobile agents with handheld equipment. •Self-service kiosks. •Self-service bag drop facilities. •Oversized luggage processing units. •Ticketing and assistance facilities. These services and facilities can process more passengers and baggage within the same area, which suggests that the capacity of the departure halls is greatly increased without the need of physically expanding. This translates into huge savings in capital investment for expansion. The nowadays scenario in airports comprise four types check-in, considering that the passengers already have their ticket bought. •Fast bag drop or assisted, which is intended for passengers who do not need to use processing facilities because they already have the boarding pass and have no hold baggage directly. Thus, they go to the security control. •Check-in at self-service kiosk without bag tag print, which is intended for passengers with no hold baggage that wish to use self-service kiosks to print their boarding pass. Then, they go to the security control. •Check-in at self-service kiosk with bag tag print, which is intended for passengers with hold baggage that wish to used self-service kiosks to print their boarding pass and then proceed to the bag drop counter, where the baggage is weighed, tagged and inserted into the baggage handling system. Then they go to the security control. •Conventional check-in, which is intended for passengers with hold baggage that wish to use conventional check-in and the corresponding full process. Then they go to the security control. Figure 70 depicts the efficiency of each check-in option. TFG Report Page 111 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE Figure 70: Efficiency advantage of split processes [64] The distribution of the processing facilities can be centralised (all located within the departures hall) or decentralised (the facilities are located along the passenger flow). Figure 71 show an example of a layout for a centralised processing area, which includes self-service kiosks and bag drop facilities. The blue zones are where queues are formed and the yellow arrows depict the flow for each type of passenger. Figure 71: Schematic layout example for the processing facilities [64] Further design considerations that must be taken into account when designing the processing area are: •The locations of baggage trolleys and storage areas. TFG Report Page 112 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE •The shape of queues and the tools that will be used. •The seating for people. •The departure flight information display, which depicts information about the flights. •The final area were the baggage go must be secured against public access and is considered to be airside. Emigration and immigration In order to verify that the documents of passengers and crew on both arrivals and departures are correct and that the corresponding person has the right to enter or exit the country, the government dictates that passport and border controls will be used. These controls are referred to immigration when controlling arrivals and emigration when controlling departures. As long as it is possible, it should be an automated service with the corresponding facilities and it should be centralised in a single location so as to make the most of the resources. Additionally, control desks and offices will be provided for interviewing rooms. For emigration, the control can be located before or after the passenger security screening. Passenger security screening Passenger security screening is a process that consists in controlling the passengers and their hand luggage by means of both equipment and trained personnel. Its function is to allow the passengers to access the security-restricted airside once it has been proven that they are not a threat to the airport, to aircraft or to people. The checked luggage is also security screened before loading it onto the aircraft. Security screening facilities should be centralised in a single facility and logically located among the other facilities and through the passenger flow. The process should be designed so as to be the simplest and least invasive search of passengers. Special attention must be payed to try to reduce the stress that passengers undergo and to try to avoid the disruption of the passenger flow by designing the process in an intuitive way. The final aim is to minimise the the amount of time spent during security screening and to avoid passenger divesting. A layout example and its dimensions is shown in Figure 72. TFG Report Page 113 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE Figure 72: Schematic layout example for the passenger security screening [64] Departure lounge Once the passengers have past the security screening facilities and access the secured airside of the terminal, they arrive at the departure lounge. At this point, the level of stress of the passenger is at maximum and, as a consequence, it is of paramount importance to design the departure lounge in such a way that it transmits calmness to the passenger. Departure lounges should be an ample, unobstructed and naturally lit space which allows the passengers direct eyesight to the aircraft. The paths to the boarding gates should be intuitive and clearly indicated. As regards to the passenger’s travel experience, the departure lounge represents perhaps the most important space of the airport, considering that they might need to spend a great amount of time in it until their flight arrives. For this reason, it should be provided with entertainment, commercial and restful facilities. The facilities that the departure lounge should or could have are listed below: •Seating. •Restaurants, shops and duty-free businesses. •Flight information displays. •Airline information desks. •Toilet facilities. •Public address and voice alarm systems. •Help desks. •Child play areas. •Entertainment facilities. •Religious facilities. TFG Report Page 114 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE 6.6.2 Arrivals The arriving passenger flow consists of the following steps: 1. When the passenger leaves the aircraft, an arrival corridor is provided for the passenger, who will head to the baggage claim. 2. If required, an immigration control will be applied. 3. Next, the passenger arrives to the baggage claim halls, where the luggage is picked up. 4. If required, a customs control will be applied. 5. Then, the passenger enters accesses the arrivals hall, where the security-restricted zone ends and the public landside zone begins. 6. Finally, the passenger can head for the forecourt to leave the airport by any transportation mean provided. Arrivals corridors Arrival corridors are the first infrastructure that an arriving passenger sees when leaves an aircraft and enters the terminal building. Independently from the length of the flights, passengers could be tired from all the stress to which they have undergone and, as a consequence, the arrival corridors must be designed in such a way that they transmit a welcoming and agreeable feeling. Arrival corridors must be designed to be wide, ample, unobstructed and with as much natural light as possible. Other facilities that must be provided are seating, toilets and wayfinding and signage to intuitively direct the arriving passengers towards the next facilities: the immigration control and the baggage claim. Arrivals requirements: immigration When arriving to the immigration control, passports or other documents are verified so as to be sure that everything is under control. The process is very similar to the emigration process, which has already been previously explained. Furthermore, health controls can be used. Further design facilities are the location of control desks and offices for interviewing rooms. Baggage claim The baggage claim is a process in which the passenger can pick up the checked baggage, which was transported in the hold of the aircraft, after the flight. The baggage claim hall will be unobstructed and with ample circulation spaces. A signage system will be necessary in order to identify which belt will provide the checked baggage of the corresponding arrival flight. Other facilities that need to be in the baggage claim hall are information points, lost baggage claim, baggage enquiry desks, trolleys and trolley parking spaces, seating and toilets. Checked baggage is delivered by means of a loop baggage claim belt, which is a system formed by four elements, as seen in Figure 73: •The baggage claim unit, which is the facility that brings the checked baggage. •The retrieval area, which is the space intended for people to pick up their luggage. •The peripheral area, which is the space used to wait, park the trolley and enter and exit the retrieval area. •The central circulation corridor, which goes from entrance to exit and which will be provided for the passengers that do not need to pick up any checked baggage. TFG Report Page 115 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE Figure 73: Bagage claim system [64] The dimensions shown in Figure 73 may vary depending on the level of service offered and the static capacity of the unit. Customs processes The government of the country where the airport is located forces the airport authorities to perform customs controls for international passengers. This means that passengers and their luggage will be checked for imported or exported goods for which they need to pay duties or fees by law. The customs control should be centralised with all the other control authorities on the arrival journey after the baggage claim hall so as to minimise the disruption on the arriving passenger flow. The customs processes usually consists in two channels: the red channel, which is intended for passengers that have articles to declare, and the green channel, which is intended for passengers that do not have articles to declare. Random inspections of passengers are usual and investigation rooms are required for the customs processes. Arrivals hall The arrivals hall is the next step of the passenger flow after the baggage claim hall and the customs controls. It consists of a waiting area for visitors that are waiting for arriving passengers. It should be designed in such a manner that arriving passengers feel welcomed and invited. Furthermore, the waiting for the visitors should be pleasant and enjoyable. Natural lights is a very important factor and eyesight towards the landside environment is strongly recommended. Other facilities than can be found at the arrivals hall are: commercial concessions, meeting points, seating, toilets, wayfinding and signage and dynamic flight information displays. Arrivals forecourt The arrivals forecourt is the limit between the terminal building and the landside public traffic network. The function of the arrivals forecourt is to allow arriving passengers and visitors to be picked up and to head for their next destination. TFG Report Page 116 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE 6.6.3 Transfers The new airport is not intended for transfer flights, seeing that these were planned to remain at the Airport of Munich, as already stated before. Nevertheless, a certain degree of transfer passengers might occur and some considerations must be taken when addressing this type of flights. Based on the fact that the number of transfer passengers is low, the transfer process can and will take place on the landside, which consists in the following process: 1. Passengers with checked luggage pick it up and exit to the landside arrivals. Those who do not have checked luggage directly go the landside arrivals. 2. Then, passengers go to the departure halls and follow the very same process as any conventional departing passenger. Therefore, when a transfer passenger arrives to the airport terminal, they continue their journey to their next destination without leaving it. This process must be as smooth and simple as possible. 6.7 Other considerations and facilities 6.7.1 Security requirements in airport terminal It is of paramount importance to have security measure at airports with the objective of minimising the risk of a security threat to an aircraft, to passenger and to the airport itself. For this reason, passengers and their luggage are security-controlled within the terminal building. In terms of security, three types of zones can be defined: •Public access zones, which is not security controlled. •Security-restricted access zones, which is not public and people can only enter if proper authentication such as a boarding pass or a staff badge is provided. •Security-controlled access zones, which are located at the departure areas and their objective is to reduce threats to aircraft. Passengers, staff, luggage and other elements are security-screened. When planning an airport, the access to the airside areas by staff, authorised persons and vehicles must be reduced to the minimum number. 6.7.2 Commercial and retail businesses Nowadays, air travel is stressful to people. From the moment they leave home their level of anxiety increases and only when they enter the secure airside area of the terminal it decreases again and passengers can relax. To ease this process, commercial, retail and food and beverage businesses are offered while waiting for their flight. The airport takes advantage of these businesses, seeing that the perception of quality and travel experience of the passenger is enhanced. Furthermore, the civil aviation community can profit from the revenue that flows from this businesses, which are a significant amount of the total revenue. Considering that the advantages that commercial and retail businesses offer, they must be integrated in the initial planning and designing of the passenger terminal. It is usual to intend from 15% to 20% of the terminal area to commercial and retail businesses. The area per passenger is generally 4.8m2for retail and 3.6m2for food and beverage and their proportion is 60% and 40%, respectively. As regards to the distribution between the landside and the airside, about 15% of the businesses are located on the landside whereas 85% are located on the airside. TFG Report Page 117 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE There are two types of distributions of commercial and retail businesses: •Centralised, which consists in concentrating all the shops in a single location (usually after the security screening area) in order to maximise foot traffic. Short-cuts must be offered for passenger that need to move quickly to the boarding gates or for frequent flyers who are already familiar with the shops. •Distributed, which includes a series of businesses close to the boarding gates. This is reassuring for passenger and, as a consequence, they will feel more relaxed and eager to shop and eat until their flight begins boarding. Regarding dimensions, public seating should allow between 1m2and 1.5m2per passenger and at restaurants a minimum of 2m2. Circulation space should range from 20% to 25% percent of the total floor area and these zones should have a minimum width of 10 m. 6.7.3 Access to air travel for person with reduced mobility People with reduced mobility have the right and should be able to use an airport as any other people without movement impairs. Therefore, their special needs must be taken into account and they will be offered assistance and the best possible comfort to them. So as to achieve a user-friendly environment for people with reduced mobility, the airport must take into account their necessities from the beginning of the planning and designing phases. The result has to be that people with reduced mobility must be able to easily and independently navigate through the airport. 6.7.4 Toilet provisions Toilet provision are extremely important at an airport. There must be sufficient toilets for both passengers and staff so as to allow temporary closure of some of them in order to be cleaned. In terms of level of service and passenger experience, toilets play an important role. 6.7.5 Passenger wayfinding and signage There are two systems that welcome and help the passenger to better understand the airport from the point of view of both navigation and public image: •Wayfinding system, which helps passengers to navigate from point A to point B. •Signage system, which consists of visual or contextual aids that provide information about navigation and wayfinding. The objective is to improve the experience of the user and the level of service, seeing that the nowadays airport are more and more complex. 6.8 Capacity equations for sizing the terminal building facilities Although simulation modelling is recommended when designing ans sizing a new terminal building, capacity equations are cheaper and valid for a predesign. Capacity equations are a useful method to estimate the order of magnitude of the capacity of every facility when performing a preliminary planning of the passenger terminal building and specific information is absent. The following processes have been extracted from [64]. As regards to the sizing of the passenger processing facilities, it is strictly dependant on the number of passengers during the peak period, the proportion of premium passengers, the processing rate, the available area per person and the maximum queuing time. Furthermore, the peak period is not uniformly distributed during an hour, but is has a varying TFG Report Page 118 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE profile due to the nature of passenger arrival. The peak may occur during shorter periods of time and, as a consequence, the peak 30-minute volume is used for calculations. It is of paramount importance to note that all the variables used in the following calculations correspond to an optimum level of service. This can be verified by comparing these numbers with those of the table from Figure 69. 6.8.1 Sizing of self-service kiosks The sizing of the self-service kiosks will be done by using the variables in Table 35. Table 35: Acronyms, definitions and values of the data used to size the self-service kiosks Acronym Definition Value SSIApproximate number of self-service kiosks Output PHP Originating peak hour passengers 2,000 CF Correction factor for demand variability 1.21 PK Peak 30-minute factor (in % of PHP)75% SSR Ratio of passengers using self-service kiosks 84% [65] PT Process time per passenger at self-service kiosk (in seconds) 120 MQT Maximum queuing time (in minutes) 3 AArea required for the self-service kiosks Output SS Total number of self-service kiosks Output SSAArea occupied by a single self-service kiosk22 0.36 AA Adjustment area for a single self-service kiosk2324 3 QMAX Maximum number of passengers waiting in queue Output QF QMAX correction factor 0.120 SP Space per person (in m2)1.5 CAF Circulation area factor (in %) 35% Having explained all the variables, the calculation process can begin: 1. Calculate the approximate number of self-service kiosks using the equation below. SSI=PHP ·PK ·SSR ·PT 60 ·(30 + MQT) SSI=2,000 ·0.75 ·0.84 ·120 60 ·(30 + 3) SSI= 76.36 ≈77 kiosks 2. Adjust requirements to account for variability in passenger arrival distribution within the peak period and in processing time using the equation below. SS =SSI·CF SS = 77 ·1.21 SS = 93.17 ≈94 kiosks 22Obtained from typical dimensions. 23To account for additional area needed for layout. 24Obtained from typical dimensions. TFG Report Page 119 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE Where CF is obtained from Table 36. Table 36: Correction factor (CF ) for demand variability (when less than 30-minute peak) [64] Correction factor (CF) for demand variability MQT CF 3 1.21 4 1.22 5 1.15 10 1.06 15 1.01 20 1.00 25 1.00 30 1.00 The smaller the MQT is, the greater the variability in demand over the period analysis. 3. Calculate the maximum number of passengers in queue using the equation below. QMAX =QF ·Peak 30 −min =QF ·P HP ·PK ·SSR QMAX = 0.120 ·2,000 ·0.75 ·0.84 QMAX = 151.2≈152 passengers Where QF is obtained from Table 37. Table 37: QMAX calculation factor (QF) [64] QMAX calculation factor (QF) MQT QF 3 0.120 4 0.151 5 0.183 10 0.289 15 0.364 20 0.416 25 0.453 30 0.495 4. Calculate the area required for the self-service process using the equation below. A= (SS ·SSA·AA +QMAX ·SP)·(1 + CAF) A= (94 ·0.36 ·3 + 152 ·1.5) ·(1 + 0.35) A= 444.85 ≈445 m2 The adjustment factor is used for the kiosk footprint, which is relatively small. As a consequence, it can not be distributed as conventional desks, considering that space is required around it for passengers to comfortably operate it. The variable AA depends on the layout and configuration of the kiosks. The variable CAF is used to provide additional area to walk through the processing area. TFG Report Page 120 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE 6.8.5 Sizing of passenger security screening facilities The sizing of the passenger security screening facilities will be done by using the variables in Table 41. Table 41: Acronyms, definitions and values of the data used to size the passenger security screening facilities Acronym Definition Value PK30MIN Throughput 30-minute demand Output CD Number of service desks open 105 PTCD Process time for service at desks (in seconds) 120 CF Correction factor for demand variability 1.15 BD Number of baggage drop positions open 76 PTBD Process time at baggage drop (in seconds) 110 PHP Originating peak hour passengers 2,000 PK Peak 30-minute factor (in % of PHP)0.75 CR Ratio of passengers using traditional check-in facilities 0.1 BR Ratio of passengers using baggage drops 0.6 PD Number of departure passport control desks 15 PTPD Process time for departure passport control (in seconds) 60 SECIApproximate number of security lanes Output PTSEC Process time per passenger at security (in seconds) 30 MQT Maximum queuing time (in minutes) 5 AArea required for the security checkpoint facility Output SEC Total number of security lanes Output SECDDepth of one security lane (in meters)33 6 SECWWidth of one security lane (in meters)34 3 QMAX Maximum number of passengers waiting in queue Output QF QMAX correction factor 0.183 SP Space per person (in m2)1 WCorridor width behind lanes (in meters) 3.5 Having explained all the variables, the calculation process can begin: 1. Calculate the demand from the previous processor. If departure emigration facility exists and is located prior to the security checkpoint, the equation below must be used. PK30MIN =CD ·60 PTCD ·30 +BD ·60 PTBD ·30 +PHP ·PK ·(1 −(CR +BR)) PK30MIN =105 ·60 120 ·30 +76 ·60 110 ·30 + 2,000 ·0.75 ·(1 −(0.1+0.6)) PK30MIN = 453.132 ≈454 passengers 2. Calculate the approximate number of security lanes using the equation below. SECI=PK30MIN ·PTSEC 60 ·(30 + MQT) 33Obtained from typical dimensions. 34Obtained from typical dimensions. TFG Report Page 127 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE SECI=454 ·30 60 ·(30 + 5) SECI= 6.486 ≈7lanes 3. Adjust requirements to account for variability in passenger arrival distribution within the peak period and in processing time using the equation below. To calculate CF, use Table 36. SEC =SECI·CF SEC = 7 ·1.15 SEC = 8.05 ≈9lanes 4. Calculate the maximum number of passengers in queue using the equation below. To calculate QF, use Table 37. QMAX =QF ·PK30MIN QMAX = 0.183 ·454 QMAX = 83.082 ≈84 passengers 5. Calculate the area required for the security checkpoint using the equation below. A=SEC ·SECD·SECW+QMAX ·SP +SEC ·SECW·W A= 9 ·6·3 + 84 ·1+9·3·3.5 A= 340.5≈341 m2 This area includes the processing area, the queuing area and the circulation area. 6.8.6 Sizing of boarding gates lounges facilities The sizing of boarding gates lounges is influences by two factors: the area that commercial concessions occupy and the seating requirements, considering that the people that need to be accommodated in the aircraft must also fit into the boarding gates lounges. For a pier (finger) terminal concept, the sizing needs to determine the length and depth of the pier. The sizing of the boarding gates lounges facilities will be done by using the variables in Table 42. Table 42: Acronyms, definitions and values of the data used to size the boarding gates lounges facilities Acronym Definition Value A(1/2) Area of the gate lounge (in m2)35 Output AS(1/2) Total number of seats offered by all aircraft36 Output LF Aircraft load factor 0.775 SR Seat ratio 0.7 SRFAdjustment factor to seat ratio 0.1 GF Open gate lounge factor 0.9 S(S/ST )Space per seated/standing person (in m2)1.5/1 XAdditional space ratio to account for boarding operation in % of global gate area 0.15 GLD(1/2) Gate lounge depth (in meters)37 Output PLPier length (in meters) Output PWPier width (in meters) Output WWidth of the circulation corridor including moving devices (in meters) 10 TFG Report Page 128 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE Having explained all the variables, the calculation process can begin: 1. Calculate the pier length. If there are 6type V aircraft stands on one side and and 7type VII on the other side, the length will be determined by the type VII aircraft stands. If its width is 40 m, the length of the pier will be PL= 7 ·40 = 280 m 2. Determine the maximum seating capacity offered by the aircraft serving one side of the pier. Then repeat the operation for the other side of the pier. The maximum seating capacity for each side of the pier are 159 for type VII aircraft and 202 for type V aircraft. Thus: AS(1) = 7 ·159 = 1,113 seats AS(2) = 6 ·202 = 1,212 seats 3. Calculate the area required for the gate lounge area using the equation below. Repeat the calculation for the other side of the pier. A(1) = (1 + X)·AS(1) ·LF ·SR ·(1 + SRF)·GF ·SS+AS(1) ·LF ·(1 −SR)·SST A(1) = (1 + 0.15) ·(1,113 ·0.775 ·0.7·(1 + 0.1) ·0.9·1.5+1,113 ·0.775 ·(1 −0.7) ·1) A(1) = 1,328.732 ≈1,329 m2 A(2) = (1 + X)·AS(2) ·LF ·SR ·(1 + SRF)·GF ·SS+AS(2) ·LF ·(1 −SR)·SST A(2) = (1 + 0.15) ·(1,212 ·0.775 ·0.7·(1 + 0.1) ·0.9·1.5+1,212 ·0.775 ·(1 −0.7) ·1) A(2) = 1,446.921 ≈1,447 m2 The variable SRFtakes into account the loss of capacity due to passengers who put their belongings on a seat next to them and, as a consequence, another passenger cannot use it. The variable GFconsiders the increase in capacity offered by the terminal concept. The variable Xaccounts for the boarding process and includes the areas involved. 4. Calculate the depth of the gate lounge using the equation below. Repeat the calculation for the other side of the pier. GLd(1) =A(1) PL GLd(1) =1,329 280 GLd(1) = 4.746 ≈5m GLd(2) =A(2) PL 35Under an open-gate configuration, serving one or two sides of the pier (1/2). 36Serving one or two sides of the pier (1/2). 37Of one or two sides of pier (1/2). TFG Report Page 129 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE GLd(2) =1,447 280 GLd(2) = 5.168 ≈6m 5. Calculate the total pier width using the equation below. PW=GLd1+GLd2+W PW= 5 + 6 + 10 PW= 21 6.8.7 Sizing of immigration facilities The sizing of the immigration facilities will be done by using the variables in Table 43. Table 43: Acronyms, definitions and values of the data used to size the immigration facilities Acronym Definition Value PCIApproximate number of arrival passport control desks Output PHP Terminating peak hour passengers 1,750 CF Correction factor for demand variability 1.06 PK Peak 30-minute factor (in % of PHP)0.75 PT Process time per passenger at arrival passport control (in seconds) 60 MQT Maximum queuing time (in minutes) 10 AArea required for the arrival passport control facility Output PC Total number of arrival passport control desks Output PCDDepth of one arrival passport control booth (in meters)38 3 PCWWidth of one arrival passport control booth (in meters)39 2.2 QMAX Maximum number of passengers waiting in queue Output QF QMAX correction factor 0.289 SP Space per person (in m2)1 WCorridor width behind desks (in meters) 3.5 Having explained all the variables, the calculation process can begin: 1. Calculate the number of desks using the equation below. PCI=PHP ·P K ·P T 60 ·(30 + MQT) PCI=1,750 ·0.75 ·60 60 ·(30 + 10) PCI= 32.812 ≈33 desks 2. Adjust requirements to account for variability in passenger arrival distribution within the peak period and in processing time using the equation below. To calculate CF, use Table 36. PC =PCI·CF 38Obtained from typical dimensions. 39Obtained from typical dimensions. TFG Report Page 130 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE PC = 33 ·1.06 PC = 34.98 ≈35 desks 3. Calculate the maximum number of passengers in queue using the equation below. To calculate QF, use Table 37. QMAX =QF ·Peak 30 −minute =QF ·P HP ·PK QMAX = 0.289 ·1,750 ·0.75 QMAX = 379.313 ≈380 passengers 4. Calculate the area required for the arrival immigration process using the equation below. A=PC ·PCD·P CW+QMAX ·SP +P C ·PCW·W A= 35 ·3·2.2 + 380 ·1 + 35 ·2.2·3.5 A= 880.5≈881 m2 6.8.8 Sizing of baggage claim facilities When sizing the baggage claim facilities, apart from the physical devices, it is important to coordinate the arrival of bags on the carousel with the arrival of the passengers. If the baggage arrives too early, their accumulation will require more devices, whereas if passengers arrive too early, their accumulation will require more space around the devices. The coordination is an ideal situation which is difficult to adjust. So as to consider all the situations, the capacity equation will suppose a maximum accumulation of bags and passengers. The sizing of the baggage claim facilities will be done by using the variables in Table 44. Table 44: Acronyms, definitions and values of the data used to size the baggage claim facilities Acronym Definition Value CL Carousel frontage passenger line up (in meters) Output PAX Number of passengers in the design aircraft 202 SP Claim frontage per passenger (in meters) 0.85 PR Ratio of passengers collecting bags 0.5 RR Recirculation rate 0.5 BC Number of baggage claim units Output PHP Peak hour number of terminating passengers 1,750 PProportion of passengers arriving by narrow body aircraft 1 OT Average claim device occupancy time per aircraft (in minutes) 20 AC Area of a carousel for the aircraft Output CWCarousel width (in meters) 6 SB Side buffer to allow passenger movement around the reclaim belt40 5 EB End buffer to allow passenger movement around the reclaim belt41 10 AArea of the baggage reclaim hall (in m2) Output Having explained all the variables, the calculation process can begin: 40Total meters allowing for both sides. 41Total meters allowing for both sides. TFG Report Page 131 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE 1. Determine the claim frontage length required to accommodate passengers from a specific aircraft served by the reclaim area by using the equation below. It is recommended to accommodate even the largest flight on one belt so as to avoid splitting a flight onto two carousels. CL =PAX ·SP ·P R ·RR CL = 202 ·0.85 ·0.5·0.5 CL = 42.925 ≈43 m 2. Determine the number of baggage claim devices by using the equation below. BC =PHP ·P·OT 60 ·PAX BC =1,750 ·1·20 60 ·202 BC = 2.888 ≈3devices 3. Determine the baggage claim area by using the equation below. AC = (CW+SB)·CL 2+EB AC = (6 + 5) ·43 2+ 10 AC = 346.5≈347 m2 4. Calculate the total area by using the equation below. A=AC ·BC A= 347 ·3 A= 1,041 m2 6.8.9 Sizing of customs facilities The sizing of the customs facilities will be done by using the variables in Table 45. Table 45: Acronyms, definitions and values of the data used to size the customs facilities PI Number of primary inspection booths (single units) Output PHP Terminating peak hour passengers 1,750 PK Peak 30-minute factor (in % of PHP)0.75 PT (PI/XR) Process time per passenger at primary inspection booth and x-ray facility (in seconds) 10/20 XR Number of x-ray units Output IR Ratio of passengers to be inspected 0.1 PIDDepth of one primary inspection booth lane 3 PIWWidth of one primary inspection booth lane 2.2 MQT (PI/XR) Maximum queuing time at primary inspection booth and at x-ray facility (in minutes) 5/3 A (PI/XR) Area required for the primary inspection booth and for the x-ray facility Output XRDDepth of one x-ray lane (in meters) 4 XRWWidth of one x-ray lane (in meters)42 3 QMAX Maximum number of passengers waiting in queue Output QF (PI/XR) QMAX correction factor 0.183/0.120 CF (PI/XR) Correction factor for demand variability 1.15/1.21 SP Space per person (in m2)1.3 WCorridor width before and behind desks (in meters) 3 TFG Report Page 132 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE Having explained all the variables, the calculation process can begin: 1. Calculate the number of customs check positions using the equation below. It is considered that all passengers go through this facility when in place. PI =PHP ·P K ·P TP I 60 ·(30 + MQTP I) PI =1,750 ·0.75 ·10 60 ·(30 + 5) PI = 6.25 ≈7booths 2. Calculate the number of x-ray units required using the equation below. To calculate CF, use Table 36. XR =CFXR ·P HP ·PK ·IR ·PTXR 60 ·(30 + MQTXR) XR = 1.21 ·1,750 ·0.75 ·0.1·20 60 ·(30 + 3) XR = 1.604 ≈2units 3. Calculate the maximum number of passengers in the queue using the equation below. To calculate QF, use Table 37. QMAXP I =QFP I ·Peak 30 −min =QFPI ·PHP ·PK QMAXP I = 0.183 ·1,750 ·0.75 QMAXP I = 240.188 ≈241 passengers QMAXXR =QFXR ·Peak 30 −min =QFXR ·PHP ·PK ·IR QMAXXR = 0.120 ·1,750 ·0.75 ·0.1 QMAXXR = 15.75 ≈16 passengers 4. Calculate the area required for the customs check facility and for the x-ray process using the equations below. API =PI ·PID·PIW+QMAXP I ·SP +PI ·PI ·PIW·W API = 7 ·3·2.2 + 241 ·1.3+7·2.2·3 API = 405.7≈406 m2 AXR =XR ·XRD·XRW+QMAXXR ·SP +XR ·XRW·2·W AXR = 2 ·4·3 + 16 ·1.3+2·3·2·3 AXR = 80.8≈81 m2 42Includes x-ray equipment, circulation and operator position. TFG Report Page 133 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE 6.8.10 Sizing of arrivals hall facilities The sizing of the arrivals hall facilities will be done by using the variables in Table 46. Table 46: Acronyms, definitions and values of the data used to size the arrivals hall facilities Acronym Definition Value PPerson present in arrivals hall Output PHP Terminating peak hour passengers 1,750 T (P/V) Dwell time for passengers/visitors (in minutes) 5/15 VR Ratio of visitors per passengers 1 AArea of the arrival hall Output SR Seat ratio 0.2 SP (S/ST) Space per seated/standing person 1.7/1.2 Having explained all the variables, the calculation process can begin: 1. Calculate the number of people present in the arrivals hall using the equation below. P=PHP ·TP+PHP ·V R ·TV 60 P=1,750 ·5+1,750 ·1·15 60 P= 583.3≈584 people 2. Calculate the area to provide in the arrivals hall using the equation below. A=P·SR ·SPS+P·(1 −SR)·SPST A= 584 ·0.2·1.7 + 584 ·(1 −0.2) ·1.2 A= 759.2≈760 m2 6.8.11 Sizing of the commercial concessions The total area required for the above-mentioned facilities is 11,725 m2. Considering that the commercial concessions of the airport must occupy around 15% of the terminal, its area will be around 2,070 m2. Of this area, 60% will be intended to retail concessions and the other 40% will be intended to food and beverage. The result is 1,242 m2with 4.0m2 per passenger and 828 m2with 3.6m2per passenger, respectively. Of these areas, 15% will be located on the landside and 85% will be located on the airside. As a result, 186 m2of the retail concessions will be located on the landside and 1,056 m2 will be located on the airside, whereas 124 m2of the food and beverage concessions will be located on the landside and 704 m2will be located on the airside. Regarding the seating at restaurants, 2m2per person will be reserved. 6.8.12 Summary of the sizing of facilities The following list summarises the results from the previously made sizing of facilities. It is of paramount importance to note that all the variables correspond to an optimum level of service. •Self-service facilities. TFG Report Page 134 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE –Number of self-service kiosks: 95. –Maximum queuing time: 3minutes. –Maximum number of passengers in queue: 152 passengers. –Area required: 445 m2. –Space per passenger: 1.5m2/passenger. –Process time: 120 s. –Ratio of passengers using self-service kiosks: 0.84. •Baggage drop facilities. –Number of baggage drop positions for Economy Class: 56. –Number of baggage drop positions for Business Class: 6. –Number of baggage drop positions for First Class: 3. –Maximum queuing time for Economy Class: 10 minutes. –Maximum queuing time for Business Class: 5minutes. –Maximum queuing time for First Class: 3minutes. –Maximum number of Economy Class passengers in queue: 328 passengers. –Maximum number of Business Class passengers in queue: 17 passengers. –Maximum number of First Class passengers in queue: 5passengers. –Area required for Economy Class: 1,155 m2. –Area required for Business Class: 104 m2. –Area required for First Class: 48 m2. –Total area required: 1,306 m2. –Space per passenger in Economy Class: 1.3m2/passenger. –Space per passenger in Business Class: 1.5m2/passenger. –Space per passenger in First Class: 1.8m2/passenger. –Ratio of Economy Class passengers: 0.9. –Ratio of Business Class passengers: 0.07. –Ratio of First Class passengers: 0.03. –Process time for Economy Class passengers: 110 s. –Process time for Business Class passengers: 100 s. –Process time for First Class passengers: 90 s. –Ratio of passengers using traditional check-in facilities: 0.16. •Traditional check-in facilities. –Number of baggage drop positions for Economy Class: 11. –Number of baggage drop positions for Business Class: 2. –Number of baggage drop positions for First Class: 2. –Maximum queuing time for Economy Class: 10 minutes. –Maximum queuing time for Business Class: 5minutes. –Maximum queuing time for First Class: 3minutes. TFG Report Page 135 of 167
UPC-ESEIAAT 6 DESCRIPTION OF THE LANDSIDE –Maximum number of Economy Class passengers in queue: 63 passengers. –Maximum number of Business Class passengers in queue: 4passengers. –Maximum number of First Class passengers in queue: 1passengers. –Area required for Economy Class: 225 m2. –Area required for Business Class: 32 m2. –Area required for First Class: 28 m2. –Total area required: 285 m2. –Space per passenger in Economy Class: 1.3m2/passenger. –Space per passenger in Business Class: 1.5m2/passenger. –Space per passenger in First Class: 1.8m2/passenger. –Ratio of Economy Class passengers: 0.9. –Ratio of Business Class passengers: 0.07. –Ratio of First Class passengers: 0.03. –Process time for Economy Class passengers: 110 s. –Process time for Business Class passengers: 100 s. –Process time for First Class passengers: 90 s. –Ratio of passengers using traditional check-in facilities: 0.16. •Emigration facilities. –Number of emigration control desks: 15. –Maximum queuing time: 5minutes. –Maximum number of passengers in queue: 84 passengers. –Area required: 299 m2. –Space per passenger: 1m2/passenger. –Process time: 60 s. –Ratio of passengers using baggage drop facilities: 0.6. –Ratio of passengers using traditional check-in facilities: 0.1. •Passenger security screening facilities. –Number of security screening lanes: 9. –Maximum queuing time: 5minutes. –Maximum number of passengers in queue: 84 passengers. –Area required: 341 m2. –Space per passenger: 1m2/passenger. –Process time: 30 s. •Boarding gates lounges facilities. –Space per seated passenger: 1.5m2. –Space per standing passenger: 1m2. –Proportion of seated occupants: 0.7. –Pier width: 21 m. TFG Report Page 136 of 167
UPC-ESEIAAT 8 ADDITIONAL AIRPORT FACILITIES AND INFRASTRUCTURES Figure 78: Minimum usable amounts of extinguishing agents [43] There are three levels of foam meeting performance: A, B and C, being A the best one. Response time The response time is the time between the initial call to the rescue and firefighting service and the time when the first vehicle is in position to apply the extinguishing agents. The rescue and firefighting service should arrive to any point of the operational runway in a response time not exceeding two minutes and to any point of the movement area in less than three minutes, in optimum visibility and surface conditions. Under the same response time, the rescue and firefighting service shall be ready to apply the extinguishing agents at a rate of at least 50% of the discharge rate specified in Figure 78. Fire stations The rescue and firefighting vehicles will be housed in a fire station and, when the response time cannot be achieved from a single station, a satellite fire station will be provided. Communication and alerting systems A discrete communication system will be provided between a fire station and the control tower, any other fire station and firefighting vehicles. Number of rescue and firefighting vehicles The minimum number of rescue and firefighting vehicles in the airport will be dictated by the table of Figure 79. In the case of the new airport, where the aerodrome category is 7, there must be a minimum of 2vehicles. TFG Report Page 143 of 167
UPC-ESEIAAT 8 ADDITIONAL AIRPORT FACILITIES AND INFRASTRUCTURES Figure 79: Tabulation of the rescue and firefighting vehicles as a function of aerodrome category [43] Personnel and rescue equipment All the personnel of the rescue and firefighting service must be adequately trained to perform their duties in the most efficient manner. The training includes human performance and team coordination. As for the rescue equipment, protective clothing and respiratory equipment will be provided so as to allow the personnel to perform their tasks in the most effective way. See the Drawings document to know where the rescue and firefighting services are located. 8.2 De-icing and anti-icing facilities De-icing and anti-icing facilities must be provided at an airport where icing conditions could occur. The distribution of these facilities can be: •Centralised, which is located adjacent to terminals. This type of de-icing and antiicing facility is acceptable as long as it does not cause excessive delays, congestion and long waiting periods and if the taxiing time from the terminal to the runway is less than the hold-over time of the fluid used. •Remote or off-gate, which is located along a taxiway. This type of de-icing and anti-icing facility allows a better usage of aircraft stands and, as a consequence, the taxiing time from the facility to the runway is shorter and thus the hold-over time of the fluid is ensured. De-icing and anti-icing facilities along a taxiway may cause queuing of aircraft and thus there should be some kind of bypass as shown in Figure 80. Figure 80: Minimum separation distance on a de-icing or anti-icing facility [43] TFG Report Page 144 of 167
UPC-ESEIAAT 8 ADDITIONAL AIRPORT FACILITIES AND INFRASTRUCTURES Moreover, remote facilities allow a better recollection of the de-icing and anti-icing fluid that run-off the aircraft so as to safely dispose it than aircraft stands. For the sake of simplicity and to not contaminate the apron system, remote de-icing and anti-icing facilities will be used. See the Drawings document to know where the de-icing and anti-icing facilities are located. Size of de-icing and anti-icing facilities and number of pads The size of a de-icing and anti-icing facility and the number and size of pads that it requires depends on: •The meteorological conditions. Airports where it snows or freezes habitually require a greater number of de-icing and anti-icing pads so as to avoid unnacceptable delays. •The aircraft size and type of aircraft to be treated. Obviously, narrow-body aircraft requires less time than wide-body aircraft and fuselage-mounted engines require more time than wing-mounted engines. •The method of application of the de-icing and anti-icing fluid: one-step or two-step de-icing and anti-icing procedure. To achieve a greater degree of flexibility and avoid great occupancy times, the number of de-icing and anti-icing pads will be based on the two-step procedure. As a consequence, the maximum aircraft departure flow rates affects are minimised. •The type and capacity of the dispensing equipment used. Mobile de-icing and antiicing equipment with small tank capacities and requiring extended fluid heating times increase the time of treatment and negatively affects the departure flow rate. •The departures flow rate. The number of aircraft that require such treatment should be equal to the number of take-offs than can be assimilated so as to avoid delays and airport congestion. An estimation of the total size required for the facility could be done from the number of aircraft that require treatment at a given time. As for the aircraft de-icing and anti-icing pad, it consists of an inner area intended to park the aircraft that will be treated and and outer area intended for the mobility of the de-icing and anti-icing mobile equipment. Its size of will be equal the aircraft stand of the restrictive aircraft (the Airbus A321 in the present case) plus a margin 3.8mfor ground vehicles plus the minimum clearances that apply for aircraft stands to avoid overlapping. Other considerations about de-icing and anti-icing facilities The excess of de-icing and anti-icing liquid that runs off an aircraft supposes a risk of contamination of ground water and thus it must be recollected and treated before getting rid of it. As a consequence, it is of paramount importance to use the bare minimum quantity. Moreover, these fluids have a negative effect on the friction characteristics of the pavement. 8.3 Control tower The air traffic control services are provided from the control tower and thus it is an element of paramount importance for an airport. The main objectives of the control tower is to order the air traffic and the traffic on the movement area in a smooth, efficient and rapid way, with the purpose of maximising the performance of the airport infrastructures. Thus, all the required authorisations for any kind of operation are issued from the control tower. It is obvious that the visibility and communication conditions from the control tower must be optimum. To achieve these conditions, some equipment is necessary: a radio TFG Report Page 145 of 167
UPC-ESEIAAT 8 ADDITIONAL AIRPORT FACILITIES AND INFRASTRUCTURES communications system, a telephonic system, an integrated-data meteorologic system and a monitoring and control graphic system, among other systems. The sizing of the different parts of a control tower depends on the traffic that the airport has. Two of the most important factors when it comes to designing a control tower are the location and the altitude. The objective is always the same: to fully visualise the movement area that needs control while not becoming a hindrance for the air traffic and the safety of operations. The optimum location of a control tower will be that which provides a panoramic view of the movement area for the controller. It is also important to not locate the control room in front of the east or west direction so as to avoid sunlight blinding. See the Drawings document to know where the control tower is located. TFG Report Page 146 of 167
UPC-ESEIAAT 9 ENVIRONMENTAL AND SOCIAL IMPACT STUDY 9 Environmental and social impact study This section’s contents are based on the Airport Planning Manual - Part 2: Land Use and Environmental Management [67]. It is well known that the public concern relative to the protection of the natural environment has been increasing during the past years. Special attention has been given to the impact of transportation and, as a consequence, to air transportation. An airport will inevitably generate pollution within its own limits but also in its environment, which has an effect not only on ecology but also on human health. Therefore, this is a matter of environmental and social security. An adequate planning of the airport project focused on the compatibility between the airport and its environment is essential so as to minimise the environmental and social negative impact. With the objective of providing the best possible conditions for the airport, the community and the ecology of the environment, the pollution sources and land use managements must be studied. To ensure the compatibility between the airport and the ecology and the community, the planning of the airport project must involve local organisations that will help minimise the environmental and social impact. Pollution prevention is defined as “the use of materials, processes or practices that reduce or eliminate the creation of pollutants and wastes at the source” [67]. Thus, environmental management measures must be implemented at airports and its surroundings to ensure a minimum impact on the environmental and social aspects. 9.1 Environmental impact associated with aviation activities This subsection describes the environmental impact related to the aviation industry. 9.1.1 Aircraft noise and its management The beginning of the use of jet aircraft in the civil aviation industry supposed a before- and-after in terms of aircraft noise, which became the most important local environmental impact of civil aviation. There are four ways with which it is possible to combat aircraft noise levels: •Reduction at source, which consists in reducing the aircraft engine noise. As a result, aircraft are becoming more and more quieter •Land-use planning and management, which consists in minimising the population affected by aircraft noise by introducing land-use zoning around airports, which are zones over which residential development is not allowed. By doing so, the possible future expansions of the airport are not limited, considering that the land is “reserved” from the beginning. •Noise abatement operational procedures, which consist in reducing the perceived noise during aircraft operations at a considerably low cost. Natural and artificial acoustical barriers and sound insulation in building are examples of noise abatement operational procedures. Moreover, a proper position of the airport building can contribute to noise reduction. •Operating restrictions, which consist in the restriction of operations during night time, for certain aircraft types and for a certain number of aircraft movements. TFG Report Page 147 of 167
UPC-ESEIAAT 9 ENVIRONMENTAL AND SOCIAL IMPACT STUDY 9.1.2 Air quality and its management Air pollution consists in the presence of air contaminants in the air that affect the air quality. The effects of the contaminants are varied [67]: •Degradation of the air quality from its normal state. •Endangerment of the health, safety and welfare of persons, fauna and flora. •Interference with normal enjoyment of life or property. •Damage to property. While a minimum degree of air pollution in an airport is inevitable, it should not be excessive. The air quality of an airport’s environment can be affected by several factors such as: •Aircraft. To reduce the emissions of this source it is necessary to further investigate cleaner engines and facilitate the efficiency of aircraft operations in the movement area. •Aircraft handling and support vehicles. To reduce the emissions of this source it is necessary to convert the vehicles to natural gas, propane, hybrid-electric or electric power. •Infrastructure and stationary sources. To reduce the emissions of this source it is necessary to modernise the equipment and optimise the energy efficiency of the operations and of the building use. •Landside access and airside ground traffic. To reduce the emissions of this source it is necessary to encourage airport employees and customers to use public transport. •Ambient air quality regulations. To ensure that all the above-mentioned factors are taken into account and being solved, ambient air quality regulations are needed. 9.1.3 Greenhouse gases and climate change There are other causes of air quality degradation which are far worse from the global environmental point of view. Greenhouse gases (GHG) are gases that remain in the atmosphere, retain heat and cause an increase in global temperatures, which has a direct impact on the climate and the sea levels. Moreover, GHG emissions in the atmosphere have a direct impact on the global climate change, which is a great danger for both natural and human systems. GHG are generated by fuel combustion, electrical power generation and ground access vehicles. The GHG emissions at airports are mainly CO2emitted from burning fossil fuels. Therefore, to minimise GHG emissions, the it necessary to minimise the time during which the engines are functioning. 9.1.4 Water and soil pollution and its management Water pollution is the consequence of discharging certain substances into the aquatic environments, which results in negative effects on the aquatic life, water quality, ecosystems, water chemistry and, ultimately, on human health. There are some activities during the construction of an airport that may cause water pollution such as clearing, grubbing and pest control. Clearing of vegetation results in soil erosion, grubbing results in alterations to the natural drainage patterns which can result in flooding or drought streams and pest control can introduce toxic chemicals into the water and disrupt the hydrologic balance of waterways in the area. TFG Report Page 148 of 167
UPC-ESEIAAT 9 ENVIRONMENTAL AND SOCIAL IMPACT STUDY As for waste liquids, they must be treated on site before being discharged in the environment or delivered to the local municipal treatment system. Waste liquids include: storm water, petroleum and chemicals such as de-icing and anti-icing fluids. 9.1.5 Waste and its management Environmentally harmful materials and waste from the airport and incoming aircraft should be managed effectively. The waste from terminal building is the largest waste source of an airport. As a consequence, the 4Rs should be applied: reduce, reuse, recycle and recover. The waste management programme should be thoroughly planned, including its procedures and special provisions. 9.1.6 Flora and fauna and its management The constructions of an airport usually requires clearing and cutting large extensions of flora, changes to the topography of the area and water pollution. As a consequence, the natural habitat and feeding area of the local fauna and the flora are deeply affected, which can disrupt the ecological balance of the area. Another effect on the fauna can be seen in the birds. The presence of birds in the environment of an airport is dangerous for the safety operation of the aircraft. The airport must be located far from bird migration routes and areas naturally attractive to birds. Other alternatives are scaring techniques and making the environment less attractive to birds. 9.1.7 Energy management Heating, ventilation, air conditioning and lighting are the main sources of energy consumption of an airport. This consumption can be decreased by using new energy efficient airport facilities. Energy consumption must be registered so as to be able to analyse the information and see where energy can be saved, both from an economic and environmental point of view. Furthermore, an energy strategy must be followed, which consists of two factors: •Choice of energy source, which depends on the energy security, the cost, the available resources, the environmental impact and the legislation. Renewable energy sources are recommended. •Effective utilisation and management of energy, which consists in meeting the operation objectives of the airport while being able to store the exceeding energy. So as to do so, it is necessary to understand where, how and why energy is used. Considering that lighting is the main energy consumption source, it is recommended to make the most of natural light during the day. 9.2 Social impact associated with aviation activities This subsection describes the social impact related to the aviation industry. 9.2.1 Land use The land used by an airport directly affects the operational safety of an airport but also its efficiency. Thus, if properly executed, the unused land of an airport can be intended to other uses that can benefit the local community other than residential or institutional land uses. Care must be taken so that the safety of people is considered and that the exposure to the environmental effects of an airport’s operation are close to zero. Examples of land TFG Report Page 149 of 167
UPC-ESEIAAT 9 ENVIRONMENTAL AND SOCIAL IMPACT STUDY use that suppose a mutual benefit for both the airport and the local community are listed below: •Agricultural land use, whose benefits are that it produces an income from what would otherwise be an unused portion of land. It prevents soil erosion and it eliminates the expenditure on taking care of this portion of land. •Recreational land use, whose benefits are that parks, gardens and sports facilities provide beauty, interest and activity in the airport’s vicinity. •Commercial land use, which could suppose an income generated by shopping centres, warehouses and offices. These facilities are not affected by night noise, considering that during those hours they are empty. •Industrial land use, which could be a valuable revenue for both airport operators and business companies, considering that they can take advantage of the benefits that air transportation offers. These facilities are also not affected by noise, considering that they are also a source of it. •Railways, highways and municipal utilities, which are infrastructures that are profitable for both the airport and the local area. 9.2.2 Land use decisions and management This subsection will address the issue of compatibility between the interests of the land and the aeronautical use of the airport. It must be insisted that the cooperation between the airport authorities and local authorities is of paramount importance to ensure that both parts are in agreement with the decisions taken. The three main problems that are presented are the high prices the land-owners expect from their properties, the local government tax base increment and the interest of owners and residents in maintaining or even increasing the value of their residence. While these can be understandable from their point of view, it is necessary to arrive to a common ground, considering that a bad management of these issues can greatly affect the development of an airport project. Land use management instruments can be divided in three and their methods will be explained next. Planning instruments Planning instruments include: •Comprehensive planning, which consists in ensuring that the community goals are taken into account when developing the airport. It is a compatibility method that is both effective and affordable. •Noise zoning regulations, which consists in defining the use of each parcel of land as a function of the noise level it receives. The government authority needs to interpret the noise contours created by the airport in the worst case scenario with the airport at maximum capacity and it should take into account the future expansions of the airport Noise zoning regulations are focused on the protection and compatibility of both the airports and the residents. Nevertheless, it is usual for a local community to want to grow in population and to increase the value of the land, which are in conflict with the need to preserve the airport’s vicinity areas without residences to comply with the noise reductions policies and affect the least number of people possible. Common ground must be found so that compatibility, private ownership of land and TFG Report Page 150 of 167
UPC-ESEIAAT 9 ENVIRONMENTAL AND SOCIAL IMPACT STUDY land productivity and value are maintained. •Subdivision regulations, which consist of regulations that apply to a particular zone and that are focused on minimising the affects of noise to already existing buildings and buildings that are in construction. •Transfer of development rights, which consist in transferring to another property away from the airport the development rights of a property. The land-owner would be compensated. •Easement acquisition, which represents the right to use a land-owner’s property for a limited purpose, in exchange for some compensation. Examples of these purposes are: the right of flight over the property, the right to create noise and the right to forbid future height obstructions into the airspace. Other restrictions are a certain limit of electromagnetic interference and light emissions. Easement acquisitions are less costly than directly buying the land and it allows the owner to remain with its ownership. Mitigating instruments Mitigating instruments include: •Building codes, which are regulations that determine how buildings must be constructed in terms of sound insulation to minimise the effects of noise. Other factors to take into account are ventilation and air conditioning in warm weathers, considering that windows should be closed to cancel the noise. •Noise insulation programmes, which are programmes that help defray the costs of noise insulation for land owners. •Land acquisitions and relocation, which consists in the airport operator buying the corresponding land and relocating the residence and businesses that are not compatible with the airport needs. This land can be cleared, sold with easements or transformed to other compatible facilities. Although looking for compatibility, this solution is costly and socially disruptive. •Transaction assistance, which consists in technically and financially helping the owners of real estate to sell their noise-affected property by paying, for instance, the realtors’ fees. Airport operators can even buy the property, noise-insulate it and resell it with easements. •Real estate disclosure, which consists in openly announcing that the a residence which is on sale is affected by noise issues. By doing so, future buyers will be aware of the product and does not complain in the future. Although complicating the sale of the residence, owners are advised to announce this problem. Financial instruments Planning instruments include: •Capital improvements planning, which consist in promoting infrastructure network around the airport so as to attract development of compatible industrial and commercial growth. At the same time, it discourages the growth of residential zones, which is a positive factor. •Tax incentives programmes, which is an encouragement for the owners to noiseinsulate their residences in exchange of tax incentives. This can be offered to attract industries that also generate noise as a method of avoiding the construction of residential zones that are noise-sensitive. •Noise-related airport charges, which is a method to encourage airlines to use TFG Report Page 151 of 167
UPC-ESEIAAT 9 ENVIRONMENTAL AND SOCIAL IMPACT STUDY the quietest possible aircraft technology. The recollected charges can be intended to provide funds for sound insulation programmes and to defray the costs that noise problems have supposed for the airport. 9.2.3 Heritage The presence of natural or cultural heritage that have aesthetic, historic, scientific, social or national value that must be protected is important when it comes do the development of an airport. When identifying a heritage near an airport, some principles must be applied: •Committing to respect, protect and conserve heritage elements and comply with any legislation and regulation there may exist. •Taking into consideration the heritage elements when making airport decisions. •Allowing community involvement when dealing with heritage elements. TFG Report Page 152 of 167