Preliminary study of an HVDC transmission network in Spain UPC By Jaime B´ arzana Gonz´ alez Electrical Engineering Department Universidad Polit´ ecnica de Catalu˜ na Supervisors: Oriol Gomis Bellmunt Montserrat Montal` a Palau Mohammadamin Aghahassani A thesis submitted for the degree of Double Master’s Degree in Industrial & Energy Engineering Barcelona, April 2024
This thesis is submitted to the Electrical Engineering Department, Universidad Polit´ ecnica de Catalu˜ na in fulfilment of the requirements for the double MSc in Industrial and Energy Engineering. Jaime B´ arzana Gonz´ alez, April 2024 Copyright © 2024 Jaime B´ arzana Gonz´ alez All right reserved.
Abstract In the past few years, there has been a concerted effort to move towards renewable energy sources and reduce dependence on fossil fuels in electricity production. This transition poses a significant contemporary challenge, especially given that many power plants currently rely on synchronous generators, whose inertia provides system stability. To mitigate the effects of instability associated with decarbonization, several solutions, known as FACTS have been implemented. These devices allow greater control of the grid, making it more flexible and adaptable. In addition, the goal is to create a strong, interconnected continental grid, and one way to achieve this is through direct current power transmission, known as HVDC. HVDC transmission offers several advantages over the traditional alternating current (HVAC) variant; these include the ability to interconnect networks with different frequencies or greater energy efficiency. However, HVDC technology has a disadvantage: it is often an expensive technology as it requires power electronics-based equipment, with a limited market. Investment in this type of technology is a goal of international organizations to provide a resilient grid and to allow the integration of renewables. In this work, a technical analysis of the current interconnection with France in the transmission grid will be carried out, locating its weaknesses and proposing two improvement scenarios; firstly, it will be seen how the HVDC technology impacts on the interconnection with France, assessing aspects such as transmitted power flows, transmission efficiency and the potential advantages that it may have over the HVAC variant, which will also be analyzed in depth. All this will have an economic study in which the feasibility of the project and which is the most appropriate alternative to implement will be assessed.
Resumen En los ´ ultimos a˜ nos, ha habido un esfuerzo concertado para apostar hacia fuentes de energ´ ıa renovable y reducir la dependencia de los combustibles f´ osiles en la producci´ on de electricidad. Esta transici´ on plantea un desaf´ ıo contempor´ aneo significativo, especialmente dado que muchas plantas de energ´ ıa actualmente dependen de generadores s´ ıncronos; los cuales, gracias a su inercia aportan la estabilidad del sistema. Para mitigar los efectos de la inestabilidad asociados con la descarbonizaci´ on, se han implementado varias soluciones, conocidas como FACTS. Estos dispositivos permiten un mayor control de la red, haci´ endola m´ as flexible y adaptable. Adem´ as, el objetivo es crear una red continental fuerte e interconectada, y una forma de lograrlo es a trav´ es de la transmisi´ on de energ´ ıa en corriente continua, la conocida como HVDC. La transmisi´ on HVDC ofrece varias ventajas sobre la variante de corriente alterna tradicional (HVAC); estas incluyen la capacidad de interconectar redes con diferentes frecuencias o una mayor eficiencia energ´ etica . Sin embargo, la tecnolog´ ıa HVDC tiene una desventaja: suele ser una tecnolog´ ıa costosa ya que requiere equipos basados en electr´ onica de potencia, con un mercado limitado. La inversi´ on en este tipo de tecnolog´ ıa es un objetivo de organizaciones internacionales para ofrecer una red resilente y que permita la integraci´ on de las renovables. En el presente trabajo se realizar´ a un an´ alisis t´ ecnico sobre la actual interconexi´ on con Francia en la red de transporte, localizando sus debilidades y planteando dos escenarios de mejora; en primer lugar se ver´ a como impacta la tecnolog´ ıa HVDC en la interconexi´ on con Francia, valorando aspectos como los flujos de potencia transmitidos, la eficiencia de la transmisi´ on y las ventajas potenciales que puede tener esta frente a la variante HVAC, la cual tambi´ en se analizar´ a en profundidad. Todo ello tendr´ a un estudio econ´ omico en el que se valorar´ a la viabilidad del proyecto y cual es la alternativa m´ as adecuada a implantar.
Resum En els darrers anys, hi ha hagut un esforc¸ concertat per apostar cap a fonts d’energia renovable i reduir la depend` encia dels combustibles f` ossils a la producci´ o d’electricitat. Aquesta transici´ o planteja un desafiament contemporani significatiu, especialment at` es que moltes plantes denergia actualment depenen de generadors s´ ıncrons; que gr` acies a la seva in` ercia aporten l’estabilitat del sistema. Per mitigar els efectes de la inestabilitat associats amb la descarbonitzaci´ o, s’han implementat diverses solucions, conegudes com a FACTS. Aquests dispositius permeten un control m´ es gran de la xarxa, fent-la m´ es flexible i adaptable. A m´ es, l’objectiu ´ es crear una xarxa continental forta i interconnectada, i una manera d’aconseguir-ho ´ es a trav´ es de la transmissi´ o d’energia en corrent continu, la coneguda com a HVDC. La transmissi´ o HVDC ofereix diversos avantatges sobre la variant de corrent altern tradicional ; aquestes inclouen la capacitat d’interconnectar xarxes amb diferents freq¨ u` encies o una major efici` encia energ` etica. Tot i aix` o, la tecnologia HVDC t´ e un desavantatge: sol ser una tecnologia costosa ja que requereix equips basats en electr` onica de pot` encia, amb un mercat limitat. La inversi´ o en aquesta mena de tecnologia ´ es un objectiu d’organitzacions internacionals per oferir una xarxa resilient i que permeti la integraci´ o de les renovables. En aquest treball es realitzar` a una an` alisi t` ecnica sobre l’actual interconnexi´ o amb Franc¸a a la xarxa de transport, localitzant-ne les debilitats i plantejant dos escenaris de millora; en primer lloc es veur` a com impacta la tecnologia HVDC a la interconnexi´ o amb Franc¸a, valorant aspectes com els fluxos de pot` encia transmesos, l’efici` encia de la transmissi´ o i els avantatges potencials que pot tenir aquesta front a la variant HVAC, que tamb´ e s’analitzar` a en profunditat. Tot aix` o tindr` a un estudi econ` omic on es valorar` a la viabilitat del projecte i quina ´ es l’alternativa m´ es adequada a implantar.
Contents 1 Introduction 1 1.1 Scope..................................... 1 1.2 Motivationofwork............................. 2 1.3 WorkStructure ............................... 2 2 State of Art 4 2.1 HVDC Networks: Fundamentals . . . . . . . . . . . . . . . . . . . . . 4 2.2 Advantages and Disadvantages of HVDC . . . . . . . . . . . . . . . . 6 2.3 Actual Network in Spain . . . . . . . . . . . . . . . . . . . . . . . . . . 8 2.3.1 HVDC links in the Spanish Power System . . . . . . . . . . . 11 2.3.1.1 Mallorca-Mainland Connection . . . . . . . . . . . . 11 2.3.1.2 France - Spain Connection . . . . . . . . . . . . . . . 12 2.4 Technological Potential of HVDC in Spain . . . . . . . . . . . . . . . . 13 2.4.1 HVDC & HVAC new connections . . . . . . . . . . . . . . . . 14 2.4.2 FACTS................................ 14 2.5 Conversion HVDC technologies . . . . . . . . . . . . . . . . . . . . . 17 2.5.1 Mercury Arc Valve Bridge . . . . . . . . . . . . . . . . . . . . . 17 2.5.2 Line Conmutated Converters (LCC) . . . . . . . . . . . . . . . 19 2.5.3 Voltage Source Converters (VSC) . . . . . . . . . . . . . . . . . 21 2.5.4 Modular Multi-level Converter (MMC) . . . . . . . . . . . . . 23 2.6 HVDCconfigurations............................ 24 2.6.1 Asymmetrical Monopole . . . . . . . . . . . . . . . . . . . . . 25 2.6.2 Symmetrical monopole . . . . . . . . . . . . . . . . . . . . . . 26 2.6.3 Bipole ................................ 27 2.6.4 Back-to-back [B2B] . . . . . . . . . . . . . . . . . . . . . . . . . 28 2.6.5 Multi-terminal ........................... 30 i
ii 3 Methodology 32 3.1 Introduction................................. 32 3.2 Route & Corridors Selection . . . . . . . . . . . . . . . . . . . . . . . . 33 3.3 Technical Analysis -Load Flow Study . . . . . . . . . . . . . . . . . . 35 3.3.1 PandaPower(PP) ......................... 36 3.3.1.1 BusModel ........................ 37 3.3.1.2 Generator Model . . . . . . . . . . . . . . . . . . . . . 38 3.3.1.3 LoadModel........................ 39 3.3.1.4 AC Line Model . . . . . . . . . . . . . . . . . . . . . . 40 3.3.1.5 DC Line Model . . . . . . . . . . . . . . . . . . . . . . 41 3.3.1.6 External Grid Model . . . . . . . . . . . . . . . . . . . 42 3.3.1.7 Power Balance & Calculation Algorithm . . . . . . . 42 3.3.2 HVAC system modelling . . . . . . . . . . . . . . . . . . . . . 45 3.3.3 HVDC system modelling . . . . . . . . . . . . . . . . . . . . . 48 3.3.4 France-Spain interconnection model . . . . . . . . . . . . . . . 49 3.4 EconomicAnalysis ............................. 52 3.4.1 Introduction............................. 52 3.4.2 Cost Analysis of the HVAC case . . . . . . . . . . . . . . . . . 54 3.4.2.1 Substation Costs . . . . . . . . . . . . . . . . . . . . . 55 3.4.2.2 LineCosts......................... 56 3.4.2.3 Reactive Compensation Costs . . . . . . . . . . . . . 57 3.4.2.4 Operation and Maintenance . . . . . . . . . . . . . . 58 3.4.3 Cost Analysis of the HVDC case . . . . . . . . . . . . . . . . . 58 3.4.3.1 Substation Costs . . . . . . . . . . . . . . . . . . . . . 58 3.4.3.2 Transmission Line Costs . . . . . . . . . . . . . . . . 60 3.4.3.3 Reactive Compensation Costs . . . . . . . . . . . . . 61 3.4.3.4 Operation and Maintenance . . . . . . . . . . . . . . 61 4 Results and Discussion 62 4.1 LoadFlowComparison .......................... 62 4.1.1 Case 0 - Current Situation . . . . . . . . . . . . . . . . . . . . . 62 4.1.2 Case A: HVAC Extra Line . . . . . . . . . . . . . . . . . . . . . 65 4.1.3 Case B: HVDC Connection - Gatika Cubnezais Link . . . . . . 66 4.1.4 Comparative Analysis . . . . . . . . . . . . . . . . . . . . . . . 68 4.1.5 Advantages of HVDC - Practical Cases . . . . . . . . . . . . . 70 4.2 Economical Comparison . . . . . . . . . . . . . . . . . . . . . . . . . . 73
iii 4.2.1 Economic Viability - BEP . . . . . . . . . . . . . . . . . . . . . 73 4.2.2 Economic Impact. HVDC vs HVAC . . . . . . . . . . . . . . . 76 4.2.3 Investment Analysis . . . . . . . . . . . . . . . . . . . . . . . . 78 4.3 Legal & Regulatory Frame . . . . . . . . . . . . . . . . . . . . . . . . . 82 5 Conclusions 85 5.1 FutureWork................................. 86 A Environmental Assessment 87 A.1 OverallComparison ............................ 87 A.2 Case A: Extra HVAC Connection . . . . . . . . . . . . . . . . . . . . . 88 A.3 Case B: HVDC Connection; Gatika -Cubnezais Link . . . . . . . . . . 90 B Economic Assessment - Budget 94 B.1 LabourCost ................................. 96 B.2 Licenses & Equipment Cost . . . . . . . . . . . . . . . . . . . . . . . . 96 B.3 TotalCost................................... 97 C Social & Gender Impact Study 98 D Load-Flow Analysis of Gatika-Cubnezais Case of Study 100 Bibliography 131
List of Figures 2.1 Basic scheme of power system structure (2) ............... 5 2.2 Temporal evolution of HVDC accumulated power (41) ........ 6 2.3 Difference in current flow (J) in various zones of a conductor with DC and AC currents (50).......................... 7 2.4 Transmission grid in Spain in 2016 (21).................. 10 2.5 Cable burial process in the seabed. (44) ................. 12 2.6 Power flow in the SPA-FRA link (37)................... 13 2.7 Converter technology chronological evolution (49)........... 17 2.8 12 pulse bridge with mercury arc valves . . . . . . . . . . . . . . . . . 18 2.9 Wave representation of the rectification by thyristors (24)....... 19 2.10 LCC converter equivalent circuit [6-pulses] (52)............. 20 2.11 VSC equivalent circuit (54)......................... 21 2.12 Influence of the voltage levels in a MMC (54).............. 24 2.13 HVDC monopole configuration with earth return (56)......... 26 2.14 SLD of the bipolar configuration & Voltage and current distribution in SS (35)................................... 28 2.15 B2B configuration for HVDC applications (31) ............. 29 2.16 Japan electrical frequency map . . . . . . . . . . . . . . . . . . . . . . 30 2.17 Multi-terminal HVDC link with four-terminal (46)........... 31 3.1 Route comparison for the load flow between HVDC at 400 kV and HVACat400kV .............................. 35 3.2 Internal data management scheme of pandapower (53) ........ 37 3.3 Bus equivalent circuit (53) ......................... 38 3.4 Generator equivalent circuit (53) ..................... 39 3.5 Load equivalent circuit (53) ........................ 40 3.6 AC Line equivalent circuit (53) ...................... 41 3.7 DC Line equivalent circuit (53) ...................... 41 iv
3 see the potential that the country has. The projects planned to improve the grid in the coming years are presented in order to integrate renewable technologies. After this, in section 2.5, the power electronics technologies used in converter stations are discussed in depth; also their development over the years, until the most innovative and currently used, are presented. The configurations that can adapt this type of installations, closely linked to the purpose, the availability level, or the budget, are also deeply explained. After the theoretical basis, the case study of the Gatika-Cubnezais link , within the environment of the Spain-France interconnection, is analyzed. In the Methodology chapter, it is explained how the grid modeling has been carried out, where all the elements are explained in detail; economic considerations are also presented. In the technical analysis it is shown how the elements have to be modelled and the calculation algorithm that will be used for power flow calculations. Regarding the economic analysis, the main items in terms of cost that appear in this type of works are explained. Once explained, the report proceeds to the results section, in chapter 4, wherein a numerical comparison of the obtained results is conducted. This comparison elucidates the advantages and quantifies the advantage of one technology over the other in terms of power losses. Additionally, other pertinent aspects are also assessed within this section. For the economic issue, the costs are analyzed and a cash-flow analysis of the project is made, thus seeing the point of view of a customer when ordering this type of projects. Subsequently, an environmental study is carried out and the regulatory framework required for projects with this type of impact is analyzed, in order to see that these are very important items to consider when designing projects of this caliber. Finally, the conclusions of the project are presented in chapter 5, explaining the importance of the results and analyzing which are the lines to follow in order to continue developing the project on a larger scale.
Chapter 2 State of Art 2.1 HVDC Networks: Fundamentals Historically, electricity has always been transported using alternating current (AC), since this is the natural way in which electricity is generated in traditional plants. Once it is generated, it must be transported to and the energy that is generated is not suitable for transport, which is why it must be transformed beforehand. The main reason of stepping-up the voltage is to increase it’s efficiency. In the electrical substations, which are located next to the generation plants, a transformation of the energy is made, keeping the power practically constant (the ideal case is almost impossible). The voltage is increased from tens of kilovolts (typically 10-15) to hundreds of kilovolts (typically 110/220/300 and 400 kV). Once this voltage rise has been achieved, it is possible to transport it and generate a flow of energy to the consumer areas with fairly low losses. Finally, when the energy is consumed, it is necessary to lower the voltage in the distribution substations in order to have voltage values in accordance with consumption. A very schematic representation can be seen in Figure 2.1. Until 1954, all power transmission was done by means of HVAC networks; in this year the HVDC Gotland power line was inaugurated, a pioneer in the technology linking peninsular Sweden with the island of Ygne, thanks to a 98-kilometer cable transferring 20 MW of power (8). 4
5 Figure 2.1: Basic scheme of power system structure (2) This milestone was the starting point in the development of a technology that has been evolving technologically and the number of links has been growing. According to (41), the trend is that by the end of 2025, the installed power will be 35 GW, having experienced an exponential growth, mainly due to the emergence of multilevel VSC technologies, which will be discussed later. In Figure 2.2, it is shown how from 2015 there is a big jump in the installed capacity; this is closely linked, as mentioned above, to the boom in the appearance of the VSC converters; it must be taken into account that these projects are developed over years since the manufacture of the converter stations is a very specific task that is carefully designed according to the characteristics of the terrain. In addition, the installation of the high voltage cable is also done very slowly since it requires specific vessels for the laying, which are limited. On the other hand, the commissioning is also a process that can take months in projects of this magnitude; from there the increase has been exponential until reaching the current stage where we see that it is a booming technology that is expected to continue growing thanks to all the advantages it has, which will be detailed in later chapters.
6 Figure 2.2: Temporal evolution of HVDC accumulated power (41) 2.2 Advantages and Disadvantages of HVDC HVDC grids are not as widespread as AC grids since it is not the natural way in which electricity is generated, and therefore, there has had to be a technological development to get to the current point. The main advantage is its better efficiency; as previously mentioned, the resistance (R) to the passage of current is a fundamental magnitude in electrical engineering. This is proportional to a parameter function of the material called resistivity (ρ); it’s also proportional to the length, while it’s inversely proportional to the section; thus, it does not depend on any other electrical magnitude. However, when entering the field of alternating current, inductive (L) and capacitive (C) effects appear, these will generate extra losses compared to direct current, which only has ohmic resistance (R). In addition, at high voltages, there is another problem called corona effect. This phenomenon is an ionization of the air surrounding the conductor; this ionization of the air causes the efficiency to drop, because the electrons that should be circulating in the transmission network are released, generating heat and light. The generation of heat and light has harmful consequences because it weakens the insulation, increases the effective resistance, generating more Joule losses and can have electromagnetic interference.
7 Due to the increase in inductive reactance (XL) in the center of the conductor (due to the greater variation in the magnetic field), the current tends to distribute in the areas closest to the edges (film effect) and therefore can there be larger peaks of current that create air ionization. This is something that does not happen in DC because there is no variation in the magnetic field, due to the unidirectional and constant current. Figure 2.3: Difference in current flow (J) in various zones of a conductor with DC and AC currents (50) Another crucial improvement is the increase in the flexibility of the network, thanks to the control achieved with VSC-based converters. With this, an independent control of the active (P) and reactive (Q) power can be made. By controlling the reactive power (Q), it is possible to perform the functions of STATCOM, injecting or absorbing to the network in case of fluctuations in voltage. By means of active power control (P), the useful power that is distributed is controlled. This is very important, since generation must cover demand; Otherwise, there will be mismatches that will lead to frequency fluctuations, which must be resolved by the TSO. In other words, the improvement in flexibility improves the stability and control of the entire grid. For systems with large uncertainties, such as renewables, this type of installations generate a substantial improvement because it allows a great integration. When there are very rigid grids, renewables must trip when there are situations
8 outside the standards, while with more flexible networks, these situations practically occur on occasions of maintenance or weather conditions that can damage the facilities (such as hurricane-force winds) In later chapters, it will be explained in depth, but VSC-HVDC systems allow the interconnection of electrical grids where the frequencies are different, something completely prohibited in AC systems as it would destabilize the network, damage the connected equipment, and could lead to resonance situations. This type of application is already used, for example, in the Brazil-Argentina link or on the Japan island. In terms of the disadvantages that arise, the vast majority are related to economic aspects; being a technology that relies on converter stations, the initial investment is very significant, so it is not always a feasible solution. Additionally, until recently, technology companies with the know −how of this type of solutions were few (ABB, GE, Siemens, Mitsubishi), creating situations where prices were inflated due to a lack of competition, potentially influencing government policies. Another point to bear in mind is that the converter stations, have switching devices that produce current peaks when the circuits are opened and closed. The higher the switching frequency, the greater the heat dissipated. It is mandatory to have cooling systems that allow these stations to have a reasonable temperature within a range. When the named plate power is large, these types of installations are expensive, since they require specific equipment, with expensive working fluids. 2.3 Actual Network in Spain Spain’s energy transmission grid is controlled entirely by Red El´ ectrica de Espa˜ na (REE), the TSO. REE controls the entire high voltage transmission grid, where there are two main voltage levels, 400 and 220 kV. In addition to this, it is in charge of such key functions as: • Coordination of the generation-demand balance.
9 • Frequency control • Reactive power management • Management of international interconnections • Infrastructure investment • Strategic planning for the future of the grid. • Integration of renewable energies • Coordination with distribution companies • Ensuring electricity supply The current grid consists of the aforementioned 400 kV and 220 kV networks. According to REE’s last annual report for 2022, the total length of the transmission network amounted to 45 101 kilometers, an increase of 0.7 % over the previous year. Spain is interconnected with Portugal, Morocco and France. The first two have standard connections by means of HVAC links; in the case of Morocco, there’s a submarine cable connection since 1997. With France, there are two connections: the first one in the western part of the country (Basque Country) with an HVAC connection; and in the eastern part (Catalonia), they have a VSC-HVDC link, connecting Baixas and Santa Llogaia since the end of 2015. The situation of the Iberian Peninsula is particular given that it is isolated from the European grid due to its geographical position, which is why reinforcing the interconnection with France is a key aspect to ensure a reliable and synchronous grid. In fact, in the past year 2023, the tender for the Bay of Biscay project (Gatika- Cubnezais connection) has been awarded. This is a pretty important milestone that will increase the interconnection capacity up to 5 GW thanks to the commissioning of a bipolar installation with almost 400 kilometers of submarine cable.
10 As for the Spanish archipelagos, the Canary Islands have a totally independent electricity system, isolated on each of the islands. Most of the generation is fossilfuel based, but the aim is to promote the integration of renewables into the grid, improve the meshing of the transmission grid on each island to make it more reliable and interconnect islands with each other, such as the Lanzarote-Fuerteventura or Tenerife-La Gomera (commissioned by the end of 2022) links. In the Balearic system,there is already a connection with the mainland since 2012, with LCC-HVDC technology, thanks to the R´omulo project. The second part of the R´omulo project allowed the creation of a link between Mallorca and Ibiza, thus creating an electrical connection between all the islands, which were previously only separated in two subsystems (Ibiza-Formentera & Mallorca Menorca). Figure 2.4: Transmission grid in Spain in 2016 (21)
11 2.3.1 HVDC links in the Spanish Power System 2.3.1.1 Mallorca-Mainland Connection R´omulo project has been a reference project in the direct current transmission sector since the day of the energization; with its commissioning, the quality and reliability of the Balearic system has been improved. This has made it possible to improve the quality of the electricity supply, reduce generation costs and improve electricity efficiency. One of the particularities of the project is that it is the second deepest submarine link in the world, at 1 485 m, behind only the Sardinia connection to the Italian peninsula, which reaches 1 650 m. To guarantee a reliable supply, a bipolar configuration was chosen, since being the only point of connection with the peninsular system, the connection had to be guaranteed even when maintenance work was being carried out at one of the poles. The project was awarded to Siemens group for the converter stations and the Prysmian-Nexans consortium for the submarine cables, with each of the groups producing one power cable and half of the return cable. Given the great depth of the Mediterranean Sea, the means for the installation of the cable are very limited, being only two ships in the world, suitable for the laying of the cable, the Italian Giulio Verne and the Norwegian Skagerrak. These ships were able to transport the complete cable without the need for intermediate splices. In addition, they are equipped with dynamic positioning systems (DGPS), which allows them to precisely follow the cable laying trajectory. To minimize the impact with the seabed, up to depths of 1 000 m, the cable is buried by means of a robot that injects water under pressure, minimizing the possibility of damage due to trawling or anchoring. In the areas closest to the coast, horizontal perforations have been made to minimize the impact with the beaches, being the entire cable laying up to the converters with buried cable.
12 The underground system has two vehicles: a remote control vehicle for monitoring the cable and total control of its position; and the pressurized water injector, which allows burial. Figure 2.5: Cable burial process in the seabed. (44) 2.3.1.2 France - Spain Connection This connection has been made mainly due to the requirements of the European Union for international connections to make the European electricity system more resilient. In addition, it will reinforce the power supply for the high-speed railway line running on the Spanish side. The connection has been made by buried cable in both the Spanish and French areas inside concrete troughs, except for a section of 8.5 km where the line runs through a tunnel to cross the Albera massif. This connection doubles the level of interconnection between France and Spain, reaching 6%, but still below the 10% required by the EU. The interconnection between both countries allows: • Energy production optimization of power plants • Integration of renewables • Increase in the supply conditions Only with a solid, meshed power grid will it be possible to integrate the renewables that are currently being invested in.
19 2.5.2 Line Conmutated Converters (LCC) LCC converters are the most classic in the direct current transmission sector, with a wide presence in the world, in fact, there are currently more than 170 installations of this type (10). In this type of technology, the conversion is based on a stable line voltage, with clear zero-crossings of the AC system to which the converter is connected in order to have a flow commutation from one switching element to another (12). It is a key point in the history of converters since it is the first one based on power electronics and the first one to be controllable. LCCs are composed of thyristors, which are bistable switches that regulate the passage or not of current by means of the so-called firing angle. This firing angle shows the times at which the thyristor must let the current through; as can be seen in the Figure 2.9, during the first 180 degrees, the device conducts and lets the current pass through it, while when it is between 180º and 360º, the semi-conductor is in cut-off since the polarity has been changed and the current is conducting in the opposite direction, preventing the current from passing. Figure 2.9: Wave representation of the rectification by thyristors (24)
20 As in the case of mercury arc rectifiers, the higher the number of pulses of the converter, the better the output signal, due to the reduction of harmonic distortion. Figure 2.10: LCC converter equivalent circuit [6-pulses] (52) I can be seen that in parallel to the thyristors there is an RC filter in each rack. This is done mainly to minimize the impact on the overshoot that is generated when a thyristor is turned off and another one starts to operate. The charge accumulated inside the thyristor must be eliminated quickly since this can cause damage to the electronics (12). In addition, the harmonic content is also reduced since the filter attenuates the output signal. Subsequently there is a reactor coil, which has several functions (11): • Smoothing of the current • Filtering harmonics • Limiting rate of change of current, reducing voltage peaks [∂I/∂t] Although this is a leap compared to mercury valves, it still has limitations. The control of the conversion by means of the firing angle, lags behind in comparison with novel technologies that have more effective control. In addition, the harmonic generation previously discussed can be improved with filters and reactors, but not completely eliminated. Lately, new methodologies have appeared, such as (48), which proposes a point-by-point technology that can improve the generation of these harmonics.
21 Regarding grid issues, line conmutated converters require networks with high short-circuit ratios. This ratio evaluates the level of stiffness of the network against changes; when there is a fault, the grid should provide the necessary current during the commutation process to make it smooth. Also with strong grids, LCC converters can stay in operation mode, because the grid support this type of situation without tripping (12). Another weakness of this technology is the link it has with reactive power. Thyristors are capacitive loads that lag the current angle with respect to the voltage; this causes the power factor to worsen due to reactive power consumption, which generates inefficiencies in the network. 2.5.3 Voltage Source Converters (VSC) Voltage source converters are self conmutated converters widely used in the HVDC industry. The novelty of the VSC converters is based on the use of IGBT‘s, which are electronic devices that function as a controlled switch. The main advantage of the use of IGBT‘s lies in the switching: besides being independent of the AC mains that feeds it, the switching speed is much higher, thus being able to make a much more effective control. Figure 2.11: VSC equivalent circuit (54) VSC as well as LCC are bidirectional devices that can operate as rectifier or as inverter depending on the requirements of the electrical network. This independence from the grid increases the controllability, being able to control separately the active and reactive power (P&Q).
22 As the switching frequency is somewhat controllable, it allows to create any grid and connect to any grid, being the most flexible device. The series RL filter is simply to reduce the harmonic content generated by the switching devices, although they generate much less distortion compared to LCC’s, due to: • PWM Technique, that allows control of the amplitude of the generation of the sinusoidal waveform without a high harmonic component. • Control of the frequency: Reduction of abrupt transients and reduction of the THD because the frequency is very high in comparison with the grid one (kHz order of magnitude) (51). The capacitor that is placed in parallel with the transistors, besides also performing the function of reducing harmonics, provides the transistor base with power in case of need, thus ensuring a fast and continuous response when switching is carried out. Additionally, it helps to maintain the voltage level on the DC side, which makes it stable and controlled, being perfect for grid −forming applications. Another strength of VSC converters is the so-called black start capability.The ability to cold start in the event of a massive power outage is becoming an increasingly common requirement in grid codes. Line commutated converters did not have this capability, since their switching power was tied to the grid, and when the grid went down, the converter was inoperative until the normal grid frequencies were recovered. However, in the case of the VSCs, they are able to continue to have switching power since they can operate independently of the electrical grid, giving the possibility of restarting the system without the need of it, just using an ancillary service energy supplier, such as a battery that can feed transistor to start the come back (40). In terms of fault ride through, VSCs are capable of much more agile current and voltage control, so they adapt well to the grid; this can often be a problem, as they are too sensitive to disturbances, even if they are not too large. In this respect,
23 LCCs are better, as they maintain system stability better, but in the face of rapid and large disturbances, they fail. Recently, there have been studies to make the sensitivity of VSCs more efficient, such as in (34), here they propose the use of bridge type fault current limiters, to increase the capability. As a summary, the comparison between LCC and VSC is as follows: Table 2.1: Comparative between HVDC converter technologies LCC VSC Constant Current Direction? ×✓ Strong grid requirement? ✓× Filtering Requirement? ✓× Independent P&Qcontrol? ×✓ Black Start Capability? ×✓ Mature Technology? ✓× High power capability for converter? ✓× Ability to work in overload? ✓× Grid-forming capability? ×✓ Good multi-terminal coordination? ×✓ Good behaviour during short-circuits on DC line? ✓× Good dynamic response ×✓ 2.5.4 Modular Multi-level Converter (MMC) The evolution of the VSC converters is the so-called modular multilevel converter sub-family, in which more IGBT modules are added. The main advantage of this is the improved harmonic quality obtained by having several input DC signals, resulting in a much smoother signal. In fact, in the Figure 2.12, we see that in (32), they studied the impact on harmonics of increasing the number of voltage levels, as well as how the higher the number of voltage levels, the better it fits the real curve.
24 Figure 2.12: Influence of the voltage levels in a MMC (54) Very good results can be obtained with only 2 or 3 voltage levels, but the switching frequency should be enormous. Therefore, it makes sense to use more voltage levels and to reduce the frequency, having an excellent harmonic quality without too much loss; obviously, the implementation of more voltage levels has a negative factor, which is the price. 2.6 HVDC configurations Once the technology to be used in the converter, the brain of the HVDC system, has been decided, it is time to look at the different types that exist. These differ in operation and design, and are as follows: 1. Monopole 2. Bipole 3. Back to Back link (B2B) 4. Multi-terminal
25 Except the B2B, the other configurations are the so-called point to point applications (P2P) which are the ones for the transfer of energy over long distances. It can be offshore cases, such as large wind farms; and it can be on-shore, where when there are very large distances (as in countries like Brazil (20), USA, or China), the transmission by DC current becomes profitable, i.e., overpasses the BEP, which will be explained in later chapters. 2.6.1 Asymmetrical Monopole This is the simplest possible configuration. In it, there are two converter stations at the ends of the line, performing the functions of inverter and rectifier, depending on the direction in which the current flows. There is only one DC cable conductor. In order to close the circuit, and therefore, to establish a current and an electrical voltage, the circuit must be closed, i.e. the electrical path. This can be done by means of a wire, or by means of the ground. In the case of the asymmetrical monopole, the ground is used to close the circuit. Here, two electrodes are connected to the converters, as can be seen in Figure 2.13, thus allowing the current to flow. This solution is very interesting as it is the most economical of all, as the totality of the costs for additional conductors are null. Moreover, as it does not depend on only one conductor, the degree of availability is very high and maintenance work is minimal, resulting in a stable system, even under saturation conditions, as there is no limitation in the return. This ground return configuration is used above all for cases where the converters are of the LCC type, since they are not as controllable as VSCs and allow greater flexibility. VSC uses another configuration that will be explained below. Finally, another drawback that this configuration has already experience, is the environmental. The passage of the current causes the soil potential to be different from zero, causing an impact on the flora and fauna.
26 Figure 2.13: HVDC monopole configuration with earth return (56) 2.6.2 Symmetrical monopole This scheme is similar to the ground return, but in this case the return is made through a metallic conductor. A major problem of this configuration is reliability, since any problem in the return would cause the current to be interrupted; while in the case of the ground return this does not happen, since there are infinite return paths between the electrodes. The conductor return is the option chosen when there are environmental restrictions, so as not to alter the ground potential. This option is worse in terms of cost, so it is less used than the ground return. In addition, the returns by earth in cases of marine HVDC, can produce reactions in the seawater, generating chlorine [Cl−], among others. Additionally, an unbalanced current can generate magnetic fields that affect the sonars of marine vessels. Since one of the converter terminals is connected to ground, it is not necessary to insulate the conductor, thus being a more economical solution. On the downside, this is a configuration which experiences large surges when there is a fault on the DC interface. It is the right solution when dealing with not too large powers, since being a synthesized system with not too much reliability (no duplicity of poles), a system failure would not be so critical.
27 2.6.3 Bipole The bipolar configuration is a configuration where the stations are connected by two transmission cables, one with negative polarity and the other with positive polarity. The systems are independent, and transmit the same power at the same time. Thanks to the fact that the neutrals of the stations are connected to ground (in normal conditions (IN= 0), the main advantage of this type of configuration is reliability. The system is able to operate even if a monopole is not in service, since the return would become grounded, operating as a single monopole. In this type of configuration, as they are not directly connected to the neutral, since both cables have polarity, it is required that the conductors are insulated, so the cost increases. Normally, when an installation is made with a monopolar configuration, it is always with the purpose of having an upgrade and installing a second terminal in the future. In the Figure 2.14 it can be seen the voltages reached by both conductors. By having a bipolar configuration we achieve that the conductors establish a greater potential difference, which improves the transmission thanks to the reduction of the current. In addition, several studies such as (38) show that THD improves when bipolar configurations are used.
28 Figure 2.14: SLD of the bipolar configuration & Voltage and current distribution in SS (35) On the downside, this is a technology in which the transformer must be designed to withstand high DC voltages, so it will be much more expensive. 2.6.4 Back-to-back [B2B] The B2B configuration is more properly a link than a configuration. This type of configuration has the rectifier and the inverter in the same substation.
35 Figure 3.1: Route comparison for the load flow between HVDC at 400 kV and HVAC at 400 kV 3.3 Technical Analysis -Load Flow Study In this chapter, the software used for the quantitative analysis of the different technologies will be introduced, followed by an explanation of how both technologies have been modeled and which are the most important aspects to be taken into account when parameterizing an electrical network.
36 3.3.1 Panda Power (PP) In order to perform a quantitative demonstration, and to be able to see the real difference between these two types of technology, a Python library, called pandapower, has been used. Pandapower is a freely accessible library for power systems, where through intuitive programming, power flow and network optimization problems can be solved. The structure of pandapower is tabular, employing element-based configurations instead of the bus-branch approach commonly used in the vast majority of power system calculation programs. Each network item is represented in tabular form, defined by its electrical and physical parameters. After simulations, the results are also saved in tables, making it easy to access information for each node defined in the grid by simply inputting the relative index. Therefore, a proper definition of the network is fundamental. In order to define any point on the grid, standard definitions provided by PP are employed, such as lines, transformers, or buses. Figure 3.2 illustrates the data management scheme employed by pandapower.
37 Figure 3.2: Internal data management scheme of pandapower (53) Below are the functions that replicate the mathematical models of the electrical components 3.3.1.1 Bus Model The buses represent the connection nodes, that is, the points to which various elements of an electrical network are connected, such as lines, loads, etc. Being the most fundamental parameter, it is only necessary to input the voltage value. The encoding format for a bus in Pandapower follows the following structure: 1pandapower.create_bus(net, vn_kv, name=None, index=None, geodata= ,→None, type=’b’, zone=None, in_service=True, max_vm_pu=nan, ,→min_vm_pu=nan, coords=None, **kwargs)
38 Figure 3.3: Bus equivalent circuit (53) Broadly speaking, there are three types of buses: 1. Slack Bus: This is the reference for power calculations in the network. It is typically the connection point of the generation and is therefore the origin of phases (θ=0). 2. PV Bus: This is a connection bus. It is used to model generators, which have known powers and voltages. The angle is not one of the input parameters. 3. PQ Bus: It is the bus to represent loads that consume both active power (P) and reactive power (Q). In this case, neither voltage nor angle are input parameters. 3.3.1.2 Generator Model Generators represent active power sources. They are represented as controlled PV buses where both magnitudes must be input data. They often have the slack condition implicitly defined , meaning they have the ability to balance the grid. The code is: 1pandapower.create_gen(net, bus, p_mw, vm_pu=1.0, sn_mva=nan, name=None, ,→index=None, max_q_mvar=nan, min_q_mvar=nan, min_p_mw=nan, max_p_mw ,→=nan, scaling=1.0, type=None, slack=False, controllable=nan, vn_kv ,→=nan, xdss_pu=nan, rdss_pu=nan, cos_phi=nan, in_service=True)
39 Figure 3.4: Generator equivalent circuit (53) 3.3.1.3 Load Model The load is directly designed as an active power sink, meaning a positive value indicates power absorption, while a negative power value indicates generation. Loads require as input the connection point (the bus) and the power, both active and reactive. Depending on the phase difference between voltage and current of a load, it will have either inductive or capacitive character. In a capacitive load, the current leads the voltage and therefore the reactive power is negative; for an inductive load, the opposite occurs. An alternative way to introduce reactive power is to input the power factor, where: PF =cos(θ) = P S=P U·I(3.1) Like in the other cases, the formulation is: 1pandapower.create_load(net, bus, p_mw, q_mvar=0, const_z_percent=0, ,→const_i_percent=0, sn_mva=nan, name=None, scaling=1.0, index=None, ,→in_service=True, type=’wye’, max_p_mw=nan, min_p_mw=nan, ,→max_q_mvar=nan, min_q_mvar=nan, controllable=nan, **kwargs)
40 Figure 3.5: Load equivalent circuit (53) 3.3.1.4 AC Line Model The line requires additional input parameters, such as the connecting buses or the electrical parameters of the line (resistance, capacitance, or inductance). Additionally, it is necessary to define a maximum current limit that the line can withstand, as this is a decisive factor in sizing It is worth mentioning that PP does not distinguish whether the line is singlephase or three-phase, and therefore, for three-phase line cases, it is necessary to introduce 3 lines. In this case, the main code for defining the line is: 1pandapower.create_line_from_parameters(net, from_bus, to_bus, length_km, ,→r_ohm_per_km, x_ohm_per_km, c_nf_per_km, max_i_ka, name=None, ,→index=None, type=None, geodata=None, in_service=True, df=1.0, ,→parallel=1, g_us_per_km=0.0, max_loading_percent=nan, alpha=None, ,→temperature_degree_celsius=None, r0_ohm_per_km=nan, x0_ohm_per_km= ,→nan, c0_nf_per_km=nan, g0_us_per_km=0, **kwargs) The electrical schematic of high-voltage lines is shown in the Figure 3.6, which will be explained in more detail in subsection 3.3.2.
41 Figure 3.6: AC Line equivalent circuit (53) 3.3.1.5 DC Line Model For the case of the direct current line, the model is based on two generators. The power at one of the two ends is defined, while at the other end, it is the defined power minus the losses introduced in the mathematical model. These values are usually provided by cable and converter manufacturers at both ends of the line. Nowadays in PP, these lines are only capable of operating in one-directional flow and in steady state. Similar to AC lines, it is necessary to express the start and end buses, power, power losses (something not required in AC lines since the software calculates it based on electrical quantities), and voltages in P.u. 1pandapower.create_dcline(net, from_bus, to_bus, p_mw, loss_percent, ,→loss_mw, vm_from_pu, vm_to_pu, index=None, name=None, max_p_mw=nan ,→, min_q_from_mvar=nan, min_q_to_mvar=nan, max_q_from_mvar=nan, ,→max_q_to_mvar=nan, in_service=True) Figure 3.7: DC Line equivalent circuit (53)
42 3.3.1.6 External Grid Model This is an interconnection point with another network, which is modeled as a slack bus. It is only necessary to specify the connection bus where the slackness appears. The equivalent circuit is that of a voltage source, which has a magnitude of 1 . 1pandapower.create_ext_grid(net, bus, vm_pu=1.0, va_degree=0.0, name=None ,→, in_service=True, s_sc_max_mva=nan, s_sc_min_mva=nan, rx_max=nan, ,→rx_min=nan, max_p_mw=nan, min_p_mw=nan, max_q_mvar=nan, ,→min_q_mvar=nan, index=None, r0x0_max=nan, x0x_max=nan, ,→controllable=nan, **kwargs)) Figure 3.8: External Grid equivalent circuit (53) 3.3.1.7 Power Balance & Calculation Algorithm The power flow resolution in based in fundamental equations of the electrical engineering field, such as Ohm’s law, that related voltage (V), current (I) and resistance (R). V=I·R(3.2) If Ohm’s law is rewritten using admittance (Y) , instead of resistance (R) being admittance the inverse of the resistance, it’s possible to write current as follows: I=V·Y(3.3)
43 Apart from Ohm’s law, the well know Kirchhoff law, state that all the currents that enter in a node, i.e a bus, should be equal to all the currents that leave it. The sign criteria in this algorithm is the typical one; when there’s a current that enters the bus, will be positive; else, it will be negative. When the are two nodes that are connected, there must be a resistance, therefore admittance between them. If there are not connected directly, the value of this resistance tends to infinite, hence admittance is zero. If this is done with all the nodes of the system, the admittance matrix can be constructed. Y= Y11 Y12 . . . Y1N Y21 Y22 . . . Y2N . . ..... . . YN1YN2. . . YNN (3.4) It should be taken into account that is a symmetrical matrix, therefore Yij =Yji. In addition, the terms of the main diagonal will be the sum of all the admittance’s hanging from the same bus. This type of matrix is very favorable for resolution by numerical methods, which will be explained later. Once this is defined, the expression of the complex electric power is adapted with the vector equations, being the power: SK=VK·I∗ K(3.5) The term I∗ Kis treated as the complex conjugate of the current matrix, where: IK= N X j=1 Ykj ·Vj(3.6) Substituting in the initial equation and bearing in mind that the voltage is a phasorial magnitude and that the admittance matrix almost always has imaginary components (reactances or capacitance’s), the following development is performed:
44 SK=VK·( N X j=1 Ykj ·Vj)∗=VK· N X j=1 Y∗ kj ·V∗ j(3.7) SK=|VK|∠(θK)·( N X j=1 (Gkj +j·Bkj)·V∗ j·(|Vj|∠θj)∗(3.8) The terms Gkj and Bkj are respectively the real and imaginary parts of the admittance matrix. Using the common factor and the definition of complex conjugate it is obtained: SK= N X j=1 (|VK||Vj|∠(θK−θj)) ·(Gkj −j·Bkj)(3.9) In order to develop further, it is necessary to make use of Euler’s formula that relates the exponential, polar and binomial forms of complex numbers. SK= N X j=1 (|VK||Vj|(cos(θK−θj) + j·sin(θK−θj)) ·(Gkj −j·Bkj)(3.10) From this equation two equations can be divided depending on whether there is a complex term or not, thus obtaining the active power (P) and the reactive power (Q): PK= N X j=1 (|VK||Vj|(cos(θK−θj) + Bkj)·sin(θK−θj)(3.11) QK= N X j=1 (|VK||Vj|(sin(θK−θj) + Bkj)·cos(θK−θj)(3.12) For the resolution of this type of nonlinear system of equations, the Newton- Rhapson method is usually used, which is an algorithm for solving equations numerically, and where its order of convergence is quadratic. The resolution of this
51 Table 3.3: Generators for the Spain-France interconnection load flow analysis Name Power Generated [MW] Santurce Combined Cycle [SPA] 396 Amorebieta Combined Cycle [SPA] 786 Golfech Nuclear Power Plan [FRA] 2620 Le Blayais Nuclear Power Plan [FRA] 3640 Finally, 4 external networks are incorporated, whose function is to absorb or transfer both active and reactive power in order to ensure frequency and voltage stability in the network, according to the formulas explained in the subsubsection 3.3.1.7.
52 3.4 Economic Analysis 3.4.1 Introduction In economic terms, high-voltage DC systems are initially much more expensive, since they require power electronics equipment (the valve hall) that the AC variant does not need. In addition, this type of technology requires very high power transformers, which are also very expensive compared to ordinary transformers, mainly because these types of transformers must have high efficiencies, therefore low impedance, which is difficult to achieve when high apparent power is required. However, when transmission distances increase, the cost associated with HVDC technology is more competitive than HVAC, mainly because: 1. Losses: The losses in DC lines are only resistive, compared to capacitive and inductive losses in AC lines, which means that to deliver the same power, in the case of AC, more power has to be generated. In DC, film effects are avoided, with the effective resistance being higher than the ohmic resistance, and therefore generating more losses, as seen in Figure 2.3. Corona effect losses are also much lower. 2. Conductors: In HVDC, the number of conductors is smaller. In the simplest configuration, only one conductor is needed, compared to the three needed in traditional transmission technology. 3. Towers: In HVAC, the phases must be well separated so that the corona effect does not appear. In addition, due to the smaller number of conductors, the tower span is smaller, thus generating lower costs.
53 Figure 3.11: a) HVAC tower ; b) HVDC tower (33) The point at which the AC case becomes less interesting from an investment point of view than the DC case is the so-called break-even-point (BEP). According to (55), this value influences between 300 and 800 km for overhead lines, and between 50 and 100 km for submarine lines. In submarine lines, the increase of capacitive loads makes the losses much higher and this is why the BEP decreases. In the case of AC transmissions, the initial costs are primarily linked to the acquisition of power transformers, which are heavy equipment necessary to transform voltage levels from generation voltage to transmission voltage. In Figure 3.12, it can be observed that there are certain points where the slope experiences an offset; this is because when the lines are very long, capacitance and inductance increase, thus making the fraction of non-utilized power (reactive power) higher in the total or apparent power. To mitigate these effects, additional equipment must be installed, such as reactors or capacitor banks. To address these issues, equipment like SynCons or STATCOMs can also be installed, which are also very expensive. Furthermore, when comparing both slopes, it is evident that increasing the length of the line is more beneficial in the case of HVDC. This is due to several reasons: primarily, the lower number of conductors/cables required since the HVDC system is not three-phase; on the other hand, when transmission is at high voltage in the case of AC, the conductor diameter must be large to avoid skin effect, which
54 is not an issue in HVDC and therefore requires a smaller diameter. This is the main reason for the use of HVDC in bulk transmission. Figure 3.12: Investment vs Distance in HVAC and HVDC lines. Break-even-point From an economic perspective, a comparison of both technologies will be conducted, focusing on aspects such as the BEP or the payback period after making the investment. It should be noted that, being such a specific cost analysis with technology from which obtaining information is very complicated, a large number of assumptions will be made, with a clear understanding of the context in which it is carried out. The vast majority of the data will be extracted from a document prepared by the prestigious CIGR´ E, an organization formed by leading experts in electrical grid issues, and the document (36), which includes some of the most knowledgeable authors on HVDC technology. These authors come from various backgrounds including industrial field, with participation from technology companies like ABB or Siemens; experts from Nordic TSOs such as Stattnett or FINGRID, which are at the forefront of HVDC in Europe; and researchers from prestigious universities such as KU Leuven, among others. 3.4.2 Cost Analysis of the HVAC case Within a conventional high-voltage transmission AC installation, the following costs can be distinguised:
55 1. Substation Costs 2. Line Costs 3. Reactive Compensation Costs 4. Operation and Maintenance Costs (O&M) 3.4.2.1 Substation Costs In electrical substations the total cost is basically divided in four big categories: • Civil Works & Earthworks • High-Voltage Equipment • Control and Protection System • Labor Cost (Project Management, Site Management and Assembly) The high-voltage equipment pack includes all expenses related to the acquisition of high-voltage switch-gear, such as circuit breakers, disconnectors, measuring transformers, or power transformers. These pieces of equipment are very expensive since they are technological products that must be prepared to interrupt the line in case of faults, such as short circuits, overvoltages caused by generation/demand fluctuations, maintenance, etc. Another significant expense in substations are civil works. A substation requires specific characteristics, where the ground must be suitable for the foundations to perform their function effectively. It is important to remember that a power transformer can weigh up to 350 tons or even more. This is one of the economic items that fluctuates the most depending on the project, as in a particular area, it may require special requirements. For instance, the need for piles due to poor soil conditions, the necessity of a platform to properly drain water when the substation is in an area with heavy rainfall, etc. The protection and control component is another significant expense within substations, as it encompasses all protection relays and the control system, which
56 monitors everything that occurs within the analysis zone of that substation. Additionally, there is coordination with neighboring substations, which must communicate in case a fault occurs between them. In the report presented by CIGR´ E (36), it is indicated that for substations of 1000 MW capacity, the cost of the substation is around 28 million euros; with a substation at each end, which would amount to 14 million euros each. Given that the reference prices are from a report published in 2012, it is necessary to apply a correction factor to adjust the price due to the inflation. In the Figure 3.13, we see the trend that inflation has followed both in Europe and particularly in Spain. Currently, the rate is around 3.1%, whereas in 2012, it was 2.87%; this will make current prices approximately 0.23% higher, placing us in a rather basic scenario. The prices of technological products, such as high-voltage equipment, can fluctuate rapidly, and depending on the geographic area, they may increase more or less, as it depends on countless factors. Figure 3.13: Spanish and European inflation rate over time (7) 3.4.2.2 Line Costs The cost of the transmission line is undoubtedly the largest and also the one with higher risk. This cost is highly dependent on the topography; the most favorable situation is in flat areas with minimal vegetation where practically no clear-
57 ing tasks are required. For the case of the HVAC connection between Gatika and Cubnezais, it will be carried out using aluminum conductor reinforced with steel (ACSR). In the (36), the overall estimation per kilometer for a 1000 MW value is shown. Since for the considered case study, the power is 2000 MW, it has been estimated that the cost is double, as the diameter of the conductor needed increases with higher power. With all this, it is estimated that the cost is 0.66 M€euros per kilometer, to which an additional 0.12 M€per kilometer must be added due to the presence of a bundled conductor. Furthermore, since the route will be along the coast of the Gulf of Biscay, the total cost is increased by 20% as recommended . In this case, to attempt to assess the actual cost currently, the fluctuation in raw materials has been examined. The Drake conductor considered has a ratio of 26/7 in favor of aluminum (provides conductivity) compared to steel (provides resistance). Therefore, it is weighted by the contribution of each material for the calculation of the total fluctuation. Table 3.4: Comparative prices of aluminum and steel 2012/2024 (1) Aluminium Steel Price April 2012 [$/ton] 2080.6 4264.5 Price February 2024 [$/ton] 2184 3773 Difference [%] 4.97 -11.53 Weighted Ratio [%] 1.47 3.4.2.3 Reactive Compensation Costs Reactive power is a part of the power consumed by inductive devices such as motors, coils, or transformers. When reactive power is excessive in the grid, stability issues may arise, and the efficiency of the grid decreases, as this power does not perform useful work. In the HVAC network, power transformers are significant consumers of reactive power, and high-voltage lines (OHL) also consume this type of power. The longer the conductor span, the more reactive power is consumed, and therefore, compensation is required. This compensation is achieved using devices such as capacitor banks, filters, or STATCOMs.
58 Normally, there is a specific point, as shown in Figure 3.12 where these types of equipment are decided to be installed; this point may depend on the distance of the connected lines, the types of loads, etc. Since this is a decision that will require specific engineering calculations and grid quality data, it will be assumed that the investment for this type of equipment is linear. The reactive power value to be compensated varies since it is usually a specific requirement of each electrical grid. In the estimation provided by (36), it shows an upper bound of twenty-one thousand euros per kilometer. It will be assumed that this is the current value since the requirements are becoming stricter to ensure a resilient network. Additionally, similar to the substations case, to adapt it to the current context, the inflation factor mentioned earlier is applied. 3.4.2.4 Operation and Maintenance For the case of operation and maintenance costs, it has been estimated that for HVAC lines, the maintenance cost is 2% of the total cost of the transmission line. This cost is derived from insulation film renewal tasks, laser scanning to assess the condition of the conductors, vegetation cleaning that could pose a threat to future short circuits, inspection of insulators and chains, etc. 3.4.3 Cost Analysis of the HVDC case In the case of an HVDC installation, the main breakdown is the same as in the previous case, but the costs are different. 3.4.3.1 Substation Costs In this case, the substations apart from having all the switchgear necessary in a substation, there are converter stations. These stations are located at the ends of the line and represent an important cost of the installation; in addition, there is a DC part, which is the one that integrates all the switchgear for the control of the power flow in the DC field.
59 The converter stations require special buildings, since the valves usually hang from the ceiling and require large building heights (about 10 meters); they also need a large span, since there can be no intermediate columns and therefore, a large delta beam is required, as shown in the Figure 3.14. Figure 3.14: Delta beam necessary for buildings with wide spans. Another cost that greatly increases the price is the cooling system. The valves, being composed of IGBT’s, are high switching devices that generate a lot of heat, that is why for proper operation a high priced forced cooling system must be installed, with a specific liquid and high performance heat exchangers, For the estimation of the cost price of an HVDC substation, a situation of linearity of the total cost can be assumed, given that these are modular solutions. In (36), it is stated that for a 1x1000 MW configuration, the cost of both can be assumed to be 90 M€for a pair of substations (each end); in our case, being a two-pole configuration, the cost will be double, since a two-pole must have two independent buildings, two DC yards, two DC yards, and two transformers. Converter stations are a very technological product where prices should not be updated only with the reference of inflation . Being a market where there are few competitors, the costs are very high due to the oligopolistic nature. In addition, these electronic products are manufactured with materials that often belong to the critical raw material (CRM) group which are limited and can have rapid price fluctuations and high values. This is something that manufacturers take into account when signing an EPC contract for projects that will be between 3 and 5 years ahead, so to minimize the
60 risk, margins are usually large to be able to absorb a possible price fluctuation at the time of purchase of the components. Accounting for the price increase since the (36) data was taken is somewhat complicated, since it depends on many factors, such as the power of the converters, the technology of the converters, the type of configuration, the length of the span, etc. In the Hitachi Energy report (42), it is stated that in the 2020-2025 scenario a price increase of 11% is expected, while for instance in the information provided by REE (23), it is said that the new Mainland - Baleares link will cost between double and triple with respect to the Romulo project, commissioned in 2011; the Romulo link is based in LCC technology while new one is VSC, so they cannot be compared directly. That is why the assumption of a 66.65% price increase will be made. 3.4.3.2 Transmission Line Costs Underground cables are much more expensive than a simple conductor, mainly due to the insulation they require; the cable is completely covered to minimize losses and ensure proper operation. HVDC cables have a slightly lower cost than HVAC cables, primarily because the insulation is less; since alternating current fluctuates over time, it can experience phenomena such as the aforementioned corona effect or the losses linked to large capacitive loads when the has an underwater path, which is why underwater HVAC is not usually selected, except for short sections where building converter stations is not profitable and the traditional option is preferred. The laying of submarine cables also entails a significant cost, as special ships are used to lay them without intermediate joints, followed by cable burial, as explained in the Mallorca-Mainland Connection chapter. With all of this included, the estimate provided by (36) is 1.6 M€/km. This value aligns with what (39) shows, estimating only the cable value at 1.64 M€/km, so this value will be adopted. Again, the assumption of a 50% price increase, mentioned above, will be made.
67 As it has been seen, the addition of a new HVAC line does not substantially enhance interconnection capacity and a HVDC link offers greater network control, thereby enabling enhanced interconnectivity and bolstering resilience against operational variations. For this reason, this alternative is evaluated, obtaining the results shown in Table 4.4 Table 4.4: Results of lines with the Gatika-Cubnezais HVDC connection (Case B) between Spain and France at 400 kV From Bus To Bus Length [km] Loading [%] Power Flow [MW] 0 1 70 42.6 768.7 0 7 380 - 1000 0 7 380 - 1000 1 2 35 43.1 770.8 2 3 35 8.2 15.2 3 4 50 6.3 15.2 4 5 115 3.8 15.1 5 6 59 4.9 15.1 6 7 54 7.6 15.1 7 8 34 123.5 2239.7 7 9 162 46.4 825.3 9 10 47 97.3 1794.7 10 11 38 64.4 1140.1 11 12 39 63.8 1135.1 12 13 58 63.2 1130.0 13 14 57 62.4 1122.6 14 15 65 - 1000 14 15 65 - 1000 14 16 104 49.8 892.5 15 16 62 108 1958.0 In this case it can be seen how there is a large power exchange, reaching 4991.6 MW, thus contrasting what was presented in chapter 3.The implementation of such a link facilitates improved integration of renewable energy sources by enabling the evacuation of large energy volumes avoiding the need to enter into situations of curtailment. The exported power is much better distributed, being 42% at the Basque end compared to the 8% that appeared in the case of an extra HVAC line. As a result of
68 the simulation, a much more uniform interconnection profile is observed, reaching substantial interconnection capacities of almost 5 As for the losses issue, it is slightly higher than the current grid case, since the converters of the HVDC link present singular losses in the converter due to the switching process and in the line, although very low, of 2.1% of the transmitted power, hence its potential advantage. When the Gatika-Cubnezais link was introduced, the same thing happened as in the Baixas-Santa Llogaia link. When such amounts of power arrive, the line that evacuates all this power is saturated, in this case up to 123.5%. It is normal that the value is even higher, since there are nuclear power plants on buses 8 and 9, adjacent to bus 7, which is where the HVDC line arrives, then the amounts of energy are enormous. To solve this problem, the solution would be to use a larger conductor or increase the number of circuits. 4.1.4 Comparative Analysis In view of the limitations of the transmission grid in the interconnection with France, leaving Spain in a situation of islanding and with the objective of reducing this weakness in order to be part of the European grid and thus have a grid with very good frequency and voltage stability, the two solutions already mentioned were presented: • Duplicate the HVAC connection in the western part of the border. • Installation of an HVDC link between Gatika and Cubnezais. The most influential comparative values of both solutions are presented in the following table:
69 Table 4.5: Global comparison of the three case Case 0 Case A Case B Active Power Losses (P) [MW] 148.2 125 162.7 Reactive Power Losses (Q) [Mvar] -537.7 -1043.9 -496.6 Median Current in the system (IK) [kA] 0.2 0.3 0.4 Interconnected Power [MW] Catalonia 2648.1 2981.0 2850.5 Basque Country 73.1 153 2141.1 Total 2721.2 3134 4991.6 It can be seen how the HVDC solution is the best in terms of interconnection capacity, improving the HVAC solution by 59%. In terms of current through the lines, all three are adequate solutions because they have average values of at most 0.5 kA, when the conductor has a rated current up to 0.9 kA. In HVDC links a lot of power is accumulated to evacuate and that is the reason why there are saturation zones, but they are easily solvable. In terms of active power losses, at first glance, the parallel HVAC line solution (Case A) appears to be the most advantageous. However, it’s imperative to consider the interconnection capacity to accurately compare both scenarios. In this instance, it’s evident that the HVDC option (Case B) delivers superior ratios, resulting in higher efficiency with a 3.25% loss based on interconnection power, compared to 3.98% for the variant utilizing a parallel HVAC line (Case A). The base case exhibits the least favorable ratios, with losses amounting to 5.44% of the interconnected value. In the case of reactive power, the most critical case is the double HVAC line, which is logical since it is the one with the most conductors; HVDC is the best option since it is a technology in which the current is direct and therefore there are no losses related to reactance. This reactive power dissipation is detrimental to the system, since this type of power is necessary to maintain voltage levels and can cause high currents, flicker or reduction of the power factor. Therefore, it can be confirmed that technically, the best option is the HVDC link between Gatika and Cubnezais ahead of the implementation of a backup HVAC network to the current one.
70 4.1.5 Advantages of HVDC - Practical Cases In this section the idea is to see numerically the advantages that this HVDC link produces when transporting energy in situations that can be seen in everyday life. Among others, the following will be mentioned: 1. High penetration of renewables, and sudden drop in production; French grid support to Spain. 2. Renewable surplus in Spain expected, French nuclear power plants lower their output. The first scenario is simulated, in which the production of renewable energy is maximum in Spain. Currently Spain has an installed power of 125.6 GW, of which more than 60% corresponds to renewable installations. At times when penetration, i.e., generation comes almost entirely from renewables, the grid is fragile since environmental variation (wind, sun, etc.) influences a rapid change in the generation profile. There are several possible situations in which this type of case may occur, for instance, the wind blows so strong that it reaches cut-out speeds and therefore disconnects from the grid; the entry of a large amount of clouds above a photovoltaic plant where it reduces production to a minimum, etc. When this penetration is at its maximum, generation by traditional means, such as combined cycle power plants (CCPP), reaches minimum values. These are fastacting plants that are put into operation to meet high demand situations, but they are not instantaneous, as could be the case with hydroelectric plants or the international link with France. In the case of nuclear plants, changes in generation must be very slow and coordinated, since the morphology of the reactors does not allow for uncoupling without a high degree of control.
71 Table 4.6: Results of lines between Spain and France at 400 kV when there is a drop in renewable (0% CCPP) generation and there is an inter-network back-up From Bus To Bus Length [km] Loading [%] Power Flow [MW] 0 1 70 145.7 2641.1 0 7 380 - 1000 0 7 380 - 1000 1 2 35 146.1 2665.1 2 3 35 153.7 2691.6 3 4 50 154.5 2729.9 4 5 115 156 2819.4 5 6 59 156.6 2865.8 6 7 54 157 2908.6 7 8 34 91.3 1653.1 7 9 162 180.4 3320.2 9 10 47 158.6 2939.8 10 11 38 125.3 2261.5 11 12 39 124.8 2242.4 12 13 58 124.3 2222.9 13 14 57 123.4 2194.2 14 15 65 - 1000 14 15 65 - 1000 14 16 104 10.1 166.4 15 16 62 108 1958 Two situations will be simulated: first, the situation where the combined cycle power plants are not operating, which would simulate the moment of the sudden drop in generation; and the situation where the combined cycle plants are operating at 50%, which would be the point at which they are in the start-up transient providing half of their rated power. The results of the interconnected power as a function of the corridor are shown in Table 4.7 and Table 4.8. Table 4.7: Power flow in the Catalan 400 kV corridor in a renewable production drop in Spain Catalan Corridor 0% CCPP 50% CCPP Mainland [MW] 166.4 207.9 HVDC Link (Baixas-Sta. Llogaia) [MW] 2000 2000 Total [MW] 2166.4 2207.9
72 Table 4.8: Power flow in the Basque 400 kV corridor in a renewable production drop in Spain Basque Corridor 0% CCPP 50% CCPP Mainland [MW] 2780.1 2195.5 HVDC Link (Gatika-Cubnezais) [MW] 2000 2000 Total [MW] 4780.1 4195.5 The columns shown in Table 4.7 and Table 4.8 correspond to: • Drop status of renewable generation without operation of CCPPs. • Situation of drop of renewable generation once the CCPPs are already backing up but in the start-up transient (50 % Rated Power). Power flow in the corridors are maximized, with high power flows even in the mainland connections. It is true that there is a saturation of the lines, as can be seen in Table 4.6,reaching an average value of 150% of their capacity; normally, these lines are built to withstand currents much higher than their rated capacity for short periods of time. The HVDC links are not saturated since they have transformers at the valve room entrances that limit the power that can pass through them. For the case of surplus renewable energy and the anticipated decrease in production in France, it’s the same idea, except that the power flow would go in the opposite direction. As a result, it can be seen how in situations where there is uncertainty associated with renewables, HVDC gives a substantial advantage, allowing a large power flow and backing up the grid.
73 4.2 Economical Comparison In this section, the economic results of both scenarios will be displayed. It is important to have understood the assumptions, as argued in the Economic Analysis chapter. 4.2.1 Economic Viability - BEP When choosing which technology should be implemented in the transmission network, there can be both technical criteria and economic criteria. When it comes to bulk transmission, where the objective is simply to transport energy between two points, the choice of either HVAC or HVDC technology is defined by profitability. HVDC, as discussed on numerous occasions, represents a product with a large initial investment, primarily due to converter stations; however, it requires lower costs in electrical infrastructure (such as high-voltage towers) and lower costs in the transmission medium. In HVDC, only one cable is employed, compared to the three conductors required for an overhead transmission line, both technologies in their most basic version, as if the number of circuits is expanded, this changes. Three scenarios have been proposed: 1. HVAC link 2. Monopolar HVDC link 3. Bipolar HVDC link After applying the assumptions mentioned earlier, in order to obtain a realistic value of unit prices, given that those found in (36) are from 2012, which can be summarized as: • Increase in labor costs or reactive compensation equipment costs linked to inflation. • Increase in conductor costs linked to the fluctuation of aluminum and steel.
74 • Increase in converter stations and DC cable costs linked to market demand and lack of competitiveness. When analyzing which solution is more economically interesting depending on the distance, in Figure 4.1 it can be seen how it fluctuates. 0 100 200 300 400 500 600 0 500 1000 1500 2000 2500 3000 3500 HVAC HVDC Monopole HVDC Bipole Figure 4.1: Total cost versus distance of the Gatika-Cubnezais Case of Study. BEP It can be seen how the highest initial investment is the one that includes the solution with a HVDC in bipolar configuration, then the monopolar configuration and finally the HVAC solution; this is within the expected, given that the converter installations have enormous costs, so much so that if the HVAC variant is compared with the bipolar HVDC, a difference of 221.5% of the price can be observed. Although it may seem that the initial costs of single-pole HVDC and HVAC are the same, this is not the case, since there is a difference of 90.9 M€between them.
75 The truly interesting thing about this graph is at what points does the HVDC monopolar option start to be more interesting in terms of investment. If we analyze both graphs, we see that from kilometer 342 onwards it becomes a more interesting option, the so-called break even point (BEP). This result is very interesting because most of the literature makes estimates of the BEP, but in most cases, they compare two underwater alternatives or two alternatives via land. In this case, two completely different solutions are compared, demonstrating the potential that HVDC has for this type of interconnections. Table 4.9 below shows the unit costs that have been considered for this analysis. Table 4.9: Unit prices for each solution Unit Prices HVAC Monopolar HVDC Bipolar HVDC Type of Price Substation [M€]. 56 90 180 Fixed Transmission Line [M€/km]. 2.376 1.6 3.2 Variable Extra Bundle [M€/km]. 0.432 0 0 Variable Reactive Compensation [M€/km] . 0.035 0 0 Variable O&M [M€/km]. 0.056 0.46 0.91 Variable It is important to mention that these unit prices are those considered for the case of 2012, therefore, to extrapolate them to 2024, it is necessary to make the hypothesis of inflation and price increases in the HVDC equipment already mentioned on several times. Therefore, it can be seen that in the case of the Gatika-Cubnezais link, the scenario of setting up a HVDC bipole is not a competitive option compared to the HVAC variant or to the HVDC monopole, and even so, it is the option that will be implemented. This shows how the decision not only takes into account economic aspects, but also the technical aspects play a major role. The advantage of implementing a bipole is mainly reliability; even if there is a failure in one of the converter stations, transmission is not interrupted and it is possible to operate in monopole mode. This increase in availability is key for this strategic link. The possibility of evacuating in times of power surplus, importing in situations of shortage or being able
76 to compensate for fluctuations in the network is key to having a strong grid. 4.2.2 Economic Impact. HVDC vs HVAC Once the profitability analysis has been made according to the distance, it is convenient to study in depth the specific results for this project. It is important to note that the cable laying distances in both comparisons are not the same, since by sea, although it is necessary to go around a lot to avoid Capbreton canyon, as mentioned on several occasions, is 390 km, while for the case by land, 436 km have been counted. The results are thus as follows, broken down into the most important items: Table 4.10: Total price breakdown for the Gatika-Cubnezais case of study HVAC Monopolar HVDC Bipolar HVDC Substation [M€]. 56.1 149.9 299.9 Transmission Line [M€]. 1051.2 1039.9 2079.7 Extra Bundle [M€]. 191.1 0 0 Reactive Compensation [M€] . 15.3 0 0 O&M [M€]. 24.5 2.95 5.9 Total Cost [M€] 1338.26 1192.83 2385.6 The estimates can be contrasted because (22) indicates that the award price is 2390 million euros, so the hypotheses are contrasted. A breakdown of the total price of the chosen option, i.e. the HVDC bipole, shows that it is distributed as shown in Figure 4.2. In addition, according to (3), 1000 million cost overrun is expected between the two-pole option of HVDC and the conventional HVAC line, which reinforces the cost model.
83 of the project had to be delayed as numerous studies needed to be redone and the consequences of the new route analyzed. All of this was communicated to the manufacturers, who adjusted their designs based on the client’s requirements, namely, INELFE. The awarding to the Hitachi Energy - Vinci consortium for the development of converter stations and NKT Cables and Prysmian for the cables, initially estimated to cost a total of 1750 million euros, escalated to 2390 million euros (22). This created conflicts between the market regulatory organizations, the Spanish CNMC and the French CRE, which held multiple negotiations to distribute the financing. Such projects are subject to significant fluctuation, which is why an additional risk provision is always included. In this case, it has been estimated at 310 million euros, nearly 13% of the total project cost. This cost overrun has been accepted by INELFE, mainly for the following reasons: • Saturation of construction materials production markets • Shortage of companies with both technical and technological capacity to provide the required solution. • Increase in the cost due to the change in the cable path • No further delay in the commissioning that could result in non-compliance with EU requirements. Regarding the negotiation meetings, it has been agreed that all cost overruns appearing in the project from the price of 2390 M€will be borne by REE at a rate of 62.5% compared to 37.5% for the French entity. This was a disagreement due to the fact that most of the laying was carried out in French territory; 68% compared to 32% in the Spanish . However, France is in a favorable situation compared to Spain and is not so dependent on this link. France has a greater number of international interconnections and is less isolated than Spain; so the Iberian nation has a larger competitive advantage.
84 In addition, as Spain is exporting country, the income from energy exchanges is greater than in the case of France, which has a much more stable and planned generation as it is based on nuclear power, unlike Spain, which has large generation peaks thanks to the large penetration of renewables, which need to be evacuated in order not to incur a curtailment.
Chapter 5 Conclusions The main objective of this work was to verify the possibility of implementing a high-voltage direct current network in Spain; something that has been on the rise in European countries for years, thanks to the advantages it brings: improved efficiency, reduction in the use of towers and fewer conductors, among others. All this has been achieved thanks to the case study of the Gatika-Cubnezais link in the Bay of Biscay, a project that is currently in the early stages of construction. Thanks to the load flow analysis that has been carried out, it has been shown that HVDC technology is a variant that allows a high transmission capacity with neighboring countries, thus creating a much more interconnected and therefore stronger grid in an efficient way thanks to its low losses. In addition, thanks to the power electronics devices that make up the converter units, a much more flexible electrical grid is achieved in the case of changes and with much greater control. Submarine cables have a unity power factor, so all the energy generated is used, except for the losses generated in the converter stations and in the line, which are minimal. It has been possible to see how in the comparison between subsea HVDC and the mainland HVAC extension option along the Basque coast, the HVDC option allows achieving interconnection capacities of nearly 5 GW, doubling the capacity of the current grid, which is only 2.7 GW, getting closer to the European Union’s goal, which sets that 10% of installed capacity must be interconnected. In the economic aspect, an analysis of which of the three options, between HVDC bipole, HVDC monopole and HVAC, was the most suitable was carried 85
86 out. It was seen that for the length studied between Gatika and Cubnezais the most suitable option was the HVDC monopole, while the one under construction is the bipole. This is a reasonable decision, since the decision has not been made purely on economic aspects; from a technical point of view, a bipole offers much more availability than a monopole, guaranteeing a continuous service even in the event of revisions or failures that may occur in the link. In terms of investment, it has also been shown that the project is a highly profitable option in a 25-year scenario; the support of the EU, the sharing of costs with France and the expected income from congestion fees with the French TSO are key points that allow for a profitability of almost 2500 M€. In addition, an environmental analysis of the implications of such a project has been carried out, showing that, although it is a submarine cable laying, it does not have a much greater impact than a traditional overhead line, thanks to the latest technologies which minimize visual impacts and interfaces with wildlife or humans. Finally, a budget analysis has been made of what the development of an academic work of this magnitude has meant, showing a timeline and a detailed analysis of the tasks carried out. An analysis of how the project affects social equality and gender issues has also been included. 5.1 Future Work One of the proposed future lines would be the realization of a more complex meshing of the system, including more number of loads and generators and adding different voltage levels; it would be interesting the modeling in specific professional software that would allow to have a graphical interface more suitable for the study of power flows. In addition, it would be interesting to perform a dynamic analysis of HVDC links, particularly the case of Gatika-Cubnezais and how this type of technology behaves in the face of rapid changes in generation and demand.
Appendix A Environmental Assessment This section analyzes the environmental impact of the installation of each of the proposed cases of study. It will be broken down into two chapters, where in the first instance the environmental impact of the HVDC and HVAC solutions will be compared in general terms and then a detailed study of each solution will be performed. A.1 Overall Comparison Both types of transmission have a very different environmental impact. Among all the aspects to consider, the following will be detailed: 1. Visual Impact 2. Cable Types and Laying 3. Energy Efficiency and Potential Losses 4. Interaction with fauna and flora 5. Converter Stations and Substations 6. Electromagnetic Fields and interaction. 87
88 Concerning visual impact, HVDC prevails over HVAC; although it is true that the substations are larger, as they must accommodate a converter building and DC switchyards, the number of cables is fewer, and some key infrastructure such as high-voltage towers which are the infrastructures that generate the greatest visual impact, that in the case of the HVDC link are not necessary. Regarding the wiring, once again, HVDC stands out as the winner since it is a technology that uses a smaller number of conductors. It is true that it depends on the type of configuration, as for example, the monopole with earth return only consists of one power cable, but a symmetric bipolar configuration usually consists of 2 power cables and one return cable. Furthermore, the cables used are insulated and have several layers such as armor, shielding, or insulation. These insulators are often made of thermoset materials that are sometimes difficult to recycle. However, although HVDC installation may even be worse in terms of cabling, it is a variant with better energy efficiency, resulting in a lower amount of wasted energy. Another important issue to be addressed concerns electromagnetic fields, which are minimized with HVDC solution, due to the fact that the cables have both insulation and shielding, this minimizes this effect. As the converter station is bunkerized and in the form of a Faraday cage, it has electromagnetic protection without influencing the environment. Once this is explained, the analysis moves on to specifically examine each proposed solution. A.2 Case A: Extra HVAC Connection The environmental impact of the construction of a new line has many milestones to consider . Mainly, these are associated with: • Civil Works • Conductor Laying
89 • Collection of materials and lifting In civil works tasks, foundations must be made for high voltage towers of 400 kV, which have considerable volumes of concrete which vary depending on the design of the tower carried out by detailed engineering. . These foundations are reinforced and it is necessary to ground all the rebar, with the environmental impact that this generates. In addition to all this, a large collection of materials must be made close to the foundation to proceed with partial assemblies and then hoist them in sections for the structure. In order to do this, it is normally necessary to clear the land and create a temporary road so that the cranes can access it. After that, a lot of machinery is needed for laying tasks, such as cable dogs, winches or tensioners. In these laying tasks, large stockpiles of conductor coils are made, therefore it is also necessary to carry out clearing work at the base of the tower. When passing through areas where access is difficult, the laying must be done with a helicopter. All these works must be done on each of the high voltage towers; The distance between each of these is variable since it depends greatly on the orography, but it can be estimated that it is between 500 and 1000 meters, which is why an average value of 750 meters will be considered. Knowing that the towns of Gatika and Cubnezais are 418 km apart, it is obtained around 558 high voltage towers. The environmental cost that this generates is enormous; especially considering that there are laying areas that pass through natural parks such as Landes de Gascogne. In addition, these towers influence the fauna, especially the habitat of migratory birds although the impact it has compared to that of HVDC on marine fauna is minimal. Furthermore, a study from the University of Bristol (18) indicates that living near this type of high voltage towers (≤100 m) is correlated with an increased possibility of experimental cancer.
90 A.3 Case B: HVDC Connection; Gatika -Cubnezais Link The installation of an underwater cable is always a project that generates a lot of controversy at an environmental level, mainly motivated by the influence it has on marine flora and fauna. This project will begin with the expansion of the substation, adding more positions and creating a space to install the valve hall. This will require typical substation construction work such as earthworks, drainage, extension of the perimeter fence, cable channels and the construction of foundations for the buildings that will house the converters. The construction will have potential effects, especially during the construction phase, such as effects on fauna, people and the landscape, as well as generating light and noise pollution. Once built, in the operation phase, the effects are greatly reduced. Currently, there is a high voltage line connection between the Gatika substation and the dismantled Lem´ oniz nuclear power plant (the entrance area of the HVDC cable) and this location was proposed to house the converter station and thus save all the civil works to be done in Gatika. This OHL could be recommissioned to feed the Gatika substation; however, since the power plant didn’t reach the minimum free surface area required to build a converter station here, the option was discarded. Thus, the 49 high-voltage pylons that are still installed between Gatika and Lem´ oniz will be dismantled, thus eliminating the visual impact. It is worth mentioning that the valves have a great impact on the generation of electromagnetic fields, however, as mentioned above, the buildings are in the form of a Faraday cage, minimizing this impact. After leaving the substation there is a section of subterranean cable for which a double trench (one for each power cable) has to be dug up to the coast. The environmental impact of all this is not too great; during construction, earthworks are necessary (with all the machinery that this requires), but once commissioned they can only affect the natural drainage network, which can be varied during
91 construction. In addition, this cable has a multi-layered insulation layer that allows the magnetic field to remain inside the cable, without any external impact. Figure A.1: Subterranean cable on Gatika - Cubnezais case and interface with the environment (25) The laying of these cables is done every approximately 1 kilometer, joining them together in junction chambers that will also be buried once all the work is done. In the following image you can see how the visual and environmental impact is minimal. Almost 70% of the trench runs along existing roads, thus minimizing the impact. When there are conflict situations, such as road crossings, river crossings, etc., what will be done is a horizontal drilling with a driven pipe, thus minimizing any interface.In order to have the least possible impact, the entrance to the sea is also made by means of horizontal perforations and is buried up to approximately 1 kilometer from the coast, where it is placed on the seabed. This type of technique requires specific machinery, but no access must be made since the starting points of the drilling are already existing roads or areas.
92 Figure A.2: Directional drilling Once on the seabed, the cable is laid using the special boats discussed in previous chapters. The impact of the cable on the marine ecosystem is minimal thanks to the cable burial process, as seen in Figure 2.5 and is only affected to a certain degree during the construction phase. In addition, the route by which the cable is laid minimizes interaction with the most important fishing grounds in the area. The submarine cable can be seen in Figure A.3 During the cable laying stages, there is an impact on fishermen who will not be able to anchor in areas where the cable is being laid. However, as the route avoids the main fishing grounds, the impact should be minimal. Figure A.3: Subsea cable on Gatika - Cubnezais case and interface with the ocean environment (25) On the seabed it has a great impact despite the use of the cable cover, since it alters the acoustic levels, can modify the chemical conditions of marine sediments, affects the habitats of animals and a long list of others, Therefore, during the construction phase, water quality must be monitored at all times, as well as the quality
99 Figure C.1: Women in energy sectors (5) It can be observed that the oil gas variants has much lower ratios, over 22%, while photovoltaics reach 40%. This gap is gradually narrowing because companies are adopting policies prioritizing aspects such as: • Pay Equality. • Gender Balance within the team. • Inclusive Language. • Favourable workplace practices. • Childcare facilities. • Etc. Thanks to these policies, the percentages between men and women will become more balanced, leading to improved rates of equality within the sector.
Appendix D Load-Flow Analysis of Gatika-Cubnezais Case of Study Listing D.1: Current Grid Model - Case 0 1## CASE 0 2reset -f 3clear() 4 5import math 6import numpy as np 7import pandapower as pp 8import pandas as pd 9import copy 10 import matplotlib.pyplot as plt 11 import os 12 import pandas as pd 13 #--------------------------------# 14 #--------------------------------# 15 16 #-------DEFINITION OF THE GRID-------# 17 18 #-------Creation of buses-------# 19 20 net = pp.create_empty_network() 21 22 bus0= pp.create_bus(net,name = "b0", vn_kv=400) #Gatika Site ,→(0) 23 bus1= pp.create_bus(net,name = "b1", vn_kv=400) #Azpeitia ,→Site (1) 100
101 24 bus2= pp.create_bus(net,name = "b2", vn_kv=400) #Hernani ,→Site (2) 25 bus3= pp.create_bus(net,name = "b3", vn_kv=400) # I r n Site ,→(3) 26 bus4= pp.create_bus(net,name = "b4", vn_kv=400) #Argia Site ,→(4) 27 bus5= pp.create_bus(net,name = "b5", vn_kv=400) #Cantegrit ,→Site (5) 28 bus6= pp.create_bus(net,name = "b6", vn_kv=400) #Saucats ,→Site (6) 29 bus7= pp.create_bus(net,name = "b7", vn_kv=400) #Cubnezais ,→Site (7) 30 bus8= pp.create_bus(net,name = "b8", vn_kv=400) #Le Blasai ,→Site (8) 31 bus9= pp.create_bus(net,name = "b9", vn_kv=400) #Donzac Site ,→(9) 32 bus10= pp.create_bus(net,name = "b10", vn_kv=400) #Lesquive ,→Site (10) 33 bus11= pp.create_bus(net,name = "b11", vn_kv=400) #Verfeil ,→Site (11) 34 bus12= pp.create_bus(net,name = "b12", vn_kv=400) #Issel ,→Site (12) 35 bus13= pp.create_bus(net,name = "b13", vn_kv=400) #Gaudiere ,→Site (13) 36 bus14= pp.create_bus(net,name = "b14", vn_kv=400) #Baixas ,→Site (14) 37 bus15= pp.create_bus(net,name = "b15", vn_kv=400) #Sta. ,→Llogaia Site (15) 38 bus16= pp.create_bus(net,name = "b16", vn_kv=400) #Vic Site ,→(16) 39 40 41 #-------Creation of lines-------# 42 43 epsilon_0=8.854187817*math.exp(-12) #Constant value 44 45 #Cable Characteristics 46 47 GMR=(11.43/1000) #Geometric Mean Radius (Function of the ,→type of cable) 48 GMD=5 # Geometric Mean Distance Between the Phases (Dab*Dbc* ,→Dca)ˆ(1/3) 49 d= 0.2 #Distance between bundle conductors (m) 50 D=(28.14/1000) #Diameter of the conductor (m) 51 r=D/2 #Diameter of the conductor (m)
102 52 53 r_eq=(d**(2-1)*r)**(1/2) #Equivalent radius 54 55 r_single_AC=88.4/1000 #Ohm/km 56 r_single_DC=73.3/1000 #Ohm/km 57 x_single=0.337 #Ohm/km 58 c_single = ((2 *math.pi *epsilon_0) / (math.log(GMD/r_eq)) ,→)*math.exp(12) # Value in nF/km 59 60 r_double=r_single_AC/2 61 x_double=x_single/2 62 c_double=c_single/2 63 64 i_max=0.9 #Maximun current that the line allowes 65 66 #HVAC LINES- Duplex conductor for OHL. See the diagram. The ,→code is based in the number of the bus that arrives. 67 68 #Line (Phase R): 69 line11= pp.create_line_from_parameters(net,from_bus=bus0, ,→to_bus=bus1, length_km=70, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L01")# (0) 70 line21 =pp.create_line_from_parameters(net,from_bus=bus1, ,→to_bus=bus2, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L12")# (1) 71 line31= pp.create_line_from_parameters(net,from_bus=bus2, ,→to_bus=bus3, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L23")# (2) 72 line41= pp.create_line_from_parameters(net,from_bus=bus3, ,→to_bus=bus4, length_km=50, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L34")# (3) 73 line51= pp.create_line_from_parameters(net,from_bus=bus4, ,→to_bus=bus5, length_km=115, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L45")# (4) 74 line61= pp.create_line_from_parameters(net,from_bus=bus5, ,→to_bus=bus6, length_km=59, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L56")# (5) 75 line71= pp.create_line_from_parameters(net,from_bus=bus6, ,→to_bus=bus7, length_km=54, r_ohm_per_km = r_double,
103 ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L67")# (6) 76 line81= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus8, length_km=34, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L78")# (7) 77 line91= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus9, length_km=162, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L79")# (8) 78 line101= pp.create_line_from_parameters(net,from_bus=bus9, ,→to_bus=bus10, length_km=47, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L910")# (9) 79 line111= pp.create_line_from_parameters(net,from_bus=bus10, ,→to_bus=bus11, length_km=38, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1011")# (10) 80 line121= pp.create_line_from_parameters(net,from_bus=bus11, ,→to_bus=bus12, length_km=39, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1112")# (11) 81 line131= pp.create_line_from_parameters(net,from_bus=bus12, ,→to_bus=bus13, length_km=58, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1213")# (12) 82 line141= pp.create_line_from_parameters(net,from_bus=bus13, ,→to_bus=bus14, length_km=57, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1314")# (13) 83 line161A= pp.create_line_from_parameters(net,from_bus=bus14, ,→to_bus=bus16, length_km=104, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1416")# (14) 84 line161B= pp.create_line_from_parameters(net,from_bus=bus15, ,→to_bus=bus16, length_km=62, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1516")# (15) 85 86 87 #Line (Phase S): 88 line12= pp.create_line_from_parameters(net,from_bus=bus0, ,→to_bus=bus1, length_km=70, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L01’")# (16)
104 89 line22= pp.create_line_from_parameters(net,from_bus=bus1, ,→to_bus=bus2, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L12’")# (17) 90 line32= pp.create_line_from_parameters(net,from_bus=bus2, ,→to_bus=bus3, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L23’")# (18) 91 line42= pp.create_line_from_parameters(net,from_bus=bus3, ,→to_bus=bus4, length_km=50, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L34’")# (19) 92 line52= pp.create_line_from_parameters(net,from_bus=bus4, ,→to_bus=bus5, length_km=115, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L45’")# (20) 93 line62= pp.create_line_from_parameters(net,from_bus=bus5, ,→to_bus=bus6, length_km=59, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L56’")# (21) 94 line72= pp.create_line_from_parameters(net,from_bus=bus6, ,→to_bus=bus7, length_km=54, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L67’")# (22) 95 line82= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus8, length_km=34, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L78’")# (23) 96 line92= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus9, length_km=162, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L79’")# (24) 97 line102= pp.create_line_from_parameters(net,from_bus=bus9, ,→to_bus=bus10, length_km=47, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L910’")# (25) 98 line112= pp.create_line_from_parameters(net,from_bus=bus10, ,→to_bus=bus11, length_km=38, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1011’")# (26) 99 line122= pp.create_line_from_parameters(net,from_bus=bus11, ,→to_bus=bus12, length_km=39, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1112’")# (27)
105 100 line132= pp.create_line_from_parameters(net,from_bus=bus12, ,→to_bus=bus13, length_km=58, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1213’")# (28) 101 line142= pp.create_line_from_parameters(net,from_bus=bus13, ,→to_bus=bus14, length_km=57, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1314’")# (29) 102 line162A= pp.create_line_from_parameters(net,from_bus=bus14, ,→to_bus=bus16, length_km=104, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1416’")# (30) 103 line162B= pp.create_line_from_parameters(net,from_bus=bus15, ,→to_bus=bus16, length_km=62, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1516’")# (31) 104 105 106 #Line (Phase T): 107 line13= pp.create_line_from_parameters(net,from_bus=bus0, ,→to_bus=bus1, length_km=70, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L01’’")# (32) 108 line23= pp.create_line_from_parameters(net,from_bus=bus1, ,→to_bus=bus2, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L12’’")# (33) 109 line33= pp.create_line_from_parameters(net,from_bus=bus2, ,→to_bus=bus3, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L23’’")# (34) 110 line43= pp.create_line_from_parameters(net,from_bus=bus3, ,→to_bus=bus4, length_km=50, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L34’’")# (35) 111 line53= pp.create_line_from_parameters(net,from_bus=bus4, ,→to_bus=bus5, length_km=115, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L45’’")# (36) 112 line63= pp.create_line_from_parameters(net,from_bus=bus5, ,→to_bus=bus6, length_km=59, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L56’’")# (37) 113 line73= pp.create_line_from_parameters(net,from_bus=bus6, ,→to_bus=bus7, length_km=54, r_ohm_per_km = r_double,
106 ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L67’’")# (38) 114 line83= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus8, length_km=34, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L78’’")# (39) 115 line93= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus9, length_km=162, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L79’’")# (40) 116 line103= pp.create_line_from_parameters(net,from_bus=bus9, ,→to_bus=bus10, length_km=47, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L910’’")# (41) 117 line113= pp.create_line_from_parameters(net,from_bus=bus10, ,→to_bus=bus11, length_km=38, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1011’’")# (42) 118 line123= pp.create_line_from_parameters(net,from_bus=bus11, ,→to_bus=bus12, length_km=39, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1112’’")# (43)) 119 line133= pp.create_line_from_parameters(net,from_bus=bus12, ,→to_bus=bus13, length_km=58, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1213’’")# (44) 120 line143= pp.create_line_from_parameters(net,from_bus=bus13, ,→to_bus=bus14, length_km=57, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1314’’")# (45) 121 line163A= pp.create_line_from_parameters(net,from_bus=bus14, ,→to_bus=bus16, length_km=104, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1416’’")# (46) 122 line163B= pp.create_line_from_parameters(net,from_bus=bus15, ,→to_bus=bus16, length_km=62, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1516’’")# (47) 123 124 125 #HVDC LINES . Baixas-Sta Llogaia has a 2x1000 MW 126 127 singular_loss= (0.9/100)*1000*2#The losses are 0.9% of the ,→power of each valve hall. As there are one converter ,→and one rectifier (2). In MW
107 128 line_loss=0.3 # As it should be stated in percent 129 130 line15A = pp.create_dcline(net, from_bus=14, to_bus=15, p_mw ,→=1000, loss_percent=line_loss, loss_mw=singular_loss, ,→vm_from_pu=1.0, vm_to_pu=1.0, max_p_mw=1000,in_service ,→=True) #Cable from Pole 1 131 line15B = pp.create_dcline(net, from_bus=14, to_bus=15, p_mw ,→=1000, loss_percent=line_loss,loss_mw=singular_loss, ,→vm_from_pu=1.0, vm_to_pu=1.0, max_p_mw=1000,in_service ,→=True) #Cable from Pole 2 132 133 #-------Creation of generators-------# 134 135 gen1=pp.create_gen(net, bus0, p_mw=396, vm_pu=1.0,name="Gen1 ,→")#Santurzi CC 136 gen2=pp.create_gen(net, bus2, p_mw=786, vm_pu=1.0,name="Gen2 ,→")#Amorebieta CC 137 gen3=pp.create_gen(net, bus9, p_mw=2620, vm_pu=1.0,name=" ,→Gen3")#Golfech NPP 138 gen4= pp.create_gen(net, bus8, p_mw=3640, vm_pu=1.0, name=" ,→Gen3")#Le Blayais NPP 139 140 141 #-------Creation of loads-------# 142 143 load1=pp.create_load(net, bus0, p_mw=593.5, q_mvar ,→=593.5*0.1, name="Unitary Load")#Bilbao 144 load2=pp.create_load(net, bus10, p_mw=640.3, q_mvar ,→=640.3*0.1, name="Unitary Load")#Toulouse 145 load3=pp.create_load(net, bus7, p_mw=547.9, q_mvar ,→=547.9*0.1, name="Unitary Load")#Bordeaux 146 load4=pp.create_load(net, bus16, p_mw=758.4, q_mvar ,→=758.4*0.1, name="Unitary Load")#Barcelona 147 148 149 #-------Creation of external grids-------# 150 151 eg1=pp.create_ext_grid(net, bus8, slack=True,vm_pu=1.0) # ,→Bourdeaux Site 152 eg2=pp.create_ext_grid(net, bus16, slack=True, vm_pu=1.0) # ,→Vic Site 153 eg3=pp.create_ext_grid(net, bus0, slack=True, vm_pu=1.0) # ,→Gatika Site 154 155 #-------SIMULATION OF THE POWER FLOW-------#
108 156 157 pp.runpp(net) 158 159 #-------RESULTS ANALYSIS-------# 160 161 #-------Bus characteristics-------# 162 163 #bus_results = net.res_bus[[’p_mw’, ’q_mvar’, ’vm_pu’, ’ ,→va_degree’]] 164 #print(bus_results) 165 166 #routeCase01 = ’Z:\DOBLE MASTER MUEI & MUEE\TFM\Technical ,→Analysis- Python Sim\C di g os Actualizados\Case ,→Studies’ 167 168 # Obtener los resultados de net.res_line y almacenarlos en ,→un DataFrame de Pandas 169 #res_bus_df = pd.DataFrame(net.res_bus) 170 171 # Nombre del archivo Excel 172 #nombre_archivo1 = "Case 0 Bus Results.xlsx" 173 174 # Ruta completa del archivo 175 #full_route = os.path.join(routeCase01, nombre_archivo1) 176 177 # Escribir los resultados en el archivo Excel en la ruta ,→especificada 178 #res_bus_df.to_excel(full_route, index=False) 179 180 #-------Line characteristics-------# 181 182 routeCase02 = r’Z:\DOBLE MASTER MUEI & MUEE\TFM\Technical ,→Analysis- Python Sim\C di g os Actualizados\Case ,→Studies’ 183 184 # Obtener los resultados de net.res_line y almacenarlos en ,→un DataFrame de Pandas 185 res_line_df = pd.DataFrame(net.res_line) 186 187 # Nombre del archivo Excel 188 nombre_archivo2 = "Case 0 Results.xlsx" 189 190 # Ruta completa del archivo 191 full_route = os.path.join(routeCase02, nombre_archivo2) 192
115 ,→max_i_ka =i_max, name="L45’’")# (36) 114 line63= pp.create_line_from_parameters(net,from_bus=bus5, ,→to_bus=bus6, length_km=59, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L56’’")# (37) 115 line73= pp.create_line_from_parameters(net,from_bus=bus6, ,→to_bus=bus7, length_km=54, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L67’’")# (38) 116 line83= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus8, length_km=34, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L78’’")# (39) 117 line93= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus9, length_km=162, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L79’’")# (40) 118 line103= pp.create_line_from_parameters(net,from_bus=bus9, ,→to_bus=bus10, length_km=47, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L910’’")# (41) 119 line113= pp.create_line_from_parameters(net,from_bus=bus10, ,→to_bus=bus11, length_km=38, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1011’’")# (42) 120 line123= pp.create_line_from_parameters(net,from_bus=bus11, ,→to_bus=bus12, length_km=39, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1112’’")# (43)) 121 line133= pp.create_line_from_parameters(net,from_bus=bus12, ,→to_bus=bus13, length_km=58, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1213’’")# (44) 122 line143= pp.create_line_from_parameters(net,from_bus=bus13, ,→to_bus=bus14, length_km=57, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1314’’")# (45) 123 line163A= pp.create_line_from_parameters(net,from_bus=bus14, ,→to_bus=bus16, length_km=104, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1416’’")# (46) 124 line163B= pp.create_line_from_parameters(net,from_bus=bus15, ,→to_bus=bus16, length_km=62, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1516’’")# (47)
116 125 126 127 #LINK 2 HVAC--------------------------------- 128 129 #Line (Phase A): 130 lineA1= pp.create_line_from_parameters(net,from_bus=bus0, ,→to_bus=bus1, length_km=70, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LA1")# (48) 131 lineA2 =pp.create_line_from_parameters(net,from_bus=bus1, ,→to_bus=bus2, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LA2")# (49) 132 lineA3= pp.create_line_from_parameters(net,from_bus=bus2, ,→to_bus=bus3, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LA3")# (50) 133 lineA4= pp.create_line_from_parameters(net,from_bus=bus3, ,→to_bus=bus4, length_km=50, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LA4")# (51) 134 lineA5= pp.create_line_from_parameters(net,from_bus=bus4, ,→to_bus=bus5, length_km=115, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LA5")# (52) 135 lineA6= pp.create_line_from_parameters(net,from_bus=bus5, ,→to_bus=bus6, length_km=59, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LA6")# (53) 136 lineA7= pp.create_line_from_parameters(net,from_bus=bus6, ,→to_bus=bus7, length_km=54, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LA7")# (54) 137 lineA8= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus8, length_km=34, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LA8")# (55) 138 139 140 141 #Line (Phase B): 142 lineB1= pp.create_line_from_parameters(net,from_bus=bus0, ,→to_bus=bus1, length_km=70, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LB1")# (56)
117 143 lineB2= pp.create_line_from_parameters(net,from_bus=bus1, ,→to_bus=bus2, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LB2")# (57) 144 lineB3= pp.create_line_from_parameters(net,from_bus=bus2, ,→to_bus=bus3, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LB3")# (58) 145 lineB4= pp.create_line_from_parameters(net,from_bus=bus3, ,→to_bus=bus4, length_km=50, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LB4")# (59) 146 lineB5= pp.create_line_from_parameters(net,from_bus=bus4, ,→to_bus=bus5, length_km=115, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LB5")# (60) 147 lineB6= pp.create_line_from_parameters(net,from_bus=bus5, ,→to_bus=bus6, length_km=59, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LB6")# (61) 148 lineB7= pp.create_line_from_parameters(net,from_bus=bus6, ,→to_bus=bus7, length_km=54, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LB7")# (62) 149 lineB8= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus8, length_km=34, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LB8")# (63) 150 151 152 153 #Line (Phase B): 154 lineC1= pp.create_line_from_parameters(net,from_bus=bus0, ,→to_bus=bus1, length_km=70, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LC1")# (64) 155 lineC2= pp.create_line_from_parameters(net,from_bus=bus1, ,→to_bus=bus2, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LC2")# (65) 156 lineC3= pp.create_line_from_parameters(net,from_bus=bus2, ,→to_bus=bus3, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LC3")# (66) 157 lineC4= pp.create_line_from_parameters(net,from_bus=bus3,
118 ,→to_bus=bus4, length_km=50, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LC4")# (67) 158 lineC5= pp.create_line_from_parameters(net,from_bus=bus4, ,→to_bus=bus5, length_km=115, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LC5")# (68) 159 lineC6= pp.create_line_from_parameters(net,from_bus=bus5, ,→to_bus=bus6, length_km=59, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LC6")# (69) 160 lineC7= pp.create_line_from_parameters(net,from_bus=bus6, ,→to_bus=bus7, length_km=54, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LC7")# (70) 161 lineC8= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus8, length_km=34, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="LC8")# (71) 162 163 164 165 #HVDC LINES . Baixas-Sta Llogaia has a 2x1000 MW 166 167 singular_loss= (0.9/100)*1000*2#The losses are 0.9% of the ,→power of each valve hall. As there are one converter ,→and one rectifier (2). In MW 168 line_loss=0.3 # As it should be stated in percent 169 170 line15A = pp.create_dcline(net, from_bus=14, to_bus=15, p_mw ,→=1000, loss_percent=line_loss, loss_mw=singular_loss, ,→vm_from_pu=1.0, vm_to_pu=1.0, max_p_mw=1000,in_service ,→=True) #Cable from Pole 1 171 line15B = pp.create_dcline(net, from_bus=14, to_bus=15, p_mw ,→=1000, loss_percent=line_loss,loss_mw=singular_loss, ,→vm_from_pu=1.0, vm_to_pu=1.0, max_p_mw=1000,in_service ,→=True) #Cable from Pole 2 172 173 #-------Creation of generators-------# 174 175 gen1=pp.create_gen(net, bus0, p_mw=396, vm_pu=1.0,name="Gen1 ,→")#Santurzi CC 176 gen2=pp.create_gen(net, bus2, p_mw=786, vm_pu=1.0,name="Gen2 ,→")#Amorebieta CC 177 gen3=pp.create_gen(net, bus9, p_mw=2620, vm_pu=1.0,name="
119 ,→Gen3")#Golfech NPP 178 gen4= pp.create_gen(net, bus8, p_mw=3640, vm_pu=1.0, name=" ,→Gen3")#Le Blayais NPP 179 180 181 #-------Creation of loads-------# 182 183 load1=pp.create_load(net, bus0, p_mw=593.5, q_mvar ,→=593.5*0.1, name="Unitary Load")#Bilbao 184 load2=pp.create_load(net, bus10, p_mw=640.3, q_mvar ,→=640.3*0.1, name="Unitary Load")#Toulouse 185 load3=pp.create_load(net, bus7, p_mw=547.9, q_mvar ,→=547.9*0.1, name="Unitary Load")#Bordeaux 186 load4=pp.create_load(net, bus16, p_mw=758.4, q_mvar ,→=758.4*0.1, name="Unitary Load")#Barcelona 187 188 189 #-------Creation of external grids-------# 190 191 eg1=pp.create_ext_grid(net, bus8,slack=True,vm_pu=1.0) # ,→Bourdeaux Site 192 eg2=pp.create_ext_grid(net, bus16,slack=True, vm_pu=1.0) # ,→Vic Site 193 eg3=pp.create_ext_grid(net, bus0,slack=True, vm_pu=1.0) # ,→Gatika Site 194 195 #-------SIMULATION OF THE POWER FLOW-------# 196 197 pp.runpp(net) 198 199 #-------RESULTS ANALYSIS-------# 200 201 #-------Bus characteristics-------# 202 203 #bus_results = net.res_bus[[’p_mw’, ’q_mvar’, ’vm_pu’, ’ ,→va_degree’]] 204 #print(bus_results) 205 206 #routeCase01 = ’Z:\DOBLE MASTER MUEI & MUEE\TFM\Technical ,→Analysis- Python Sim\C di g os Actualizados\Case ,→Studies’ 207 208 # Obtener los resultados de net.res_line y almacenarlos en ,→un DataFrame de Pandas 209 #res_bus_df = pd.DataFrame(net.res_bus)
120 210 211 # Nombre del archivo Excel 212 #nombre_archivo1 = "Case 0 Bus Results.xlsx" 213 214 # Ruta completa del archivo 215 #full_route = os.path.join(routeCase01, nombre_archivo1) 216 217 # Escribir los resultados en el archivo Excel en la ruta ,→especificada 218 #res_bus_df.to_excel(full_route, index=False) 219 220 #-------Line characteristics-------# 221 222 routeCase02 = r’Z:\DOBLE MASTER MUEI & MUEE\TFM\Technical ,→Analysis- Python Sim\C di g os Actualizados\Case ,→Studies’ 223 224 # Obtener los resultados de net.res_line y almacenarlos en ,→un DataFrame de Pandas 225 res_line_df = pd.DataFrame(net.res_line) 226 227 # Nombre del archivo Excel 228 nombre_archivo2 = "Case 0 Results.xlsx" 229 230 # Ruta completa del archivo 231 full_route = os.path.join(routeCase02, nombre_archivo2) 232 233 # Escribir los resultados en el archivo Excel en la ruta ,→especificada 234 res_line_df.to_excel(full_route, index=False) 235 236 #------- DC Line characteristics-------# 237 238 routeCase03 = r’Z:\DOBLE MASTER MUEI & MUEE\TFM\Technical ,→Analysis- Python Sim\C di g os Actualizados\Case ,→Studies’ 239 240 # Obtener los resultados de net.res_dcline y almacenarlos en ,→un DataFrame de Pandas 241 res_dcline_df = pd.DataFrame(net.res_dcline) 242 243 # Nombre del archivo Excel 244 nombre_archivo3 = "Case 0 Results_DCline.xlsx" 245 246 # Ruta completa del archivo
121 247 ruta_completa = os.path.join(routeCase03, nombre_archivo3) 248 249 # Escribir los resultados en el archivo Excel en la ruta ,→especificada 250 res_dcline_df.to_excel(ruta_completa, index=False) Listing D.3: HVDC Link - The Gatika Cubnezais Case of Study - Case B 1## CASE B 2reset -f 3clear() 4 5import math 6import numpy as np 7import pandapower as pp 8import pandas as pd 9import copy 10 import matplotlib.pyplot as plt 11 import os 12 import pandas as pd 13 #--------------------------------# 14 #--------------------------------# 15 16 #-------DEFINITION OF THE GRID-------# 17 18 #-------Creation of buses-------# 19 20 net = pp.create_empty_network() 21 22 bus0= pp.create_bus(net,name = "b0", vn_kv=400) #Gatika Site ,→(0) 23 bus1= pp.create_bus(net,name = "b1", vn_kv=400) #Azpeitia ,→Site (1) 24 bus2= pp.create_bus(net,name = "b2", vn_kv=400) #Hernani ,→Site (2) 25 bus3= pp.create_bus(net,name = "b3", vn_kv=400) # I r n Site ,→(3) 26 bus4= pp.create_bus(net,name = "b4", vn_kv=400) #Argia Site ,→(4) 27 bus5= pp.create_bus(net,name = "b5", vn_kv=400) #Cantegrit ,→Site (5) 28 bus6= pp.create_bus(net,name = "b6", vn_kv=400) #Saucats ,→Site (6) 29 bus7= pp.create_bus(net,name = "b7", vn_kv=400) #Cubnezais ,→Site (7)
122 30 bus8= pp.create_bus(net,name = "b8", vn_kv=400) #Le Blasai ,→Site (8) 31 bus9= pp.create_bus(net,name = "b9", vn_kv=400) #Donzac Site ,→(9) 32 bus10= pp.create_bus(net,name = "b10", vn_kv=400) #Lesquive ,→Site (10) 33 bus11= pp.create_bus(net,name = "b11", vn_kv=400) #Verfeil ,→Site (11) 34 bus12= pp.create_bus(net,name = "b12", vn_kv=400) #Issel ,→Site (12) 35 bus13= pp.create_bus(net,name = "b13", vn_kv=400) #Gaudiere ,→Site (13) 36 bus14= pp.create_bus(net,name = "b14", vn_kv=400) #Baixas ,→Site (14) 37 bus15= pp.create_bus(net,name = "b15", vn_kv=400) #Sta. ,→Llogaia Site (15) 38 bus16= pp.create_bus(net,name = "b16", vn_kv=400) #Vic Site ,→(16) 39 40 41 #-------Creation of lines-------# 42 43 epsilon_0=8.854187817*math.exp(-12) #Constant value 44 45 #Cable Characteristics 46 47 GMR=(11.43/1000) #Geometric Mean Radius (Function of the ,→type of cable) 48 GMD=5 # Geometric Mean Distance Between the Phases (Dab*Dbc* ,→Dca)ˆ(1/3) 49 d= 0.2 #Distance between bundle conductors (m) 50 D=(28.14/1000) #Diameter of the conductor (m) 51 r=D/2 #Diameter of the conductor (m) 52 53 r_eq=(d**(2-1)*r)**(1/2) #Equivalent radius 54 55 r_single_AC=88.4/1000 #Ohm/km 56 r_single_DC=73.3/1000 #Ohm/km 57 x_single=0.337 #Ohm/km 58 c_single = ((2 *math.pi *epsilon_0) / (math.log(GMD/r_eq)) ,→)*math.exp(12) # Value in nF/km 59 60 r_double=r_single_AC/2 61 x_double=x_single/2 62 c_double=c_single/2
123 63 64 i_max=0.9 #Maximun current that the line allowes 65 66 #HVAC LINES- Duplex conductor for OHL. See the diagram. The ,→code is based in the number of the bus that arrives. 67 68 #Line (Phase R): 69 line11= pp.create_line_from_parameters(net,from_bus=bus0, ,→to_bus=bus1, length_km=70, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L01")# (0) 70 line21 =pp.create_line_from_parameters(net,from_bus=bus1, ,→to_bus=bus2, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L12")# (1) 71 line31= pp.create_line_from_parameters(net,from_bus=bus2, ,→to_bus=bus3, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L23")# (2) 72 line41= pp.create_line_from_parameters(net,from_bus=bus3, ,→to_bus=bus4, length_km=50, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L34")# (3) 73 line51= pp.create_line_from_parameters(net,from_bus=bus4, ,→to_bus=bus5, length_km=115, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L45")# (4) 74 line61= pp.create_line_from_parameters(net,from_bus=bus5, ,→to_bus=bus6, length_km=59, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L56")# (5) 75 line71= pp.create_line_from_parameters(net,from_bus=bus6, ,→to_bus=bus7, length_km=54, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L67")# (6) 76 line81= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus8, length_km=34, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L78")# (7) 77 line91= pp.create_line_from_parameters(net,from_bus=bus7, ,→to_bus=bus9, length_km=162, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L79")# (8) 78 line101= pp.create_line_from_parameters(net,from_bus=bus9, ,→to_bus=bus10, length_km=47, r_ohm_per_km = r_double,
124 ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L910")# (9) 79 line111= pp.create_line_from_parameters(net,from_bus=bus10, ,→to_bus=bus11, length_km=38, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1011")# (10) 80 line121= pp.create_line_from_parameters(net,from_bus=bus11, ,→to_bus=bus12, length_km=39, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1112")# (11) 81 line131= pp.create_line_from_parameters(net,from_bus=bus12, ,→to_bus=bus13, length_km=58, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1213")# (12) 82 line141= pp.create_line_from_parameters(net,from_bus=bus13, ,→to_bus=bus14, length_km=57, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1314")# (13) 83 line161A= pp.create_line_from_parameters(net,from_bus=bus14, ,→to_bus=bus16, length_km=104, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1416")# (14) 84 line161B= pp.create_line_from_parameters(net,from_bus=bus15, ,→to_bus=bus16, length_km=62, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L1516")# (15) 85 86 87 #Line (Phase S): 88 line12= pp.create_line_from_parameters(net,from_bus=bus0, ,→to_bus=bus1, length_km=70, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L01’")# (16) 89 line22= pp.create_line_from_parameters(net,from_bus=bus1, ,→to_bus=bus2, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L12’")# (17) 90 line32= pp.create_line_from_parameters(net,from_bus=bus2, ,→to_bus=bus3, length_km=35, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L23’")# (18) 91 line42= pp.create_line_from_parameters(net,from_bus=bus3, ,→to_bus=bus4, length_km=50, r_ohm_per_km = r_double, ,→x_ohm_per_km = x_double, c_nf_per_km = c_double, ,→max_i_ka =i_max, name="L34’")# (19)
References [1] Aluminium prices — 1989-2024 datos. https://es.tradingeconomics. com/commodity/aluminum. (Accessed on 02/25/2024). [2] Basic electric power and structure of power system. https://www. brainkart.com. (Accessed on 11/01/2023). [3] Decisi´ on sobre la distribuci´ on transfronteriza de costes en el proyecto de interconexi´ on en el Golfo de Vizcaya. https://www.cnmc.es/sites/ default/files/1807064_0.pdf. (Accessed on 03/25/2024). [4] El Observatorio de la Energ´ ıa. https://www.energia.barcelona. (Accessed on 04/23/2024). [5] El papel de la mujer en la transici´ on a las energ´ ıas renovables. https://energy.worldwiderecruitment.org/ el-papel-de-la-mujer-en-las-energias-renovables/. (Accessed on 04/28/2024). [6] Estudio de Impactos Ambiental de la l´ ınea el´ ectrica a 400 kV Morella - La Plana 2. https://www.ree.es. (Accessed on 01/15/2024). [7] Euro area inflation rate. https://tradingeconomics.com/euro-area/ inflation-cpi. (Accessed on 02/25/2024). [8] The Gotland HVDC link — Hitachi Energy. https://www. hitachienergy.com. (Accessed on 11/05/2023). [9] HVDC Cable Transmissions. https://library.e.abb.com. (Accessed on 01/27/2024). [10] HVDC Classic (LCC). https://www.hitachienergy.com. (Accessed on 11/15/2023). 131
132 [11] The inductor and the effects of inductance on a coil. https://www. electronics-tutorials.ws. (Accessed on 11/25/2023). [12] Line-Commutated Converters - Current Source Converters. https://www. entsoe.eu/Technopedia. (Accessed on 11/19/2023). [13] Liquidaci´ on de las operaciones en el mercado — omie. https://www.omie.es/es/faq/ liquidacion-de-las-operaciones-en-el-mercado. (Accessed on 04/30/2024). [14] Mercury arc rectifiers - Kempton steam museum. https:// kemptonsteam.org. (Accessed on 11/15/2023). [15] Plan de desarrollo de la Red de Transporte de Energ´ ıa El´ ectrica. https: //www.planificacionelectrica.es. (Accessed on 01/06/2024). [16] Portrait ´ energ´ etique de la grande agglom´ eration toulousaine. https: //www.aua-toulouse.org/wp-content/uploads/2019/11/pdf_ pv8p-acte-2019-11-portraitenergetiquegat.pdf. (Accessed on 04/23/2024). [17] Thyristor controlled series compensation — Hitachi Energy. https://www. hitachienergy.com. (Accessed on 01/07/2024). [18] ¿Progreso en la investigaci´ on de los efectos de las torres de alta tensi´ on sobre la salud? https://cordis.europa.eu. (Accessed on 04/28/2024). [19] Estudio de Impacto Ambiental de la linea el´ ectrica a 400 kV Pinilla- - Cofrentes. https://www.ree.es, November 2008. (Accessed on 01/14/2024). [20] ABB commissions world’s longest power transmission link in brazil. https: //new.abb.com, August 2014. (Accessed on 01/03/2024). [21] Cartograf´ ıa y datos geogr´ aficos - Instituto Geogr´ afico Nacional. https:// www.ign.es, March 2018. (Accessed on 01/06/2024). [22] Acuerdo por el que se emite informe a solicitud de la DGPEM sobre la peticion de REE de reconocimiento del caracter singular de la interconexion electrica Espa˜ na-Francia por el golfo de Vizcaya (linea HVDC Gatika-Cubnezais)
133 y su inclusion en el regimen retributivo de inversiones singulares con caracteristicas tecnicas especiales. https://www.cnmc.es/sites/default/ files/2427400_1.pdf, April 2019. (Accessed on 03/20/2024). [23] El nuevo cable con la pen´ ınsula costar´ a el triple que el anterior. https://www.elmundo.es/baleares/2019/04/22/ 5cbd7d0c21efa099308b458c.html, April 2019. (Accessed on 03/17/2024). [24] Firing angle of SCR Explained - electrical concepts. https:// electricalbaba.com/firing-angle-scr/, April 2019. (Accessed on 11/19/2023). [25] Estudio de Impacto Ambiental - Interconexi´ on el´ ectrica Espa˜ na-Francia por el Golfo de Bizkaia. https://www.ree.es/sites/default/files/ 04_SOSTENIBILIDAD/Documentos/tramitacion_ambiental/EIA/ 1.Doc_Sintesis_EsIA_Interconexion_Cable_Es_Fr_Golfo_ Bizkaia.pdf, April 2021. (Accessed on 03/26/2024). [26] Strat´ egie M´ etropolitaine de D´ eveloppement des ´ Energies Renouvelables. https://www.bordeaux-metropole.fr/sites/ MET-BXMETRO-DRUPAL/files/2024-02/FeuilleRoute_Energies_ renouvelables_2020e2026_delib%2006_14_2021.pdf, July 2021. (Accessed on 04/23/2024). [27] El consumo energ´ etico en euskadi se recuper´ o en 2021 pero sin alcanzar niveles prepandemia. https: //www.eve.eus/Jornadas-y-Noticias/Noticias/ El-consumo-energetico-en-Euskadi-se-recupero-en-20?lang= es-es, February 2022. (Accessed on 04/23/2024). [28] Will there be enough cables for the clean energy transition? https://www. ft.com, July 2023. (Accessed on 01/27/2024). [29] Main grid transmission reliability rate reached the highest recorded level in 2023 - fingrid. https://www.fingrid.fi, January 2024. (Accessed on 03/06/2024).
134 [30] M. Alam, M. Rahaman, F. Dhali, and U. Student. Technical comparison of modern hvac and hvdc transmission system along with cost analysis. Journal of Control and Instrumentation Engineering, 8:10, 02 2022. [31] ALSTOM. HVDC for begineers. http://cigre.ru, 2016. (Accessed on 12/02/2023). [32] L. Barros, A. P. Martins, and J. Pinto. A comprehensive review on modular multilevel converters, submodule topologies, and modulation techniques. https://www.mdpi.com/, January 2022. (Accessed on 11/26/2023). [33] C. Bertrand. Analysis of electric power and energy systems. https: //bcornelusse.github.io/ELEC0447-analysis-power-systems/ pdf/lecture6.pdf. (Accessed on 02/19/2024). [34] M. Changizian, A. Mizani, and A. Shoulaie. Fault ride-through capability enhancement of voltage source converter-high voltage direct current systems with bridge type fault current limiters. https://www.mdpi.com, October 2017. (Accessed on 11/26/2023). [35] A. Dimitriou, C. Charalambous, I. Gonos, and T. T. A. Papadopoulos. Modelling and assessment of short-term electromagnetic interference on a railway system from pole-to-ground faults on VSC-HVDC cable networks with sea electrodes. https://ieeexplore, October 2020. (Accessed on 12/02/2023). [36] W. Dirk, A. K¨ uster, D. van Hertem, D. Soerangr, G. Asplund, M. Meisingset, M. Takasaki, T. Rauhala, K. Friedrich, B. Kl¨ ockl, R. Atmuri, and M. Bennett. Voltage Source Converter (VSC) HVDC for Power Transmission – Economic Aspects and Comparison with other AC and DC Technologies. CIGRE, 2012. [37] INELFE. Interconexi´ on El´ ectrica por los Pireneos Catalanes. https://www. ree.es/sites/default/files/monograficoinelfe.pdf, September 2011. (Accessed on 02/19/2024). [38] G. Kamalapur. A comparative study of Monopolar and Bipolar HVDC transmission systems. https://www.researchgate.net, October 2020. (Accessed on 01/05/2024).
135 [39] E. Liun. Stochastic methodology to estimate costs of hvdc transmission system. 02 2016. [40] T. Midtsund, A. Becker, and K. Egeland. A live black-start capability test of a voltage source HVDC converter. https://library.e.abb.com, September 2015. (Accessed on 11/26/2023). [41] A. Nishioka. Global rise of HVDC and its background : Hitachi review. https://www.hitachi.com, April 2020. (Accessed on 11/05/2023). [42] A. Nishioka, F. Alvarez, and T. Omori. Global rise of hvdc and its background. https://www.hitachi.com, 2020. (Accessed on 03/17/2024). [43] N. Ottosson and L. Kjellin. Modular back-to-back HVDC, with capacitor commutated converters (CCC). https://abb.com. (Accessed on 12/02/2023). [44] REE. R´ omulo - Interconexi´ on El´ ectrica con Baleares. https://www. ree.es/sites/default/files/01_ACTIVIDADES/Documentos/ folleto_romulo_es.pdf, August 2012. (Accessed on 02/19/2024). [45] M. Reta-Hern´ andez. Transmission Line Parameters. https://www. unioviedo.es, 2006. (Accessed on 01/14/2024). [46] P. Roncero-S´ anchez. Multiterminal HVDC system with power quality enhancement. https://www.mdpi.com, February 2021. (Accessed on 12/15/2023). [47] S. Sayed and A. Massoud. Minimum transmission power loss in multiterminal HVDC systems: A general methodology for radial and mesh networks. https://www.sciencedirect.com, December 2018. (Accessed on 12/15/2023). [48] T. Shahsavariana. Novel modulated equivalent model of point-to-point LCC- based high voltage AC/DC/AC system for geomagnetic storm-induced unbalanced harmonic studies. https://www.sciencedirect.com, May 2020. (Accessed on 11/25/2023). [49] A. Stan. Overview and assessment of HVDC current applications and future trends. https://www.mdpi.com, January 2022. (Accessed on 11/15/2023).
136 [50] R. Suchantke. Using helical voltage loops for the AC resistance measurement of complex conductor designs (milliken conductors, bus bars, ...). https: //www.researchgate.net, January 2019. (Accessed on 01/05/2024). [51] W. Sun, R. Torres-Olguin, and O. Anaya-Lara. Investigation on fault-ride through methods for VSC-HVDC connected offshore wind farms. https: //www.sciencedirect.com/, January 2016. (Accessed on 11/26/2023). [52] Y. Tang. Analysis and Design of Damping Circuit Parameters for LCC valves based on broadband model. https://www.mdpi.com, January 2022. (Accessed on 11/25/2023). [53] L. Thurner, A. Scheidler, F. Sch¨ afer, J.-H. Menke, J. Dollichon, F. Meier, S. Meinecke, and M. Braun. Pandapower—An Open-Source Python Tool for Convenient Modeling, Analysis, and Optimization of Electric Power Systems. IEEE Transactions on Power Systems, 33(6):6510–6521, 2018. [54] Q. Xiaomin. Analysis on characteristic of DC short-circuit fault in multi-terminal AC/DC hybrid distribution network. https:/www. researchgate.net, November 2018. (Accessed on 11/25/2023). [55] A. Yona. Technical and Economic Analysis of an HVDC Transmission System for Renewable Energy Connection in Afghanistan. https://www. researchgate.net, January 2022. (Accessed on 01/04/2024). [56] L. Zhu. A decoupled circuital model methodology for calculating DC currents in AC grids induced by HVDC grounding current. https://www. researchgate.net/, January 2019. (Accessed on 11/29/2023).