Study for process improvement of electric charging points installation
Serra Gómez, Roger
- Published
- 2024-07-09
- Publisher
- Universitat Politècnica de Catalunya
- Language
- en
Abstract
This thesis investigates process improvement for the installation of electric vehicle (EV) charging points by Elecnor for Endesa X, focusing on optimizing workflow, reducing inefficiencies, and maintaining high-quality standards in the installation of 100 charging points annually. The primary objectives of the project are to install these charging points efficiently, ensuring quality, minimizing costs, and achieving customer satisfaction. Additionally, the project aims to enhance the skills of the project team through continuous improvement and training initiatives. The adopted methodology combines waterfall and agile project management approaches to ensure thorough planning and flexibility during execution. Key components include the project charter, scope management plan, cost management plan, quality plan, and risk management plan. Process improvement techniques such as Value Stream Mapping (VSM) and Flowchart are used to identify and address inefficiencies. Detailed scheduling with Gantt charts and critical path analysis ensures precise task sequencing and dependency identification. Implementing the project management plan leads to significant improvements. The use of detailed scheduling tools allows for real-time adjustments, keeping the project on track despite delays. Quality control tools such as Pareto charts and control diagrams maintain high standards. The project management plan is crucial for achieving the objectives, providing a structured approach to managing scope, schedule, cost, quality, risk, and communication. The project's success underscores the importance of comprehensive planning to deliver complex infrastructure projects on time and within budget. Additionally, integrating community participation and renewable energy considerations has a positive impact on the project's environmental and social aspects. This thesis demonstrates how effective project management enhances the efficiency and reliability of EV charging point installations, supporting broader adoption of electric vehicles and contributing to sustainable transportation initiatives
Full text
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 1 Permits Acquisition 23 días lun 15/01/24 mié 14/02/24 2 Approval of Design and Planning 1 día mié 14/02/24 mié 14/02/24 3 Obtaining All Necessary Permits 1 día mié 14/02/24 mié 14/02/24 4 Installation of the 50th Charging Point 1 día mié 19/06/24 mié 19/06/24 300 5 Completion of All Installations 1 día lun 16/09/24 lun 16/09/24 600 6 Final Review and Project Closure 1 día mar 17/09/24 mar 17/09/24 600 7 Physical Site Inspection for Charger 1 1 día lun 15/01/24 lun 15/01/24 8 Civil Works for Charger 1 1 día lun 12/02/24 lun 12/02/24 1000 9 Cement Curing for Charger 1 2 días mar 13/02/24 mié 14/02/24 1 10 Electrical Installation for Charger 1 1 día jue 15/02/24 jue 15/02/24 2 11 Parking Line Painting for Charger 1 1 día lun 19/02/24 lun 19/02/24 3 12 Documentation Post-Installation for Charger 1 15 días mar 20/02/24 dom 10/03/24 4 13 Commissioning for Charger 1 1 día mar 26/03/24 mar 26/03/24 5 14 Physical Site Inspection for Charger 2 1 día mar 16/01/24 mar 16/01/24 1000 15 Civil Works for Charger 2 1 día mar 13/02/24 mar 13/02/24 1001 16 Cement Curing for Charger 2 2 días mié 14/02/24 jue 15/02/24 7 17 Electrical Installation for Charger 2 1 día lun 19/02/24 lun 19/02/24 8 18 Parking Line Painting for Charger 2 1 día mar 20/02/24 mar 20/02/24 9 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 1 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 19 Documentation Post-Installation for Charger 2 14 días mié 21/02/24 lun 11/03/24 10 20 Commissioning for Charger 2 1 día mié 27/03/24 mié 27/03/24 11 21 Physical Site Inspection for Charger 3 1 día mié 17/01/24 mié 17/01/24 1001 22 Civil Works for Charger 3 1 día mié 14/02/24 mié 14/02/24 1002 23 Cement Curing for Charger 3 2 días jue 15/02/24 vie 16/02/24 13 24 Electrical Installation for Charger 3 1 día mar 20/02/24 mar 20/02/24 14 25 Parking Line Painting for Charger 3 1 día mié 21/02/24 mié 21/02/24 15 26 Documentation Post-Installation for Charger 3 14 días jue 22/02/24 mar 12/03/24 16 27 Commissioning for Charger 3 1 día jue 28/03/24 jue 28/03/24 17 28 Physical Site Inspection for Charger 4 1 día jue 18/01/24 jue 18/01/24 1002 29 Civil Works for Charger 4 1 día jue 15/02/24 jue 15/02/24 1003 30 Cement Curing for Charger 4 2 días lun 19/02/24 mar 20/02/24 19 31 Electrical Installation for Charger 4 1 día mié 21/02/24 mié 21/02/24 20 32 Parking Line Painting for Charger 4 1 día jue 22/02/24 jue 22/02/24 21 33 Documentation Post-Installation for Charger 4 16 días lun 26/02/24 sáb 16/03/24 22 34 Commissioning for Charger 4 1 día lun 01/04/24 lun 01/04/24 23 35 Physical Site Inspection for Charger 5 1 día lun 22/01/24 lun 22/01/24 1003 36 Civil Works for Charger 5 1 día lun 19/02/24 lun 19/02/24 1004 37 Cement Curing for Charger 5 2 días mar 20/02/24 mié 21/02/24 25 38 Electrical Installation for Charger 5 1 día jue 22/02/24 jue 22/02/24 26 39 Parking Line Painting for Charger 5 1 día lun 26/02/24 lun 26/02/24 27 40 Documentation Post-Installation for Charger 5 15 días mar 27/02/24 dom 17/03/24 28 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 2 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 41 Commissioning for Charger 5 1 día mar 02/04/24 mar 02/04/24 29 42 Physical Site Inspection for Charger 6 1 día mar 23/01/24 mar 23/01/24 1004 43 Civil Works for Charger 6 1 día mar 20/02/24 mar 20/02/24 1005 44 Cement Curing for Charger 6 2 días mié 21/02/24 jue 22/02/24 31 45 Electrical Installation for Charger 6 1 día lun 26/02/24 lun 26/02/24 32 46 Parking Line Painting for Charger 6 1 día mar 27/02/24 mar 27/02/24 33 47 Documentation Post-Installation for Charger 6 14 días mié 28/02/24 lun 18/03/24 34 48 Commissioning for Charger 6 1 día mié 03/04/24 mié 03/04/24 35 49 Physical Site Inspection for Charger 7 1 día mié 24/01/24 mié 24/01/24 1005 50 Civil Works for Charger 7 1 día mié 21/02/24 mié 21/02/24 1006 51 Cement Curing for Charger 7 2 días jue 22/02/24 vie 23/02/24 37 52 Electrical Installation for Charger 7 1 día mar 27/02/24 mar 27/02/24 38 53 Parking Line Painting for Charger 7 1 día mié 28/02/24 mié 28/02/24 39 54 Documentation Post-Installation for Charger 7 14 días jue 29/02/24 mar 19/03/24 40 55 Commissioning for Charger 7 1 día jue 04/04/24 jue 04/04/24 41 56 Physical Site Inspection for Charger 8 1 día jue 25/01/24 jue 25/01/24 1006 57 Civil Works for Charger 8 1 día jue 22/02/24 jue 22/02/24 1007 58 Cement Curing for Charger 8 2 días lun 26/02/24 mar 27/02/24 43 59 Electrical Installation for Charger 8 1 día mié 28/02/24 mié 28/02/24 44 60 Parking Line Painting for Charger 8 1 día jue 29/02/24 jue 29/02/24 45 61 Documentation Post-Installation for Charger 8 16 días lun 04/03/24 sáb 23/03/24 46 62 Commissioning for Charger 8 1 día lun 08/04/24 lun 08/04/24 47 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 3 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 63 Physical Site Inspection for Charger 9 1 día lun 29/01/24 lun 29/01/24 1007 64 Civil Works for Charger 9 1 día lun 26/02/24 lun 26/02/24 1008 65 Cement Curing for Charger 9 2 días mar 27/02/24 mié 28/02/24 49 66 Electrical Installation for Charger 9 1 día jue 29/02/24 jue 29/02/24 50 67 Parking Line Painting for Charger 9 1 día lun 04/03/24 lun 04/03/24 51 68 Documentation Post-Installation for Charger 9 15 días mar 05/03/24 dom 24/03/24 52 69 Commissioning for Charger 9 1 día mar 09/04/24 mar 09/04/24 53 70 Physical Site Inspection for Charger 10 1 día mar 30/01/24 mar 30/01/24 1008 71 Civil Works for Charger 10 1 día mar 27/02/24 mar 27/02/24 1009 72 Cement Curing for Charger 10 2 días mié 28/02/24 jue 29/02/24 55 73 Electrical Installation for Charger 10 1 día lun 04/03/24 lun 04/03/24 56 74 Parking Line Painting for Charger 10 1 día mar 05/03/24 mar 05/03/24 57 75 Documentation Post-Installation for Charger 10 14 días mié 06/03/24 lun 25/03/24 58 76 Commissioning for Charger 10 1 día mié 10/04/24 mié 10/04/24 59 77 Physical Site Inspection for Charger 11 1 día mié 31/01/24 mié 31/01/24 1009 78 Civil Works for Charger 11 1 día mié 28/02/24 mié 28/02/24 1010 79 Cement Curing for Charger 11 2 días jue 29/02/24 vie 01/03/24 61 80 Electrical Installation for Charger 11 1 día mar 05/03/24 mar 05/03/24 62 81 Parking Line Painting for Charger 11 1 día mié 06/03/24 mié 06/03/24 63 82 Documentation Post-Installation for Charger 11 14 días jue 07/03/24 mar 26/03/24 64 83 Commissioning for Charger 11 1 día jue 11/04/24 jue 11/04/24 65 84 Physical Site Inspection for Charger 12 1 día jue 01/02/24 jue 01/02/24 1010 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 4 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 85 Civil Works for Charger 12 1 día jue 29/02/24 jue 29/02/24 1011 86 Cement Curing for Charger 12 2 días lun 04/03/24 mar 05/03/24 67 87 Electrical Installation for Charger 12 1 día mié 06/03/24 mié 06/03/24 68 88 Parking Line Painting for Charger 12 1 día jue 07/03/24 jue 07/03/24 69 89 Documentation Post-Installation for Charger 12 16 días lun 11/03/24 sáb 30/03/24 70 90 Commissioning for Charger 12 1 día lun 15/04/24 lun 15/04/24 71 91 Physical Site Inspection for Charger 13 1 día lun 05/02/24 lun 05/02/24 1011 92 Civil Works for Charger 13 1 día lun 04/03/24 lun 04/03/24 1012 93 Cement Curing for Charger 13 2 días mar 05/03/24 mié 06/03/24 73 94 Electrical Installation for Charger 13 1 día jue 07/03/24 jue 07/03/24 74 95 Parking Line Painting for Charger 13 1 día lun 11/03/24 lun 11/03/24 75 96 Documentation Post-Installation for Charger 13 15 días mar 12/03/24 dom 31/03/24 76 97 Commissioning for Charger 13 1 día mar 16/04/24 mar 16/04/24 77 98 Physical Site Inspection for Charger 14 1 día mar 06/02/24 mar 06/02/24 1012 99 Civil Works for Charger 14 1 día mar 05/03/24 mar 05/03/24 1013 100 Cement Curing for Charger 14 2 días mié 06/03/24 jue 07/03/24 79 101 Electrical Installation for Charger 14 1 día lun 11/03/24 lun 11/03/24 80 102 Parking Line Painting for Charger 14 1 día mar 12/03/24 mar 12/03/24 81 103 Documentation Post-Installation for Charger 14 14 días mié 13/03/24 lun 01/04/24 82 104 Commissioning for Charger 14 1 día mié 17/04/24 mié 17/04/24 83 105 Physical Site Inspection for Charger 15 1 día mié 07/02/24 mié 07/02/24 1013 106 Civil Works for Charger 15 1 día mié 06/03/24 mié 06/03/24 1014 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 5 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 107 Cement Curing for Charger 15 2 días jue 07/03/24 vie 08/03/24 85 108 Electrical Installation for Charger 15 1 día mar 12/03/24 mar 12/03/24 86 109 Parking Line Painting for Charger 15 1 día mié 13/03/24 mié 13/03/24 87 110 Documentation Post-Installation for Charger 15 14 días jue 14/03/24 mar 02/04/24 88 111 Commissioning for Charger 15 1 día jue 18/04/24 jue 18/04/24 89 112 Physical Site Inspection for Charger 16 1 día jue 08/02/24 jue 08/02/24 1014 113 Civil Works for Charger 16 1 día jue 07/03/24 jue 07/03/24 1015 114 Cement Curing for Charger 16 2 días lun 11/03/24 mar 12/03/24 91 115 Electrical Installation for Charger 16 1 día mié 13/03/24 mié 13/03/24 92 116 Parking Line Painting for Charger 16 1 día jue 14/03/24 jue 14/03/24 93 117 Documentation Post-Installation for Charger 16 16 días lun 18/03/24 sáb 06/04/24 94 118 Commissioning for Charger 16 1 día lun 22/04/24 lun 22/04/24 95 119 Physical Site Inspection for Charger 17 1 día lun 12/02/24 lun 12/02/24 1015 120 Civil Works for Charger 17 1 día lun 11/03/24 lun 11/03/24 1016 121 Cement Curing for Charger 17 2 días mar 12/03/24 mié 13/03/24 97 122 Electrical Installation for Charger 17 1 día jue 14/03/24 jue 14/03/24 98 123 Parking Line Painting for Charger 17 1 día lun 18/03/24 lun 18/03/24 99 124 Documentation Post-Installation for Charger 17 15 días mar 19/03/24 dom 07/04/24 100 125 Commissioning for Charger 17 1 día mar 23/04/24 mar 23/04/24 101 126 Physical Site Inspection for Charger 18 1 día mar 13/02/24 mar 13/02/24 1016 127 Civil Works for Charger 18 1 día mar 12/03/24 mar 12/03/24 1017 128 Cement Curing for Charger 18 2 días mié 13/03/24 jue 14/03/24 103 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 6 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 129 Electrical Installation for Charger 18 1 día lun 18/03/24 lun 18/03/24 104 130 Parking Line Painting for Charger 18 1 día mar 19/03/24 mar 19/03/24 105 131 Documentation Post-Installation for Charger 18 14 días mié 20/03/24 lun 08/04/24 106 132 Commissioning for Charger 18 1 día mié 24/04/24 mié 24/04/24 107 133 Physical Site Inspection for Charger 19 1 día mié 14/02/24 mié 14/02/24 1017 134 Civil Works for Charger 19 1 día mié 13/03/24 mié 13/03/24 1018 135 Cement Curing for Charger 19 2 días jue 14/03/24 vie 15/03/24 109 136 Electrical Installation for Charger 19 1 día mar 19/03/24 mar 19/03/24 110 137 Parking Line Painting for Charger 19 1 día mié 20/03/24 mié 20/03/24 111 138 Documentation Post-Installation for Charger 19 14 días jue 21/03/24 mar 09/04/24 112 139 Commissioning for Charger 19 1 día jue 25/04/24 jue 25/04/24 113 140 Physical Site Inspection for Charger 20 1 día jue 15/02/24 jue 15/02/24 1018 141 Civil Works for Charger 20 1 día jue 14/03/24 jue 14/03/24 1019 142 Cement Curing for Charger 20 2 días lun 18/03/24 mar 19/03/24 115 143 Electrical Installation for Charger 20 1 día mié 20/03/24 mié 20/03/24 116 144 Parking Line Painting for Charger 20 1 día jue 21/03/24 jue 21/03/24 117 145 Documentation Post-Installation for Charger 20 16 días lun 25/03/24 sáb 13/04/24 118 146 Commissioning for Charger 20 1 día lun 29/04/24 lun 29/04/24 119 147 Physical Site Inspection for Charger 21 1 día lun 19/02/24 lun 19/02/24 1019 148 Civil Works for Charger 21 1 día lun 18/03/24 lun 18/03/24 1020 149 Cement Curing for Charger 21 2 días mar 19/03/24 mié 20/03/24 121 150 Electrical Installation for Charger 21 1 día jue 21/03/24 jue 21/03/24 122 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 7 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 151 Parking Line Painting for Charger 21 1 día lun 25/03/24 lun 25/03/24 123 152 Documentation Post-Installation for Charger 21 15 días mar 26/03/24 dom 14/04/24 124 153 Commissioning for Charger 21 1 día mar 30/04/24 mar 30/04/24 125 154 Physical Site Inspection for Charger 22 1 día mar 20/02/24 mar 20/02/24 1020 155 Civil Works for Charger 22 1 día mar 19/03/24 mar 19/03/24 1021 156 Cement Curing for Charger 22 2 días mié 20/03/24 jue 21/03/24 127 157 Electrical Installation for Charger 22 1 día lun 25/03/24 lun 25/03/24 128 158 Parking Line Painting for Charger 22 1 día mar 26/03/24 mar 26/03/24 129 159 Documentation Post-Installation for Charger 22 14 días mié 27/03/24 lun 15/04/24 130 160 Commissioning for Charger 22 1 día mié 01/05/24 mié 01/05/24 131 161 Physical Site Inspection for Charger 23 1 día mié 21/02/24 mié 21/02/24 1021 162 Civil Works for Charger 23 1 día mié 20/03/24 mié 20/03/24 1022 163 Cement Curing for Charger 23 2 días jue 21/03/24 vie 22/03/24 133 164 Electrical Installation for Charger 23 1 día mar 26/03/24 mar 26/03/24 134 165 Parking Line Painting for Charger 23 1 día mié 27/03/24 mié 27/03/24 135 166 Documentation Post-Installation for Charger 23 14 días jue 28/03/24 mar 16/04/24 136 167 Commissioning for Charger 23 1 día jue 02/05/24 jue 02/05/24 137 168 Physical Site Inspection for Charger 24 1 día jue 22/02/24 jue 22/02/24 1022 169 Civil Works for Charger 24 1 día jue 21/03/24 jue 21/03/24 1023 170 Cement Curing for Charger 24 2 días lun 25/03/24 mar 26/03/24 139 171 Electrical Installation for Charger 24 1 día mié 27/03/24 mié 27/03/24 140 172 Parking Line Painting for Charger 24 1 día jue 28/03/24 jue 28/03/24 141 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 8 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 173 Documentation Post-Installation for Charger 24 16 días lun 01/04/24 sáb 20/04/24 142 174 Commissioning for Charger 24 1 día lun 06/05/24 lun 06/05/24 143 175 Physical Site Inspection for Charger 25 1 día lun 26/02/24 lun 26/02/24 1023 176 Civil Works for Charger 25 1 día lun 25/03/24 lun 25/03/24 1024 177 Cement Curing for Charger 25 2 días mar 26/03/24 mié 27/03/24 145 178 Electrical Installation for Charger 25 1 día jue 28/03/24 jue 28/03/24 146 179 Parking Line Painting for Charger 25 1 día lun 01/04/24 lun 01/04/24 147 180 Documentation Post-Installation for Charger 25 15 días mar 02/04/24 dom 21/04/24 148 181 Commissioning for Charger 25 1 día mar 07/05/24 mar 07/05/24 149 182 Physical Site Inspection for Charger 26 1 día mar 27/02/24 mar 27/02/24 1024 183 Civil Works for Charger 26 1 día mar 26/03/24 mar 26/03/24 1025 184 Cement Curing for Charger 26 2 días mié 27/03/24 jue 28/03/24 151 185 Electrical Installation for Charger 26 1 día lun 01/04/24 lun 01/04/24 152 186 Parking Line Painting for Charger 26 1 día mar 02/04/24 mar 02/04/24 153 187 Documentation Post-Installation for Charger 26 14 días mié 03/04/24 lun 22/04/24 154 188 Commissioning for Charger 26 1 día mié 08/05/24 mié 08/05/24 155 189 Physical Site Inspection for Charger 27 1 día mié 28/02/24 mié 28/02/24 1025 190 Civil Works for Charger 27 1 día mié 27/03/24 mié 27/03/24 1026 191 Cement Curing for Charger 27 2 días jue 28/03/24 vie 29/03/24 157 192 Electrical Installation for Charger 27 1 día mar 02/04/24 mar 02/04/24 158 193 Parking Line Painting for Charger 27 1 día mié 03/04/24 mié 03/04/24 159 194 Documentation Post-Installation for Charger 27 14 días jue 04/04/24 mar 23/04/24 160 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 9 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 327 Documentation Post-Installation for Charger 46 14 días mié 08/05/24 lun 27/05/24 274 328 Commissioning for Charger 46 1 día mié 12/06/24 mié 12/06/24 275 329 Physical Site Inspection for Charger 47 1 día mié 03/04/24 mié 03/04/24 1045 330 Civil Works for Charger 47 1 día mié 01/05/24 mié 01/05/24 1046 331 Cement Curing for Charger 47 2 días jue 02/05/24 vie 03/05/24 277 332 Electrical Installation for Charger 47 1 día mar 07/05/24 mar 07/05/24 278 333 Parking Line Painting for Charger 47 1 día mié 08/05/24 mié 08/05/24 279 334 Documentation Post-Installation for Charger 47 14 días jue 09/05/24 mar 28/05/24 280 335 Commissioning for Charger 47 1 día jue 13/06/24 jue 13/06/24 281 336 Physical Site Inspection for Charger 48 1 día jue 04/04/24 jue 04/04/24 1046 337 Civil Works for Charger 48 1 día jue 02/05/24 jue 02/05/24 1047 338 Cement Curing for Charger 48 2 días lun 06/05/24 mar 07/05/24 283 339 Electrical Installation for Charger 48 1 día mié 08/05/24 mié 08/05/24 284 340 Parking Line Painting for Charger 48 1 día jue 09/05/24 jue 09/05/24 285 341 Documentation Post-Installation for Charger 48 16 días lun 13/05/24 sáb 01/06/24 286 342 Commissioning for Charger 48 1 día lun 17/06/24 lun 17/06/24 287 343 Physical Site Inspection for Charger 49 1 día lun 08/04/24 lun 08/04/24 1047 344 Civil Works for Charger 49 1 día lun 06/05/24 lun 06/05/24 1048 345 Cement Curing for Charger 49 2 días mar 07/05/24 mié 08/05/24 289 346 Electrical Installation for Charger 49 1 día jue 09/05/24 jue 09/05/24 290 347 Parking Line Painting for Charger 49 1 día lun 13/05/24 lun 13/05/24 291 348 Documentation Post-Installation for Charger 49 15 días mar 14/05/24 dom 02/06/24 292 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 16 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 349 Commissioning for Charger 49 1 día mar 18/06/24 mar 18/06/24 293 350 Physical Site Inspection for Charger 50 1 día mar 09/04/24 mar 09/04/24 1048 351 Civil Works for Charger 50 1 día mar 07/05/24 mar 07/05/24 1049 352 Cement Curing for Charger 50 2 días mié 08/05/24 jue 09/05/24 295 353 Electrical Installation for Charger 50 1 día lun 13/05/24 lun 13/05/24 296 354 Parking Line Painting for Charger 50 1 día mar 14/05/24 mar 14/05/24 297 355 Documentation Post-Installation for Charger 50 14 días mié 15/05/24 lun 03/06/24 298 356 Commissioning for Charger 50 1 día mié 19/06/24 mié 19/06/24 299 357 Physical Site Inspection for Charger 51 1 día mié 10/04/24 mié 10/04/24 1049 358 Civil Works for Charger 51 1 día mié 08/05/24 mié 08/05/24 1050 359 Cement Curing for Charger 51 2 días jue 09/05/24 vie 10/05/24 301 360 Electrical Installation for Charger 51 1 día mar 14/05/24 mar 14/05/24 302 361 Parking Line Painting for Charger 51 1 día mié 15/05/24 mié 15/05/24 303 362 Documentation Post-Installation for Charger 51 14 días jue 16/05/24 mar 04/06/24 304 363 Commissioning for Charger 51 1 día jue 20/06/24 jue 20/06/24 305 364 Physical Site Inspection for Charger 52 1 día jue 11/04/24 jue 11/04/24 1050 365 Civil Works for Charger 52 1 día jue 09/05/24 jue 09/05/24 1051 366 Cement Curing for Charger 52 2 días lun 13/05/24 mar 14/05/24 307 367 Electrical Installation for Charger 52 1 día mié 15/05/24 mié 15/05/24 308 368 Parking Line Painting for Charger 52 1 día jue 16/05/24 jue 16/05/24 309 369 Documentation Post-Installation for Charger 52 16 días lun 20/05/24 sáb 08/06/24 310 370 Commissioning for Charger 52 1 día lun 24/06/24 lun 24/06/24 311 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 17 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 371 Physical Site Inspection for Charger 53 1 día lun 15/04/24 lun 15/04/24 1051 372 Civil Works for Charger 53 1 día lun 13/05/24 lun 13/05/24 1052 373 Cement Curing for Charger 53 2 días mar 14/05/24 mié 15/05/24 313 374 Electrical Installation for Charger 53 1 día jue 16/05/24 jue 16/05/24 314 375 Parking Line Painting for Charger 53 1 día lun 20/05/24 lun 20/05/24 315 376 Documentation Post-Installation for Charger 53 15 días mar 21/05/24 dom 09/06/24 316 377 Commissioning for Charger 53 1 día mar 25/06/24 mar 25/06/24 317 378 Physical Site Inspection for Charger 54 1 día mar 16/04/24 mar 16/04/24 1052 379 Civil Works for Charger 54 1 día mar 14/05/24 mar 14/05/24 1053 380 Cement Curing for Charger 54 2 días mié 15/05/24 jue 16/05/24 319 381 Electrical Installation for Charger 54 1 día lun 20/05/24 lun 20/05/24 320 382 Parking Line Painting for Charger 54 1 día mar 21/05/24 mar 21/05/24 321 383 Documentation Post-Installation for Charger 54 14 días mié 22/05/24 lun 10/06/24 322 384 Commissioning for Charger 54 1 día mié 26/06/24 mié 26/06/24 323 385 Physical Site Inspection for Charger 55 1 día mié 17/04/24 mié 17/04/24 1053 386 Civil Works for Charger 55 1 día mié 15/05/24 mié 15/05/24 1054 387 Cement Curing for Charger 55 2 días jue 16/05/24 vie 17/05/24 325 388 Electrical Installation for Charger 55 1 día mar 21/05/24 mar 21/05/24 326 389 Parking Line Painting for Charger 55 1 día mié 22/05/24 mié 22/05/24 327 390 Documentation Post-Installation for Charger 55 14 días jue 23/05/24 mar 11/06/24 328 391 Commissioning for Charger 55 1 día jue 27/06/24 jue 27/06/24 329 392 Physical Site Inspection for Charger 56 1 día jue 18/04/24 jue 18/04/24 1054 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 18 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 393 Civil Works for Charger 56 1 día jue 16/05/24 jue 16/05/24 1055 394 Cement Curing for Charger 56 2 días lun 20/05/24 mar 21/05/24 331 395 Electrical Installation for Charger 56 1 día mié 22/05/24 mié 22/05/24 332 396 Parking Line Painting for Charger 56 1 día jue 23/05/24 jue 23/05/24 333 397 Documentation Post-Installation for Charger 56 16 días lun 27/05/24 sáb 15/06/24 334 398 Commissioning for Charger 56 1 día lun 01/07/24 lun 01/07/24 335 399 Physical Site Inspection for Charger 57 1 día lun 22/04/24 lun 22/04/24 1055 400 Civil Works for Charger 57 1 día lun 20/05/24 lun 20/05/24 1056 401 Cement Curing for Charger 57 2 días mar 21/05/24 mié 22/05/24 337 402 Electrical Installation for Charger 57 1 día jue 23/05/24 jue 23/05/24 338 403 Parking Line Painting for Charger 57 1 día lun 27/05/24 lun 27/05/24 339 404 Documentation Post-Installation for Charger 57 15 días mar 28/05/24 dom 16/06/24 340 405 Commissioning for Charger 57 1 día mar 02/07/24 mar 02/07/24 341 406 Physical Site Inspection for Charger 58 1 día mar 23/04/24 mar 23/04/24 1056 407 Civil Works for Charger 58 1 día mar 21/05/24 mar 21/05/24 1057 408 Cement Curing for Charger 58 2 días mié 22/05/24 jue 23/05/24 343 409 Electrical Installation for Charger 58 1 día lun 27/05/24 lun 27/05/24 344 410 Parking Line Painting for Charger 58 1 día mar 28/05/24 mar 28/05/24 345 411 Documentation Post-Installation for Charger 58 14 días mié 29/05/24 lun 17/06/24 346 412 Commissioning for Charger 58 1 día mié 03/07/24 mié 03/07/24 347 413 Physical Site Inspection for Charger 59 1 día mié 24/04/24 mié 24/04/24 1057 414 Civil Works for Charger 59 1 día mié 22/05/24 mié 22/05/24 1058 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 19 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 415 Cement Curing for Charger 59 2 días jue 23/05/24 vie 24/05/24 349 416 Electrical Installation for Charger 59 1 día mar 28/05/24 mar 28/05/24 350 417 Parking Line Painting for Charger 59 1 día mié 29/05/24 mié 29/05/24 351 418 Documentation Post-Installation for Charger 59 14 días jue 30/05/24 mar 18/06/24 352 419 Commissioning for Charger 59 1 día jue 04/07/24 jue 04/07/24 353 420 Physical Site Inspection for Charger 60 1 día jue 25/04/24 jue 25/04/24 1058 421 Civil Works for Charger 60 1 día jue 23/05/24 jue 23/05/24 1059 422 Cement Curing for Charger 60 2 días lun 27/05/24 mar 28/05/24 355 423 Electrical Installation for Charger 60 1 día mié 29/05/24 mié 29/05/24 356 424 Parking Line Painting for Charger 60 1 día jue 30/05/24 jue 30/05/24 357 425 Documentation Post-Installation for Charger 60 16 días lun 03/06/24 sáb 22/06/24 358 426 Commissioning for Charger 60 1 día lun 08/07/24 lun 08/07/24 359 427 Physical Site Inspection for Charger 61 1 día lun 29/04/24 lun 29/04/24 1059 428 Civil Works for Charger 61 1 día lun 27/05/24 lun 27/05/24 1060 429 Cement Curing for Charger 61 2 días mar 28/05/24 mié 29/05/24 361 430 Electrical Installation for Charger 61 1 día jue 30/05/24 jue 30/05/24 362 431 Parking Line Painting for Charger 61 1 día lun 03/06/24 lun 03/06/24 363 432 Documentation Post-Installation for Charger 61 15 días mar 04/06/24 dom 23/06/24 364 433 Commissioning for Charger 61 1 día mar 09/07/24 mar 09/07/24 365 434 Physical Site Inspection for Charger 62 1 día mar 30/04/24 mar 30/04/24 1060 435 Civil Works for Charger 62 1 día mar 28/05/24 mar 28/05/24 1061 436 Cement Curing for Charger 62 2 días mié 29/05/24 jue 30/05/24 367 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 20 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 437 Electrical Installation for Charger 62 1 día lun 03/06/24 lun 03/06/24 368 438 Parking Line Painting for Charger 62 1 día mar 04/06/24 mar 04/06/24 369 439 Documentation Post-Installation for Charger 62 14 días mié 05/06/24 lun 24/06/24 370 440 Commissioning for Charger 62 1 día mié 10/07/24 mié 10/07/24 371 441 Physical Site Inspection for Charger 63 1 día mié 01/05/24 mié 01/05/24 1061 442 Civil Works for Charger 63 1 día mié 29/05/24 mié 29/05/24 1062 443 Cement Curing for Charger 63 2 días jue 30/05/24 vie 31/05/24 373 444 Electrical Installation for Charger 63 1 día mar 04/06/24 mar 04/06/24 374 445 Parking Line Painting for Charger 63 1 día mié 05/06/24 mié 05/06/24 375 446 Documentation Post-Installation for Charger 63 14 días jue 06/06/24 mar 25/06/24 376 447 Commissioning for Charger 63 1 día jue 11/07/24 jue 11/07/24 377 448 Physical Site Inspection for Charger 64 1 día jue 02/05/24 jue 02/05/24 1062 449 Civil Works for Charger 64 1 día jue 30/05/24 jue 30/05/24 1063 450 Cement Curing for Charger 64 2 días lun 03/06/24 mar 04/06/24 379 451 Electrical Installation for Charger 64 1 día mié 05/06/24 mié 05/06/24 380 452 Parking Line Painting for Charger 64 1 día jue 06/06/24 jue 06/06/24 381 453 Documentation Post-Installation for Charger 64 16 días lun 10/06/24 sáb 29/06/24 382 454 Commissioning for Charger 64 1 día lun 15/07/24 lun 15/07/24 383 455 Physical Site Inspection for Charger 65 1 día lun 06/05/24 lun 06/05/24 1063 456 Civil Works for Charger 65 1 día lun 03/06/24 lun 03/06/24 1064 457 Cement Curing for Charger 65 2 días mar 04/06/24 mié 05/06/24 385 458 Electrical Installation for Charger 65 1 día jue 06/06/24 jue 06/06/24 386 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 21 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 459 Parking Line Painting for Charger 65 1 día lun 10/06/24 lun 10/06/24 387 460 Documentation Post-Installation for Charger 65 15 días mar 11/06/24 dom 30/06/24 388 461 Commissioning for Charger 65 1 día mar 16/07/24 mar 16/07/24 389 462 Physical Site Inspection for Charger 66 1 día mar 07/05/24 mar 07/05/24 1064 463 Civil Works for Charger 66 1 día mar 04/06/24 mar 04/06/24 1065 464 Cement Curing for Charger 66 2 días mié 05/06/24 jue 06/06/24 391 465 Electrical Installation for Charger 66 1 día lun 10/06/24 lun 10/06/24 392 466 Parking Line Painting for Charger 66 1 día mar 11/06/24 mar 11/06/24 393 467 Documentation Post-Installation for Charger 66 14 días mié 12/06/24 lun 01/07/24 394 468 Commissioning for Charger 66 1 día mié 17/07/24 mié 17/07/24 395 469 Physical Site Inspection for Charger 67 1 día mié 08/05/24 mié 08/05/24 1065 470 Civil Works for Charger 67 1 día mié 05/06/24 mié 05/06/24 1066 471 Cement Curing for Charger 67 2 días jue 06/06/24 vie 07/06/24 397 472 Electrical Installation for Charger 67 1 día mar 11/06/24 mar 11/06/24 398 473 Parking Line Painting for Charger 67 1 día mié 12/06/24 mié 12/06/24 399 474 Documentation Post-Installation for Charger 67 14 días jue 13/06/24 mar 02/07/24 400 475 Commissioning for Charger 67 1 día jue 18/07/24 jue 18/07/24 401 476 Physical Site Inspection for Charger 68 1 día jue 09/05/24 jue 09/05/24 1066 477 Civil Works for Charger 68 1 día jue 06/06/24 jue 06/06/24 1067 478 Cement Curing for Charger 68 2 días lun 10/06/24 mar 11/06/24 403 479 Electrical Installation for Charger 68 1 día mié 12/06/24 mié 12/06/24 404 480 Parking Line Painting for Charger 68 1 día jue 13/06/24 jue 13/06/24 405 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 22 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 481 Documentation Post-Installation for Charger 68 16 días lun 17/06/24 sáb 06/07/24 406 482 Commissioning for Charger 68 1 día lun 22/07/24 lun 22/07/24 407 483 Physical Site Inspection for Charger 69 1 día lun 13/05/24 lun 13/05/24 1067 484 Civil Works for Charger 69 1 día lun 10/06/24 lun 10/06/24 1068 485 Cement Curing for Charger 69 2 días mar 11/06/24 mié 12/06/24 409 486 Electrical Installation for Charger 69 1 día jue 13/06/24 jue 13/06/24 410 487 Parking Line Painting for Charger 69 1 día lun 17/06/24 lun 17/06/24 411 488 Documentation Post-Installation for Charger 69 15 días mar 18/06/24 dom 07/07/24 412 489 Commissioning for Charger 69 1 día mar 23/07/24 mar 23/07/24 413 490 Physical Site Inspection for Charger 70 1 día mar 14/05/24 mar 14/05/24 1068 491 Civil Works for Charger 70 1 día mar 11/06/24 mar 11/06/24 1069 492 Cement Curing for Charger 70 2 días mié 12/06/24 jue 13/06/24 415 493 Electrical Installation for Charger 70 1 día lun 17/06/24 lun 17/06/24 416 494 Parking Line Painting for Charger 70 1 día mar 18/06/24 mar 18/06/24 417 495 Documentation Post-Installation for Charger 70 14 días mié 19/06/24 lun 08/07/24 418 496 Commissioning for Charger 70 1 día mié 24/07/24 mié 24/07/24 419 497 Physical Site Inspection for Charger 71 1 día mié 15/05/24 mié 15/05/24 1069 498 Civil Works for Charger 71 1 día mié 12/06/24 mié 12/06/24 1070 499 Cement Curing for Charger 71 2 días jue 13/06/24 vie 14/06/24 421 500 Electrical Installation for Charger 71 1 día mar 18/06/24 mar 18/06/24 422 501 Parking Line Painting for Charger 71 1 día mié 19/06/24 mié 19/06/24 423 502 Documentation Post-Installation for Charger 71 14 días jue 20/06/24 mar 09/07/24 424 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 23 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 503 Commissioning for Charger 71 1 día jue 25/07/24 jue 25/07/24 425 504 Physical Site Inspection for Charger 72 1 día jue 16/05/24 jue 16/05/24 1070 505 Civil Works for Charger 72 1 día jue 13/06/24 jue 13/06/24 1071 506 Cement Curing for Charger 72 2 días lun 17/06/24 mar 18/06/24 427 507 Electrical Installation for Charger 72 1 día mié 19/06/24 mié 19/06/24 428 508 Parking Line Painting for Charger 72 1 día jue 20/06/24 jue 20/06/24 429 509 Documentation Post-Installation for Charger 72 16 días lun 24/06/24 sáb 13/07/24 430 510 Commissioning for Charger 72 1 día lun 29/07/24 lun 29/07/24 431 511 Physical Site Inspection for Charger 73 1 día lun 20/05/24 lun 20/05/24 1071 512 Civil Works for Charger 73 1 día lun 17/06/24 lun 17/06/24 1072 513 Cement Curing for Charger 73 2 días mar 18/06/24 mié 19/06/24 433 514 Electrical Installation for Charger 73 1 día jue 20/06/24 jue 20/06/24 434 515 Parking Line Painting for Charger 73 1 día lun 24/06/24 lun 24/06/24 435 516 Documentation Post-Installation for Charger 73 15 días mar 25/06/24 dom 14/07/24 436 517 Commissioning for Charger 73 1 día mar 30/07/24 mar 30/07/24 437 518 Physical Site Inspection for Charger 74 1 día mar 21/05/24 mar 21/05/24 1072 519 Civil Works for Charger 74 1 día mar 18/06/24 mar 18/06/24 1073 520 Cement Curing for Charger 74 2 días mié 19/06/24 jue 20/06/24 439 521 Electrical Installation for Charger 74 1 día lun 24/06/24 lun 24/06/24 440 522 Parking Line Painting for Charger 74 1 día mar 25/06/24 mar 25/06/24 441 523 Documentation Post-Installation for Charger 74 14 días mié 26/06/24 lun 15/07/24 442 524 Commissioning for Charger 74 1 día mié 31/07/24 mié 31/07/24 443 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 24 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 525 Physical Site Inspection for Charger 75 1 día mié 22/05/24 mié 22/05/24 1073 526 Civil Works for Charger 75 1 día mié 19/06/24 mié 19/06/24 1074 527 Cement Curing for Charger 75 2 días jue 20/06/24 vie 21/06/24 445 528 Electrical Installation for Charger 75 1 día mar 25/06/24 mar 25/06/24 446 529 Parking Line Painting for Charger 75 1 día mié 26/06/24 mié 26/06/24 447 530 Documentation Post-Installation for Charger 75 14 días jue 27/06/24 mar 16/07/24 448 531 Commissioning for Charger 75 1 día jue 01/08/24 jue 01/08/24 449 532 Physical Site Inspection for Charger 76 1 día jue 23/05/24 jue 23/05/24 1074 533 Civil Works for Charger 76 1 día jue 20/06/24 jue 20/06/24 1075 534 Cement Curing for Charger 76 2 días lun 24/06/24 mar 25/06/24 451 535 Electrical Installation for Charger 76 1 día mié 26/06/24 mié 26/06/24 452 536 Parking Line Painting for Charger 76 1 día jue 27/06/24 jue 27/06/24 453 537 Documentation Post-Installation for Charger 76 16 días lun 01/07/24 sáb 20/07/24 454 538 Commissioning for Charger 76 1 día lun 05/08/24 lun 05/08/24 455 539 Physical Site Inspection for Charger 77 1 día lun 27/05/24 lun 27/05/24 1075 540 Civil Works for Charger 77 1 día lun 24/06/24 lun 24/06/24 1076 541 Cement Curing for Charger 77 2 días mar 25/06/24 mié 26/06/24 457 542 Electrical Installation for Charger 77 1 día jue 27/06/24 jue 27/06/24 458 543 Parking Line Painting for Charger 77 1 día lun 01/07/24 lun 01/07/24 459 544 Documentation Post-Installation for Charger 77 15 días mar 02/07/24 dom 21/07/24 460 545 Commissioning for Charger 77 1 día mar 06/08/24 mar 06/08/24 461 546 Physical Site Inspection for Charger 78 1 día mar 28/05/24 mar 28/05/24 1076 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 25 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 679 Physical Site Inspection for Charger 97 1 día lun 01/07/24 lun 01/07/24 1095 680 Civil Works for Charger 97 1 día lun 29/07/24 lun 29/07/24 1096 681 Cement Curing for Charger 97 2 días mar 30/07/24 mié 31/07/24 577 682 Electrical Installation for Charger 97 1 día jue 01/08/24 jue 01/08/24 578 683 Parking Line Painting for Charger 97 1 día lun 05/08/24 lun 05/08/24 579 684 Documentation Post-Installation for Charger 97 15 días mar 06/08/24 dom 25/08/24 580 685 Commissioning for Charger 97 1 día mar 10/09/24 mar 10/09/24 581 686 Physical Site Inspection for Charger 98 1 día mar 02/07/24 mar 02/07/24 1096 687 Civil Works for Charger 98 1 día mar 30/07/24 mar 30/07/24 1097 688 Cement Curing for Charger 98 2 días mié 31/07/24 jue 01/08/24 583 689 Electrical Installation for Charger 98 1 día lun 05/08/24 lun 05/08/24 584 690 Parking Line Painting for Charger 98 1 día mar 06/08/24 mar 06/08/24 585 691 Documentation Post-Installation for Charger 98 14 días mié 07/08/24 lun 26/08/24 586 692 Commissioning for Charger 98 1 día mié 11/09/24 mié 11/09/24 587 693 Physical Site Inspection for Charger 99 1 día mié 03/07/24 mié 03/07/24 1097 694 Civil Works for Charger 99 1 día mié 31/07/24 mié 31/07/24 1098 695 Cement Curing for Charger 99 2 días jue 01/08/24 vie 02/08/24 589 696 Electrical Installation for Charger 99 1 día mar 06/08/24 mar 06/08/24 590 697 Parking Line Painting for Charger 99 1 día mié 07/08/24 mié 07/08/24 591 698 Documentation Post-Installation for Charger 99 14 días jue 08/08/24 mar 27/08/24 592 699 Commissioning for Charger 99 1 día jue 12/09/24 jue 12/09/24 593 700 Physical Site Inspection for Charger 100 1 día jue 04/07/24 jue 04/07/24 1098 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 32 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 701 Civil Works for Charger 100 1 día jue 01/08/24 jue 01/08/24 1099 702 Cement Curing for Charger 100 2 días lun 05/08/24 mar 06/08/24 595 703 Electrical Installation for Charger 100 1 día mié 07/08/24 mié 07/08/24 596 704 Parking Line Painting for Charger 100 1 día jue 08/08/24 jue 08/08/24 597 705 Documentation Post-Installation for Charger 100 16 días lun 12/08/24 sáb 31/08/24 598 706 Commissioning for Charger 100 1 día lun 16/09/24 lun 16/09/24 599 707 708 709 710 711 712 713 714 715 716 717 718 719 720 721 722 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 33 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 723 724 725 726 727 728 729 730 731 732 733 734 735 736 737 738 739 740 741 742 743 744 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 34 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 745 746 747 748 749 750 751 752 753 754 755 756 757 758 759 760 761 762 763 764 765 766 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 35 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 767 768 769 770 771 772 773 774 775 776 777 778 779 780 781 782 783 784 785 786 787 788 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 36 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 789 790 791 792 793 794 795 796 797 798 799 800 801 802 803 804 805 806 807 808 809 810 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 37 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 811 812 813 814 815 816 817 818 819 820 821 822 823 824 825 826 827 828 829 830 831 832 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 38 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 833 834 835 836 837 838 839 840 841 842 843 844 845 846 847 848 849 850 851 852 853 854 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 39 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 855 856 857 858 859 860 861 862 863 864 865 866 867 868 869 870 871 872 873 874 875 876 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 40 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 877 878 879 880 881 882 883 884 885 886 887 888 889 890 891 892 893 894 895 896 897 898 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 41 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 1031 1032 1033 1034 1035 1036 1037 1038 1039 1040 1041 1042 1043 1044 1045 1046 1047 1048 1049 1050 1051 1052 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 48 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 1053 1054 1055 1056 1057 1058 1059 1060 1061 1062 1063 1064 1065 1066 1067 1068 1069 1070 1071 1072 1073 1074 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 49 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 1075 1076 1077 1078 1079 1080 1081 1082 1083 1084 1085 1086 1087 1088 1089 1090 1091 1092 1093 1094 1095 1096 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 50 Proyecto: Cronograma Fecha: jue 13/06/24
Id Modo de tarea Nombre de tarea Duración Comienzo Fin Predecesoras Nombres de los recursos 1097 1098 1099 D L M X J V S D L M X J V 08 ene '24 15 ene '24 22 ene '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 51 Proyecto: Cronograma Fecha: jue 13/06/24
14/02 14/02 V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 52 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 53 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 54 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 55 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 56 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 57 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 64 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 65 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 66 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 67 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 68 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 69 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 70 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 71 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 72 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 73 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 80 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 81 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 82 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 83 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 84 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 85 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 86 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 87 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 88 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 89 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 96 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 97 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 98 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 99 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 100 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 101 Proyecto: Cronograma Fecha: jue 13/06/24
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J 22 ene '24 29 ene '24 05 feb '24 12 feb '24 19 feb '24 26 feb '24 04 mar '24 11 mar '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 102 Proyecto: Cronograma Fecha: jue 13/06/24
14/02 14/02 J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 103 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 104 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 105 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 112 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 113 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 114 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 115 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 116 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 117 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 118 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 119 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 120 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 121 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 128 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 129 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 130 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 131 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 132 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 133 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 134 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 135 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 136 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 137 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 144 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 145 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 146 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 147 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 148 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 149 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 150 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 151 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 152 Proyecto: Cronograma Fecha: jue 13/06/24
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X 11 mar '24 18 mar '24 25 mar '24 01 abr '24 08 abr '24 15 abr '24 22 abr '24 29 abr '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 153 Proyecto: Cronograma Fecha: jue 13/06/24
19/06 16/09 17/09 L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 256 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 257 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 258 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 259 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 260 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 261 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 262 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 263 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 264 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 265 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 272 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 273 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 274 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 275 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 276 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 277 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 278 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 279 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 280 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 281 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 288 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 289 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 290 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 291 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 292 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 293 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 294 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 295 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 296 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 297 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 304 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 305 Proyecto: Cronograma Fecha: jue 13/06/24
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D 05 ago '24 12 ago '24 19 ago '24 26 ago '24 02 sep '24 09 sep '24 16 sep '24 Tarea División Hito Resumen Resumen del proyecto Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Tareas externas Hito externo Fecha límite Progreso Progreso manual Página 306 Proyecto: Cronograma Fecha: jue 13/06/24